Free Practice Questions for Iran Nezam Electrical Supervision Exam
Exam-style questions and explanations by OpenExamPrep.
Loading practice questions...
Explore More Iran Construction Engineering Org (IRCEO / Nezam Mohandesi)
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
Key Facts: Iran Nezam Electrical Supervision Exam Exam
60 Questions
Total Questions
INBR / MRUD
150 minutes
Time Limit
INBR
50 / 100
Passing Threshold (clause 6-4, 1405 instruction)
INBR
3 wrong = 1 right
Negative Marking Rule
INBR
Open-Book
Exam Delivery Mode
INBR
Grade 3
Initial License Grade Awarded
IRCEO
The Iran Nezam Electrical Supervision examination is a 150-minute open-book paper of 60 four-option multiple-choice questions, held nationwide under the Office of National Building Regulations. It assesses an electrical engineer's supervisory duties, on-site testing and verification procedures (Topic 13), wiring and conduit workmanship, construction site electrical safety (Topic 12), and life-safety systems inspections (Topics 3 and 15). Negative marking applies and the pass threshold is 50 out of 100. The official paper is in Persian; OpenExamPrep provides independent English-language practice questions for the same topics.
Sample Iran Nezam Electrical Supervision Exam Practice Questions
Try these sample questions to review concepts for the Iran Nezam Electrical Supervision Exam exam. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.
1During pre-commissioning testing of a newly wired residential sub-distribution board under INBR Topic 13, the electrical supervisor performs an insulation resistance test with a 500V DC Megger between live conductors and protective earth. What is the minimum acceptable insulation resistance value?
2When verifying the insulation resistance of an Extra-Low Voltage circuit (SELV/PELV, nominal voltage ≤ 50V) in accordance with INBR Topic 13, what test voltage and minimum insulation resistance must the supervising engineer verify?
3Prior to conducting a mandatory insulation resistance test on a building distribution panel feeding electronic dimmers, LED drivers, and surge protective devices (SPDs), what preparatory action must the supervising engineer instruct the electrical contractor to take?
4When measuring the resistance of a newly driven vertical earth rod electrode using the 3-point fall-of-potential tester (earth tester), how must the current probe (C2) and potential probe (P2) be positioned relative to the earth electrode (E)?
5Before measuring the individual resistance of a building's earth pit electrode with an earth tester, which critical step must the supervising electrical engineer verify?
6Under INBR Topic 13, what is the maximum acceptable overall resistance of the main earthing system for a typical residential building supplied by a public low-voltage TN-S or TN-C-S distribution network?
7A 230V final subcircuit feeding standard socket-outlets in a TN system is protected by a 16A Type B miniature circuit breaker (MCB). Under INBR Topic 13, what is the maximum allowable earth fault loop impedance (Zs) to guarantee automatic disconnection within 0.4 seconds?
8Under INBR Topic 13, what is the maximum permissible automatic disconnection time for 230V AC final branch circuits not exceeding 32A supplying portable equipment in a TN earthing system?
9Under INBR Topic 13, which rated residual operating current (IΔn) is mandatory for Residual Current Devices (RCDs) installed for additional personal protection on domestic general-purpose socket-outlet circuits?
10When carrying out instrumental testing of a general (non-time-delayed) 30 mA RCD under INBR Topic 13, what is the maximum statutory tripping time permitted when injecting a residual current of 1× IΔn (30 mA)?
About the Iran Nezam Electrical Supervision Exam Exam
The Iran Nezam Electrical Supervision exam is the official national professional licensure examination administered by the Ministry of Roads and Urban Development for electrical engineers seeking the supervision (Nezarat) practicing grade in the Construction Engineering Organization of Iran (IRCEO). Supervising electrical engineers are legally charged with verifying on-site electrical installations, conduit and wiring execution, earthing and bonding systems, switchboard fabrication and clearances, life-safety systems (fire alarm and elevators), temporary site electrical safety, and executing statutory pre-commissioning testing and verification in strict compliance with the Iranian National Building Regulations.
Exam sponsor: Office of National Building Regulations and Building Control (inbr.ir), Ministry of Roads and Urban Development; delivered nationwide by the National Organization for Educational Testing (Sazman-e Sanjesh) educational services company. The requirements and fees below concern the certification or admission exam, separate from our free practice resources.
Assessment
60 four-option multiple-choice questions covering electrical testing and commissioning (Topic 13), wiring and equipment inspection (Topic 13, Publication 110), supervisory duties (Topic 2), site electrical safety (Topic 12), and fire alarm/elevator inspections (Topics 3, 15)
Time Limit
150 minutes
Passing Score
50 out of 100 (50%) — clause 6-4 of the official 1405 registration instruction, calculated after the negative-marking deduction
Exam / Certification Fees
Set per sitting and shown in the inbr.ir registration cart; the official 1405 registration instruction does not publish a fixed amount
Exam sponsor websiteFees, eligibility, and exam policies can change. Confirm them with the exam sponsor before applying or paying.
Our practice resources: topics covered
We aim to reflect publicly available exam outlines and topic information in our study resources. Coverage, format, and difficulty may differ from the actual exam, and we cannot guarantee that every detail is accurate or current. Confirm exam requirements, fees, and policies with the official exam sponsor.
Electrical Testing & Commissioning (INBR Topic 13)
Mandatory testing procedures: insulation resistance measurement with 500V DC Megger, earth electrode resistance measurement by 3-point fall-of-potential method, earth fault loop impedance, RCD operating current and trip time under 300 ms, phase sequence, polarity verification, and continuity testing of protective bonding conductors
Wiring & Conduit Installation Supervision (INBR Topic 13 & Pub 110)
Supervising physical installations: PVC/metal conduit bending radii and fill factor (max 40%), minimum embedding depths in walls and slabs (1.5 cm cover), junction box placement and accessibility, conductor color identification, termination torque, cable tray grounding, switchboard clearances (min 0.8-1.0 m), and ingress protection (IP ratings)
Supervisory Procedures & Legal Duties (INBR Topic 2 & Law)
Issuance of mandatory stage reports (rough-in, pre-pour, testing, energization), contractor non-conformance notices, municipal stop-work orders, inter-disciplinary coordination with civil and mechanical supervisors, and engineer professional liability under Article 34
Jobsite Electrical Safety (INBR Topic 12)
Temporary power supervision on construction sites: site distribution boards, mandatory 30 mA RCD protection on temporary sockets, overhead power line safe approach distances, crane and scaffolding protective bonding, and temporary electrical cord safety
Fire Alarm & Elevator Electrical Inspection (INBR Topics 3 & 15)
Supervision of life-safety electrical installations: fire alarm detector spacing, manual call point mounting heights (1.10-1.40 m), fire-resistant cabling and smoke damper interfaces; elevator machine room main switch, phase failure/reversal relay, car top inspection station, and pit emergency stop switch
Preparing for the Iran Nezam Electrical Supervision Exam Exam
What You Need to Know
- Passing score: 50 out of 100 (50%) — clause 6-4 of the official 1405 registration instruction, calculated after the negative-marking deduction
- Assessment: 60 four-option multiple-choice questions covering electrical testing and commissioning (Topic 13), wiring and equipment inspection (Topic 13, Publication 110), supervisory duties (Topic 2), site electrical safety (Topic 12), and fire alarm/elevator inspections (Topics 3, 15)
- Time limit: 150 minutes
- Exam / certification fees: Set per sitting and shown in the inbr.ir registration cart; the official 1405 registration instruction does not publish a fixed amount Official sources
Using Our Practice Resources
- Work through all 100 available questions
- Review every answer and explanation
- Track weak areas and revisit them
- Use our AI tutor for tough concepts
Iran Nezam Electrical Supervision Exam: Suggested Study Strategy
Frequently Asked Questions
What is the format of the Iran Nezam Electrical Supervision exam?
The examination consists of 60 four-option multiple-choice questions to be completed in 150 minutes. Clause 6-2 of the official 1405 registration instruction confirms the paper is held open book, so candidates may bring approved INBR books (Mabahes) and notes. Negative marking applies: three incorrect answers cancel one correct answer. The official paper is set in Persian.
What passing score is required for the Electrical Supervision exam?
Clause 6-4 of the official 1405 registration instruction sets the passing threshold at 50 out of 100 (50%). Because three incorrect answers cancel one correct answer (deducting 1/3 point per mistake), candidates who answer questions incorrectly must achieve more than 30 raw correct answers to reach the 50% net threshold. A passing score remains valid for up to 3 years toward obtaining the Grade 3 (Payeh 3) supervision license.
What are the eligibility requirements for the Electrical Supervision license exam?
Candidates must hold an accredited Bachelor's, Master's, or Ph.D. degree in Electrical Engineering (Power, Control, Electronics, or Telecommunications recognized by the Ministry of Science). A minimum period of post-graduation practical work is required: 3 years for Bachelor's holders, 2 years for Master's holders, and 1 year for doctoral holders, alongside active provincial Nezam membership.
Which National Building Regulations (INBR) and references are tested in Electrical Supervision?
The core tested texts include INBR Topic 13 (Design and Execution of Electrical Installations - specifically testing, verification, earthing, and workmanship), Topic 1 (Definitions), Topic 2 (Administrative Regulations and Supervisory Duties), Topic 3 (Fire Protection - fire alarm and emergency lighting), Topic 12 (Construction Site Safety - temporary electrical works), Topic 15 (Elevators and Escalators - electrical controls and safety switches), and Management and Planning Organization Publication 110 (Technical Specifications for Electrical Installations).
What are the key on-site testing requirements a supervising electrical engineer must verify under Topic 13?
Under Topic 13, the supervising engineer must verify: (1) insulation resistance with a Megger (minimum 1.0 MΩ at 500V DC for 230/400V installations); (2) earth electrode resistance using the 3-point fall-of-potential tester; (3) earth fault loop impedance to confirm automatic disconnection times; (4) residual current device (RCD) tripping current (30 mA) and tripping time (<300 ms at 1x IΔn); (5) polarity of switches and single-pole protection devices; (6) phase sequence (clockwise rotation); and (7) continuity of protective conductors (PE) and equipotential bonding (<0.05 Ω).