Bonding & Grounding Infrastructure

Key Takeaways

  • Bonding connects conductive parts to limit potential differences. Grounding connects the relevant system to the building’s grounding system.

  • The primary bonding busbar (PBB) is the primary ICT connection point, and secondary bonding busbars (SBBs) provide local connection points.

  • The telecommunications bonding backbone (TBB) links busbars. The backbone bonding conductor (BBC) interconnects TBBs where required.

  • The telecommunications bonding conductor (TBC) connects the telecommunications bonding infrastructure to the building grounding system.

  • Apply the sizing and topology rules for each conductor’s function, route and governing edition.

Last updated: November 2026

Bonding and Grounding Functions

Bonding intentionally joins conductive parts to limit potential differences and provide the required electrical path. The telecommunications bonding infrastructure connects to the building grounding system under the applicable electrical code. Coordinate the connection with the electrical designer. An isolated ground for ICT equipment can introduce unintended differences in potential.

Telecommunications Bonding Components

Current termOlder termFunction
Primary bonding busbar (PBB)Telecommunications main grounding busbar (TMGB)Primary connection point for the telecommunications bonding infrastructure
Secondary bonding busbar (SBB)Telecommunications grounding busbar (TGB)Local connection point for specified bonds within a telecommunications space
Telecommunications bonding backbone (TBB)TBBBackbone bonding path between telecommunications spaces
Backbone bonding conductor (BBC)Grounding equalizer (GE)Interconnects multiple bonding backbones where required
Telecommunications bonding conductor (TBC)Bonding conductor for telecommunications (BCT)Bonds the telecommunications infrastructure to the building grounding system

Draw the full path from racks and other applicable conductive equipment to the space’s busbar, then through the designed bonding network to the building grounding system. Show busbar locations, conductor routes and termination details. Older documents can use legacy labels. Use current nomenclature and identify legacy equivalents when documenting an existing installation. UFC bonding terminology and examples

Size and Route the Conductors

Identify each conductor’s function before selecting its size. The backbone route length and required topology affect the TBB design. Apply the relevant sizing and routing provisions separately for the TBC, BBC, rack and equipment connections, and electrical grounding conductors. Verify conductor paths, access and coordination with the applicable electrical code. TIA-607-E publication notice

Worked Example — Review a Remote Telecommunications Room

A renovation adds a room with two cabinets, a metallic tray and a longer run back to an existing primary bonding busbar. Locate the secondary busbar where the installer can reach its connections. Identify which cabinets, pathways and other conductive elements require bonding, then draw the path from those connections through the telecommunications bonding infrastructure to the building grounding system. Verify conductor sizing and protection for the longer route with the applicable standard. If the cabinet lineup changes, revisit access and conductor routing before assembly.

During review, confirm that the new links can be traced and inspected and that the drawings and specifications use the same terminology. If the existing record shows a TGB, identify its current equivalent and verify its condition and capacity before planning reuse.

Test Your Knowledge

Which busbar is the primary bonding point for the telecommunications infrastructure?

A

Secondary bonding busbar (SBB)

B

Telecommunications bonding backbone (TBB)

C

Primary bonding busbar (PBB)

D

Telecommunications bonding conductor (TBC)

Test Your Knowledge

What component interconnects separate telecommunications bonding backbones where the design requires it?

A

Rack bonding busbar

B

Backbone bonding conductor

C

Work-area equipment cord

D

Service grounding electrode

Test Your Knowledge

What should govern selection of a telecommunications bonding conductor?

A

Conductor function and the applicable sizing rules

B

A single size shared by every bonding conductor

C

Only the current carried by active network ports

D

The nominal voltage rated on the patch panel