11.7 Masonry Reinforcement, Grouting & Wall Systems

Key Takeaways

  • Grout is a fluid mixture placed to bond reinforcement to masonry units; it is proportioned for high slump (8 to 11 inches) and is not the same material as mortar
  • Fine grout is used in narrow cells and thin joints; coarse grout containing pea gravel is used where the space is large enough to accept it
  • High-lift grouting above about 5 feet requires cleanout openings at the base of each grouted cell so debris can be removed and steel inspected
  • Bond beams are horizontal grouted courses containing continuous reinforcement, used at floor and roof lines, above openings, and at wall tops
  • Hot-weather masonry practice — wetting units where required, shading materials, and protecting fresh work — governs most Arizona placements
Last updated: August 2026

Reinforced Masonry Is a Different Trade From Mortar Work

Quick Answer: In reinforced concrete masonry, the block and mortar form a set of vertical cells and horizontal bond beams that are filled with grout around reinforcing steel. Grout is not mortar: it is proportioned to be fluid — commonly an 8 to 11 inch slump — so it flows around bars and fills every void.

Section 11.3 covered units, mortar types, and laying practice. This section covers what turns a stacked wall into a structural element. On the commercial trade exam, masonry questions run heavily toward reinforcement placement, grouting procedure, and inspection — the things a general building contractor supervises rather than performs.

Mortar Versus Grout

MortarGrout
PurposeBonds units together; fills the jointsBonds reinforcement to the masonry; fills cells and bond beams
ConsistencyStiff, workable, retains its shape on a trowelFluid, self-consolidating in placement
Slump~ 2½ inches (measured by cone penetration in practice)8 to 11 inches
AggregateSand onlySand (fine grout) or sand plus pea gravel (coarse grout)
Placed byMason with a trowelPump, bucket, or chute into cells

Grout is intentionally wet. The high water content that would ruin concrete is correct here, because the dry masonry units absorb excess water from the grout almost immediately, dropping the effective water-cement ratio after placement. A stiff grout that will not flow leaves voids around the steel, which is the failure the inspection process exists to catch.

Grout typeUse
Fine groutNarrow cells, small clearances, thin collar joints
Coarse groutLarger cells with adequate clear dimension to pass pea gravel

Choose by the smallest clear dimension the grout must pass through, including around reinforcing bars.

Reinforcement Placement

Vertical steel sits in cells and is held in position by positioners or by tying to dowels projecting from the foundation. Two requirements decide whether it works:

  • Position. Bars must be centered in the cell (or at the specified location) and remain there during grouting. A bar leaning against the block face has no grout cover and is not doing what the engineer designed.
  • Lap splices. Bars are lapped the specified length, which is stated on the structural drawings and depends on bar size, grout strength, and cover. Field crews should never eyeball a lap.

Horizontal steel comes in two forms:

FormWhere
Joint reinforcement (ladder or truss wire)Bedded in the mortar joint at specified vertical intervals — commonly every 16 inches
Bond beam reinforcementContinuous bars in a grouted bond-beam course

Bond beams are horizontal courses formed with bond-beam or lintel block, reinforced and grouted continuously. They appear at floor and roof bearing lines, at the top of walls, above openings, and at intervals set by the structural drawings. They tie the wall together, distribute concentrated loads, and are essential to the wall's out-of-plane and seismic performance. Where a bond beam sits over a cell that is not to be grouted, the bottom is closed off — with metal lath or a plate — so grout stays in the beam rather than running down the wall.

Low-Lift and High-Lift Grouting

The wall cannot be grouted to full height in one pour without either blowing the wall apart or leaving voids. Two procedures exist:

Low-lift groutingHigh-lift grouting
ProcedureLay a limited height of wall, then grout, then continueLay the wall to full story height, then grout in lifts
Typical liftRoughly 4 to 5 feet at a timeGrout placed in lifts within a taller pour, consolidated between lifts
CleanoutsGenerally not requiredRequired at the base of every grouted cell
AdvantageSimple; no cleanout patchingFaster; fewer interruptions to the masons

Cleanout openings are the detail the exam tests. When the grout pour height exceeds roughly 5 feet, an opening at least about 3 inches across is left at the bottom of each cell to be grouted. Their purpose is twofold: mortar droppings and debris are removed through them, and the inspector verifies reinforcement position and lap length before the cells are closed and grouted. They are then sealed to resist the grout pressure.

Consolidation. Grout must be consolidated — mechanically vibrated — and then reconsolidated after initial water loss so that the settlement shrinkage does not leave a void at the top of the lift. Skipping reconsolidation is a common source of hollow bond beams.

Hot-Weather Masonry — the Arizona Default

Most Arizona masonry is placed in hot-weather conditions, and the governing concern is that mortar and grout lose water to evaporation and to the units faster than hydration can use it.

ConditionPractice
Rising ambient temperatureShade sand and mixing water; use cool mixing water
High temperature and windReduce the time mortar sits before use; retemper only within the allowed window; work in shorter runs
Units hot to the touchShade unit stockpiles; do not wet concrete masonry units, which are laid dry — this is opposite to clay brick with high absorption, which may require wetting
Fresh work exposedFog and cover completed work; protect from direct sun and wind

That third row is a classic exam discriminator. Clay brick with a high initial rate of absorption may need to be wetted before laying so it does not pull water out of the mortar. Concrete masonry units are laid dry — wetting CMU adds water the unit will later give up as shrinkage, producing cracking.

Warning: in monsoon season the opposite risk appears. Freshly laid masonry must be covered at the end of each day, because a downpour on green work washes out joints and leaches efflorescence-forming salts to the surface.

Test Your Knowledge

What distinguishes grout from mortar in reinforced masonry construction?

A
B
C
D
Test Your Knowledge

A mason plans to grout a CMU wall in a single pour approximately 8 feet high. What does the procedure require?

A
B
C
D
Test Your Knowledge

Why is grout reconsolidated after initial placement?

A
B
C
D
Test Your Knowledge

In hot Arizona conditions, how should concrete masonry units and high-absorption clay brick be handled before laying?

A
B
C
D