All Practice Exams

100+ Free Arizona ROC CR-8 Floor Covering Practice Questions

Prepare for the Arizona ROC CR-8 Floor Covering Examination exam with instant access — no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
100+ Questions
100% Free

Loading practice questions...

2026 Statistics

Key Facts: Arizona ROC CR-8 Floor Covering Exam

80

Official Scored Questions

PSI Arizona ROC CR-8 Bulletin

150 Minutes

Time Limit

PSI Content Outline

70%

Passing Score

Arizona Registrar of Contractors

$66

Exam Fee

PSI Services LLC

Open-Book Computerized

Format

PSI Services LLC

4 Years

Trade Experience Requirement

Arizona Registrar of Contractors

Pass the Arizona ROC CR-8 Floor Covering exam with 100 verified practice questions covering concrete RH testing (ASTM F2170), calcium chloride MVER (ASTM F1869), NWFA solid/engineered wood fastening, CRI power stretching, LVT adhesive open times, and OSHA silica dust controls.

Sample Arizona ROC CR-8 Floor Covering Practice Questions

Try these sample questions to test your Arizona ROC CR-8 Floor Covering exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1Under ASTM F2170, when performing in-situ relative humidity (RH) testing on a 6-inch thick concrete slab on grade that is drying from one side only, to what depth must the test hole be drilled?
A.1.2 inches (20% of slab thickness)
B.2.4 inches (40% of slab thickness)
C.3.0 inches (50% of slab thickness)
D.4.5 inches (75% of slab thickness)
Explanation: ASTM F2170 specifies that for concrete slabs drying from one side (such as a slab on grade with a vapor retarder below), in-situ probes must be installed at a depth equal to 40% of the total slab thickness. For a 6-inch slab, 40% depth equals 2.4 inches. This depth represents the internal moisture level that will equilibrate throughout the slab after flooring installation.
2According to ASTM F2170, what is the required probe hole drilling depth for a 5-inch thick elevated concrete slab drying from both the top and bottom sides?
A.1.0 inch (20% of slab thickness)
B.2.0 inches (40% of slab thickness)
C.2.5 inches (50% of slab thickness)
D.3.75 inches (75% of slab thickness)
Explanation: When an elevated concrete slab is exposed to air on both top and bottom surfaces, moisture evaporates from both directions. ASTM F2170 requires drilling to 20% of the slab thickness for two-sided drying. For a 5-inch slab, 20% of 5 inches is 1.0 inch.
3After drilling test holes and inserting plastic sleeves into a concrete slab per ASTM F2170, what is the minimum required equilibration period before inserting probes and taking official relative humidity readings?
A.4 hours
B.12 hours
C.24 hours
D.72 hours
Explanation: Under the current ASTM F2170 standard revision, in-situ probe sleeves must be allowed to equilibrate for a minimum of 24 hours after hole drilling and sleeve insertion before taking official relative humidity readings. This ensures that friction heat from drilling dissipates and moisture within the hole reaches equilibrium with the surrounding concrete matrix.
4Per ASTM F1869, what is the exact duration range that an anhydrous calcium chloride test kit must remain sealed to the concrete subfloor to measure Moisture Vapor Emission Rate (MVER)?
A.12 to 24 hours
B.24 to 48 hours
C.60 to 72 hours
D.84 to 96 hours
Explanation: ASTM F1869 mandates that anhydrous calcium chloride test kits must be left in place under a sealed transparent dome for a minimum of 60 hours up to a maximum of 72 hours. The weight gain of the calcium chloride over this exact time frame is converted into lbs of water vapor per 1,000 sq ft per 24 hours.
5What is the standard baseline maximum allowable Moisture Vapor Emission Rate (MVER) per ASTM F1869 for standard vinyl composition tile (VCT) installations using traditional water-based acrylic adhesives without moisture mitigation?
A.1.0 lb / 1,000 sq ft / 24 hours
B.3.0 lbs / 1,000 sq ft / 24 hours
C.5.0 lbs / 1,000 sq ft / 24 hours
D.8.0 lbs / 1,000 sq ft / 24 hours
Explanation: The traditional industry baseline maximum allowable MVER for standard resilient flooring adhesives (such as water-based acrylic VCT adhesives) is 3.0 lbs per 1,000 sq ft per 24 hours. Emissions exceeding 3.0 lbs require specialized moisture mitigation systems or high-moisture resistant adhesives.
6You are preparing to perform ASTM F1869 Calcium Chloride moisture testing on a 6,500 square foot commercial concrete floor slab. What is the minimum number of test kits required?
A.6 kits
B.7 kits
C.9 kits
D.12 kits
Explanation: ASTM F1869 requires 3 test kits for the first 1,000 square feet of slab area, plus 1 additional test kit for each additional 1,000 square feet (or fraction thereof). For 6,500 sq ft: First 1,000 sq ft = 3 kits. Remaining 5,500 sq ft = 6 additional kits (rounding up for fractions). Total = 3 + 6 = 9 test kits.
7Per ASTM F710, how is concrete surface pH tested prior to resilient flooring installation, and what is the typical acceptable pH range for standard water-based adhesives?
A.Apply phenolphthalein directly to dry concrete; acceptable pH is 4.0 to 6.0
B.Place distilled water drops on clean concrete, wait 60 seconds, use pH strip; acceptable pH is 7.0 to 9.0
C.Scrape concrete dust into acid solution; acceptable pH is 10.0 to 13.0
D.Drill a 1-inch hole and insert electronic pH probe; acceptable pH is 5.0 to 7.0
Explanation: ASTM F710 specifies placing drops of distilled water on a clean, abraded concrete surface, waiting 60 seconds, and testing the liquid with a calibrated pH paper strip or digital meter. Standard resilient adhesives typically require a concrete surface pH between 7.0 and 9.0 (some modern high-tack formulations allow up to 10.0 or 11.0).
8What is the minimum 28-day compressive strength required for cementitious self-leveling underlayment installed over concrete in commercial heavy-traffic floor applications per ASTM F710?
A.1,200 psi
B.2,000 psi
C.3,000 psi
D.5,000 psi
Explanation: ASTM F710 and resilient floor manufacturers mandate that cementitious underlayments used in commercial installations must achieve a minimum compressive strength of 3,000 psi at 28 days to withstand heavy rolling loads, hospital beds, and forklift traffic without indentation or crushing.
9When preparing a subfloor for glue-down luxury vinyl tile (LVT) or direct-glue hardwood, what is the maximum allowable surface variation using a 10-foot straightedge?
A.1/16 inch in 10 feet
B.3/16 inch in 10 feet
C.3/8 inch in 10 feet
D.1/2 inch in 10 feet
Explanation: Standard resilient and hardwood flooring industry guidelines (including ASTM F710 and NWFA) specify a maximum subfloor flatness variation of 3/16 inch in 10 feet (or 1/8 inch in 6 feet). High spots must be ground down and low spots filled with approved skim coat or leveling patch.
10Which surface preparation method is recommended to remove concrete curing compounds, laitance, and sealers to achieve an ICRI Concrete Surface Profile (CSP) of 3 to 5 prior to applying a heavy moisture mitigation epoxy?
A.Acid etching with muriatic acid
B.Shot blasting
C.Solvent wiping with mineral spirits
D.Pressure washing with cold water
Explanation: Shot blasting mechanically abrades the concrete surface by propelling steel shot at high velocity, efficiently removing laitance, sealers, and contaminants to create a textured ICRI CSP 3 to 5 profile necessary for mechanical bonding of thick epoxy moisture mitigation membranes.

About the Arizona ROC CR-8 Floor Covering Exam

Comprehensive practice exam for the Arizona ROC CR-8 (Floor Covering) trade license. Grounded in ASTM moisture testing, NWFA hardwood standards, CRI 104/105 carpet guidelines, resilient LVT heat welding, adhesive science, and OSHA 1926 safety regulations.

Questions

60 scored questions

Time Limit

150 minutes

Passing Score

70%

Exam Fee

$66 (PSI Services LLC / Arizona Registrar of Contractors)

Arizona ROC CR-8 Floor Covering Exam Content Outline

43%

Ceramic Floor Tile and Stone

26 of 60 items on the official PSI content outline. Substrate preparation, mortars, setting, grouting and movement joints for tile and stone floors.

20%

Wood Flooring

12 of 60 items on the official PSI content outline. Solid and engineered wood, acclimation, moisture testing, nail-down, glue-down and floating installations.

15%

Carpeting

9 of 60 items on the official PSI content outline. Cushion, tackless strip, seaming, power stretching and glue-down carpet and carpet tile.

13%

Resilient Flooring

8 of 60 items on the official PSI content outline. Sheet vinyl, VCT, LVT and rubber flooring, adhesives, welding and finishing.

8%

Estimating Materials

5 of 60 items on the official PSI content outline. Area takeoffs, waste and pattern-match allowances, and adhesive coverage rates.

How to Pass the Arizona ROC CR-8 Floor Covering Exam

What You Need to Know

  • Passing score: 70%
  • Exam length: 60 questions
  • Time limit: 150 minutes
  • Exam fee: $66

Keys to Passing

  • Work through all 100 available questions
  • Review every answer and explanation
  • Track weak areas and revisit them
  • Use our AI tutor for tough concepts

Arizona ROC CR-8 Floor Covering Study Tips from Top Performers

1Memorize ASTM F2170 probe depth rules: 40% of slab thickness for slabs drying from one side (slab on grade), and 20% depth for slabs drying from both sides (elevated metal deck).
2Know the ASTM F1869 test kit calculation: minimum 3 test kits for the first 1,000 sq ft, plus 1 additional kit for each additional 1,000 sq ft of slab area.
3Review CRI 104/105 carpet power stretching rules: carpet MUST be power stretched 1% to 1.5% in both length and width; knee kickers are strictly for positioning/hooking, not stretching.
4Understand NWFA solid hardwood acclimation and moisture rules: wood MC must be within 4% of subfloor MC for solid strip (< 3" wide) and within 2% for wide plank (>= 3" wide).
5Study OSHA 1926.1153 Respirable Crystalline Silica Table 1 requirements for concrete floor grinding: handheld grinders require integrated dust shrouds connected to HEPA dust extractors.

Frequently Asked Questions

What scope of work is covered under the Arizona ROC CR-8 Floor Covering license?

The CR-8 classification authorizes contractors to prepare subfloors and install, repair, or replace carpet, resilient tile and sheet goods, luxury vinyl tile/plank (LVT/LVP), solid and engineered hardwood, linoleum, laminate, underlayment, floor mats, and non-structural seamless/epoxy floor coatings in both residential and commercial structures.

How many questions are on the PSI AZ ROC CR-8 exam and what is the passing score?

The official PSI CR-8 content outline lists 60 multiple-choice questions with 150 minutes allowed. Candidates must achieve a minimum passing score of 70% (42 correct answers).

Is the Arizona CR-8 Floor Covering trade exam open-book?

Yes. The exam is open-book and administered at computer testing centers. Candidates may bring approved reference materials (such as CRI 104/105, NWFA Guidelines, ASTM standards, RFCI technical manuals, and OSHA 1926) provided they are permanently bound and tabbed per PSI regulations.

What are the key moisture testing standards required for the CR-8 exam?

Candidates must master ASTM F2170 (in-situ relative humidity testing using probes inserted at 40% or 20% slab depth) and ASTM F1869 (Calcium Chloride Moisture Vapor Emission Rate testing measured in lbs/1,000 sq ft/24 hours), along with ASTM F710 for pH and surface flatness.

How does this practice bank prepare me for the CR-8 exam?

This 100-question practice bank covers all CR-8 blueprint domains, including trade math (square yardage, waste factors, MVER calculations, leveling bag volume), technical installation standards (NWFA, CRI, RFCI, ASTM), and OSHA 1926 safety requirements.