12.6 Structural Steel Erection & Connections

Key Takeaways

  • Wide-flange shapes are designated by nominal depth and weight per foot, as in W12x26, and ASTM A992 is the standard grade for structural wide-flange members
  • Bolted connections are either snug-tightened bearing joints or pretensioned/slip-critical joints, and only the latter require a verified installation method
  • Turn-of-nut, calibrated wrench, twist-off tension-control bolts, and direct-tension-indicator washers are the four accepted pretensioning methods
  • A welding symbol places field-side information below the reference line and other-side information above it, with a flag denoting a field weld
  • OSHA 29 CFR 1926 subpart R requires the controlling contractor to certify the concrete's adequacy before steel erection begins, and columns to be anchored with at least four anchor rods
Last updated: August 2026

Why Metals Is the Second-Heaviest Area

Quick Answer: Metals is 13 of 100 items on the AZ ROC B-1/B-2/KB-1/KB-2 outline — more than Carpentry, more than Safety, second only to Concrete. Questions cluster around shapes and grades, bolted connection types, welding fundamentals, and erection safety.

A general building contractor rarely swings the iron, but the general contractor is the controlling contractor under OSHA's steel erection rules, which places specific, non-delegable duties on them before the first column goes up. That combination — technical knowledge plus a regulatory role — is why the area carries so much weight.

Shapes, Grades, and Designations

DesignationShapeReading it
W12x26Wide flangeNominal 12 in. deep, 26 lb per linear foot
HSS6x6x1/4Hollow structural section6 x 6 in. square tube, ¼ in. wall
C10x15.3American standard channel10 in. deep, 15.3 lb/ft
L4x4x1/2Angle4 x 4 in. legs, ½ in. thick
WTStructural teeCut from a W shape
PLPlateThickness x width x length

The number after the "x" in a W shape is weight per foot, not a dimension — a W12x26 and a W12x40 are the same nominal depth with very different flange thickness and capacity. Substituting one for the other because "they're both W12s" is a real field error.

GradeWhere used
ASTM A992Standard for structural wide-flange shapes, 50 ksi yield
ASTM A36Plates, angles, and miscellaneous steel, 36 ksi yield
ASTM A500HSS tube and pipe
ASTM A325 / F3125 Gr. A325Structural bolts, medium strength
ASTM A490 / F3125 Gr. A490Structural bolts, high strength

Mill certifications tie each delivered piece back to its grade. On a commercial job the general contractor collects them as part of the submittal and closeout record.

Bolted Connections

Nearly all field connections are bolted; welding is mostly shop work. The exam distinction that matters is the joint type, because it determines the installation method and the inspection.

Joint typeHow it carries loadInstallation
Snug-tightened bearing jointBolt bears against the hole; plies may slip into bearingBolts brought to snug tight — the full effort of an ironworker with a spud wrench, or a few impacts of an impact wrench
Pretensioned jointBolt is tensioned to a specified minimumRequires a verified pretensioning method
Slip-critical jointFriction between faying surfaces prevents any slipPretensioned and faying surfaces prepared to a specified class

Most connections in a typical building are snug-tightened, and over-tightening them is not "extra safety" — it is a deviation from the specification. Pretensioned and slip-critical joints appear where slip cannot be tolerated: connections subject to load reversal, fatigue, or oversized and slotted holes.

The Four Pretensioning Methods

MethodHow it works
Turn-of-nutFrom snug tight, rotate the nut a specified additional amount based on bolt length and diameter
Calibrated wrenchTorque wrench calibrated daily against a tension-measuring device
Twist-off tension-control boltsThe splined end shears off at the required tension
Direct-tension-indicator washersProtrusions flatten to a measurable gap at the required tension

Hole types matter too: standard round, oversize, short-slotted, and long-slotted holes each carry rules about washers and about which joint types may use them. Never enlarge a hole with a torch — flame cutting a bolt hole is prohibited unless specifically permitted and is a classic field violation.

Welding Fundamentals

ProcessCommon nameTypical use
SMAWStickField welding, wind-tolerant
GMAWMIGShop, high deposition
FCAWFlux-coredField structural welding
SAWSubmerged arcShop, long automated welds

Weld types. A fillet weld joins members at an angle and is described by its leg size; a groove weld fills a prepared joint between members and may be complete- or partial-penetration.

Reading a welding symbol. The rules are positional and are worth memorizing because they turn up as an exam item:

  • Information below the reference line applies to the arrow side of the joint.
  • Information above the reference line applies to the other side.
  • A flag at the kink means a field weld.
  • A circle at the kink means weld all around.
  • The number to the left of the symbol is the weld size; numbers to the right are length and pitch.

Quality. Structural welding follows AWS D1.1, and welders qualify to specific procedures. Inspection ranges from visual inspection to ultrasonic testing on complete-penetration welds. Common defects — undercut, porosity, incomplete fusion, slag inclusions, and cracks — are all rejectable and traceable to the procedure or the welder rather than the design.

Erection Safety: OSHA Subpart R

29 CFR 1926 Subpart R governs steel erection and places specific duties on the controlling contractor — normally the general contractor:

RequirementDetail
Concrete strength certificationThe controlling contractor must provide written notification that concrete in footings, piers, and walls has attained either 75% of specified compressive strength or sufficient strength to support loads, before steel erection begins
Adequate accessFirm, properly graded, drained access roads and a work area for hoisting equipment
Column anchorageColumns anchored with a minimum of four anchor rods, designed to resist a specified eccentric load
Repair or modification of anchor rodsNot permitted without the approval of the project structural engineer of record
Double connectionsAt columns and beam webs over a column, a means must be provided so the first member remains supported when the second is being connected
Fall protectionGenerally required for connectors and in controlled decking zones per the subpart's specific triggers
Perimeter safety cablesRequired at the perimeter of multi-story structures

That first row is the one general contractors most often miss. Steel erection may not begin on a written promise or a phone call — the subpart requires written notification that the supporting concrete has reached the required strength, and it is the controlling contractor who issues it.

Warning: anchor rods set out of tolerance are a routine problem, and the fix is not a field decision. Repairing, replacing, or field-modifying anchor rods requires the approval of the structural engineer of record.

Test Your Knowledge

A connection detail specifies ASTM A992 steel. Where is that grade normally used?

A
B
C
D
Test Your Knowledge

A connection detail calls for a slip-critical joint. What does that require beyond a snug-tightened installation?

A
B
C
D
Test Your Knowledge

On a welding symbol, what does information placed below the reference line indicate?

A
B
C
D
Test Your Knowledge

Under OSHA 29 CFR 1926 subpart R, what must the controlling contractor provide before steel erection begins?

A
B
C
D