All Practice Exams

100+ Free Grade-2 Constructor Practice Questions

Prepare for the National Qualification Examination for Grade-2 Constructors (全国二级建造师执业资格考试) exam with instant access — no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
100+ Questions
100% Free

Loading practice questions...

Same family resources

Explore More China Constructor Qualification (建造师)

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.

2026 Statistics

Key Facts: Grade-2 Constructor Exam

Statutory Credential

Governing Authority

Practice Scope

Exam Papers

Passing Cycle

Passing Benchmark

Primary Standards

Official Portal

China's statutory professional qualification for construction project managers (二级建造师) on small and medium projects, testing construction project management, PRC construction laws, CPM network scheduling, cost control, GB 50300 quality acceptance, safety regulations, and specialized engineering practice.

Sample Grade-2 Constructor Practice Questions

Try these sample questions to test your Grade-2 Constructor exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1Under the Chinese Construction Project Manager system and the PRC Construction Law, what is the statutory status and primary responsibility of the Construction Project Manager (项目经理)?
A.The Project Manager is the statutory representative (法定代表人) of the construction enterprise and bears unlimited civil liability
B.The Project Manager is the designated representative of the enterprise's legal representative on site and the first person responsible for project construction management
C.The Project Manager is an independent third-party supervisor appointed directly by the government housing bureau
D.The Project Manager is an agent of the project owner (建设单位) responsible solely for financial disbursement approval
Explanation: According to the PRC Construction Law and national construction project management specifications (GB/T 50326), the Construction Project Manager (项目经理) is the authorized representative appointed in writing by the enterprise's legal representative (企业法定代表人) to manage the construction project, and acts as the first person responsible (第一责任人) for project quality, safety, schedule, and cost management.
2Which type of project organizational structure is characterized by a strict single command source (单一指令源) where each subordinate node receives orders from only one direct superior, commonly used in military and conventional construction projects?
A.Functional organizational structure (职能组织结构)
B.Linear organizational structure (线性组织结构)
C.Matrix organizational structure (矩阵组织结构)
D.Work Breakdown Structure (工作分解结构)
Explanation: In a linear organizational structure (线性组织结构), command relationships run strictly vertically along hierarchical lines. Every sub-unit or individual has only one direct superior, eliminating conflicting orders from multiple departments. In contrast, functional structures suffer from multiple command sources, and matrix structures have dual command sources (vertical line and horizontal project).
3According to the national standard 'Code for Construction Organization Plan of Building Engineering' (GB/T 50502), how are Construction Organization Plans (施工组织设计) classified based on their scope and detail level?
A.Preliminary Design, Technical Design, and Working Drawing Design
B.General Construction Organization Plan, Unit Project Construction Organization Plan, and Construction Scheme (施工方案)
C.Feasibility Study Report, Construction Permit Application, and Quality Acceptance Dossier
D.Safety Plan, Environmental Plan, and Quality Assurance Plan
Explanation: GB/T 50502 classifies construction organization plans into three hierarchical levels: (1) General Construction Organization Plan (施工组织总设计) for entire project groups or complex clusters, (2) Unit Project Construction Organization Plan (单位工程施工组织设计) for single standalone buildings or structures, and (3) Construction Scheme / Specialized Plan (施工方案) for critical division/sub-division engineering works or specialized tasks.
4In the dynamic control cycle (动态控制原理) of construction project targets, what is the correct sequence of core managerial steps?
A.Target decomposition -> Target tracking & data collection -> Target comparison -> Deviation analysis -> Corrective action
B.Deviation analysis -> Target decomposition -> Corrective action -> Target tracking -> Acceptance
C.Corrective action -> Target tracking -> Target comparison -> Target decomposition -> Final accounting
D.Target tracking -> Corrective action -> Target decomposition -> Milestone signing -> Post-evaluation
Explanation: The fundamental principle of dynamic control (动态控制) involves: (1) Decomposing project targets and defining planned baseline values (目标分解与计划值确定), (2) Regularly tracking actual progress/cost and collecting actual values (目标跟踪与实际值收集), (3) Comparing planned values with actual values (计划值与实际值比较), (4) Analyzing deviations if any occur (偏差分析), and (5) Implementing corrective organizational, technical, economic, or contractual measures (采取纠偏措施).
5In a double-code network diagram (双代号网络图), what is the function and characteristic of a virtual activity / dummy arrow (虚箭线 / 虚工作)?
A.It represents a critical construction task that consumes significant labor and budget
B.It consumes neither time duration nor physical resources, serving solely for logic linking, distinction, or rupture elimination
C.It represents an activity with negative float that will cause severe project delay
D.It indicates an external milestone deadline imposed by the client
Explanation: In double-code CPM network diagrams, a dummy activity (虚工作) is represented by a dashed arrow. It consumes zero duration (t = 0) and zero resources, and is used exclusively to express logical dependencies between tasks (联系), avoid ambiguous duplicate numbering of parallel tasks sharing start/end nodes (区分), and eliminate false logical relationships (断路).
6A construction network plan has five paths with durations as follows: Path 1: 18 days; Path 2: 24 days; Path 3: 21 days; Path 4: 24 days; Path 5: 16 days. Assuming no external contractual constraints, what is the planned total project duration (计算工期) and what are the critical paths?
A.Duration is 18 days; Path 1 is the critical path
B.Duration is 24 days; both Path 2 and Path 4 are critical paths
C.Duration is 21 days; Path 3 is the only critical path
D.Duration is 103 days (sum of all paths); all paths are critical
Explanation: In CPM network planning, the calculated project duration is equal to the duration of the longest path from the start node to the end node. Here, the maximum path duration is 24 days. Any path that has the maximum total duration is a critical path (关键线路). Since Path 2 and Path 4 both have a duration of 24 days, both are critical paths.
7Activity M in a double-code network schedule has an Early Start (ES) of Day 4, a Duration (D) of 6 days, and a Late Finish (LF) of Day 15. What is the Total Float (总时差 TF) of Activity M?
A.3 days
B.5 days
C.6 days
D.9 days
Explanation: Early Finish (EF) = Early Start (ES) + Duration (D) = 4 + 6 = 10 days. Total Float (TF) is the difference between Late Finish and Early Finish: TF = LF - EF = 15 - 10 = 5 days (or equivalently, Late Start LS = LF - D = 15 - 6 = 9 days, and TF = LS - ES = 9 - 4 = 5 days).
8Activity K has a duration of 5 days and an Early Start (ES) of Day 8. It has two immediate successor activities: Activity P with ES = 16 days, and Activity Q with ES = 14 days. What is the Free Float (自由时差 FF) of Activity K?
A.1 day
B.3 days
C.6 days
D.8 days
Explanation: The Early Finish of Activity K is EF = ES + D = 8 + 5 = 13 days. Free Float (FF) is defined as the minimum Early Start of all immediate successor activities minus the Early Finish of the activity: FF = min(ES_successors) - EF_K = min(16, 14) - 13 = 14 - 13 = 1 day.
9In a single-code network diagram (单代号网络图), what does the circular or rectangular node represent, and what does the arrow represent?
A.Nodes represent milestone events; arrows represent work activities with durations
B.Nodes represent work activities (including name, ID, duration); arrows represent logical dependencies between activities
C.Nodes represent labor teams; arrows represent material delivery routes
D.Nodes represent cash disbursement milestones; arrows represent financial audits
Explanation: In a single-code network diagram (单代号网络图 / Activity-on-Node AON), each node represents a distinct work activity, containing the activity code, name, and duration. Arrows (箭线) represent only the logical precedence relationships (dependencies) between tasks and carry no duration or resource consumption.
10Compared to CPM network schedules, what is the primary advantage and primary limitation of a traditional Gantt chart (横道图) in construction management?
A.Advantage: accurately displays total float; Limitation: difficult to understand for workers
B.Advantage: clear, intuitive, and easy to read; Limitation: cannot clearly show logical dependencies between activities or identify the critical path
C.Advantage: automatically recalculates resource leveling; Limitation: cannot depict calendar dates
D.Advantage: mathematically guarantees lowest cost; Limitation: only applicable to projects under 1 month
Explanation: A Gantt chart (横道图) is simple, intuitive, and clearly depicts start dates, finish dates, and durations against a calendar timeline. However, its major drawbacks are that it cannot clearly represent complex logical dependencies between tasks, cannot calculate total and free float, and cannot explicitly identify the critical path or critical activities.

About the Grade-2 Constructor Exam

The National Qualification Examination for Grade-2 Constructors (全国二级建造师执业资格考试) is China's official statutory professional licensing examination for construction project managers (项目经理) and site leaders on small- and medium-scale construction projects. Administered provincially under a unified national syllabus and question bank established by the Ministry of Housing and Urban-Rural Development (MOHURD) and the Ministry of Human Resources and Social Security (MOHRSS), the credential assesses comprehensive competence in construction organization, CPM schedule control, cost management (Earned Value analysis, price adjustments), quality assurance (GB 50300 acceptance hierarchy), safety management (JGJ 59, State Council Decree No. 493 accident tiers), bidding and contract administration (Civil Code, standard construction contracts, 28-day claim procedures), and specialized technical execution in building, municipal, and civil infrastructure engineering.

Assessment

Paper 1: Construction Project Management (建设工程施工管理, 100 pts, 2.0 hrs: 60 single-choice, 20 multiple-choice); Paper 2: Construction Regulations and Relevant Laws (建设工程法规及相关知识, 100 pts, 2.0 hrs: 60 single-choice, 20 multiple-choice); Paper 3: Professional Engineering Management and Practical Case Practice (专业工程管理与实务, 120 pts, 2.5 hrs: 20 single-choice, 10 multiple-choice, 4 subjective case problems across 6 specialty tracks: Building Engineering, Municipal Public Works, Highway Engineering, Water Resources & Hydropower, Mechanical & Electrical Engineering, Mining Engineering). Passing scores are valid on a rolling 2-year cycle.

Time Limit

6.5 hours total (2.0 hours for Paper 1, 2.0 hours for Paper 2, 2.5 hours for Paper 3)

Passing Score

50%–60% of total score per subject (determined annually by provincial authorities; rolling 2-year cycle)

Exam Fee

Set locally; Shanghai 2026 charges RMB 10 registration, RMB 60 for each basic paper, and RMB 70 for the specialty paper (RMB 200 total) (Provincial Housing and Urban-Rural Development Departments (省住建厅) & Provincial Human Resources and Social Security Departments (省人社厅), under MOHURD / MOHRSS unified examination syllabus)

Grade-2 Constructor Exam Content Outline

30%

construction-management-fundamentals

Core concepts and analytical methods of construction project management: statutory duties and authority of the Project Manager (项目经理) under the Constructor system, project organization structures (linear, matrix, functional organizations), work breakdown structure (WBS), construction organization plan hierarchy (施工组织总设计, 单位工程施工组织设计, 施工方案), dynamic progress control, double-code (双代号) and single-code (单代号) CPM network diagrams, critical path determination, early/late start and finish times, Total Float (TF) and Free Float (FF) calculations, the 6-stage cost management cycle (forecast, plan, control, accounting, analysis, assessment), Earned Value Management (EVM) parameters (Planned Value PV, Earned Value EV, Actual Cost AC, Cost Variance CV, Schedule Variance SV, CPI, SPI), three-stage quality control (pre-control, in-process, post-control, PDCA cycle), construction safety management systems, and green/civilized construction site environmental management (noise, dust, wastewater control).

25%

construction-laws-and-regulations

Statutory legal system and administrative regulations governing the construction industry in China: PRC Construction Law (中华人民共和国建筑法), construction permit (施工许可证) application prerequisites, validity, suspension, and restart reporting rules, builder and contractor enterprise qualification licensing grades, registered constructor practicing scope, stamp signing liabilities, and continuing education rules, PRC Bidding and Tendering Law (招标投标法), bidding document issuance rules, bid security (投标保证金 <=2%), bid validity period, tender evaluation committee composition, winning bidder criteria, construction contract classifications (lump sum, unit price, cost-plus), PRC Labor Contract Law, statutory wage protection systems for rural migrant workers (农民工工资专用账户), work-related injury insurance (工伤保险), statutory safety responsibilities of owner, designer, contractor, and supervising engineer under the Regulations on the Safety Management of Construction Projects (建设工程安全生产管理条例), safety production licenses, and accident reporting timelines, casualty classifications, and investigation procedures under State Council Decree No. 493.

30%

professional-engineering-practice

Technical construction execution and quality standards across building and municipal public works tracks: shallow foundation and deep excavation safety, dewatering methods, cast-in-place bored pile drilling and mud slurry control, precast pile driving, pile integrity testing (low-strain / high-strain sonic logging), reinforced concrete frame formwork design, stripping strength thresholds, rebar joint mechanical splicing and cover thickness, concrete pouring, vibration, and curing durations (min 7 days standard, 14 days mineral admixture/impermeable), masonry construction mortar strength grades, brick layout rules, ring beams (圈梁) and structural tie-columns (构造柱), basement waterproof concrete (impermeability grade P6/P8) and external membrane protection, roof SBS modified bitumen waterproofing and slope drainage, dangerous part-project (危大工程) safety regulations and expert panel review thresholds (MOHURD Decree No. 37: excavation >=5m, formwork height >=8m, span >=18m, scaffolding >=50m), municipal trench excavation and pipe jacking (顶管法), urban road subgrade compaction and asphalt concrete paving/compaction temperatures, bridge substructure pier/cap construction, precast girder hoisting, and the 4-level quality acceptance hierarchy under GB 50300 (inspection batch 检验批, sub-item 分项, sub-division 分部, unit project 单位工程).

15%

contract-and-dispute-management

Construction contract execution, change orders, dispute resolution, and project closeout: standard model construction contract clauses (GF-2017-0201), contract change order valuation rules, price adjustment calculation using the Price Index Formula (价格指数调整法), construction claims management, statutory 28-day claim notification, 28-day detailed claim report submission, engineer's 28-day review and response obligation, compensable owner delays vs non-compensable contractor delays, liquidated damages for delay, project completion acceptance procedures, handover criteria, warranty liability periods (2 years MEP/finishes, 5 years waterproofing, design working life for structural foundation), construction project dossier archiving rules (城建档案馆归档), and lifelong project quality responsibility commit letters.

How to Pass the Grade-2 Constructor Exam

What You Need to Know

  • Passing score: 50%–60% of total score per subject (determined annually by provincial authorities; rolling 2-year cycle)
  • Assessment: Paper 1: Construction Project Management (建设工程施工管理, 100 pts, 2.0 hrs: 60 single-choice, 20 multiple-choice); Paper 2: Construction Regulations and Relevant Laws (建设工程法规及相关知识, 100 pts, 2.0 hrs: 60 single-choice, 20 multiple-choice); Paper 3: Professional Engineering Management and Practical Case Practice (专业工程管理与实务, 120 pts, 2.5 hrs: 20 single-choice, 10 multiple-choice, 4 subjective case problems across 6 specialty tracks: Building Engineering, Municipal Public Works, Highway Engineering, Water Resources & Hydropower, Mechanical & Electrical Engineering, Mining Engineering). Passing scores are valid on a rolling 2-year cycle.
  • Time limit: 6.5 hours total (2.0 hours for Paper 1, 2.0 hours for Paper 2, 2.5 hours for Paper 3)
  • Exam fee: Set locally; Shanghai 2026 charges RMB 10 registration, RMB 60 for each basic paper, and RMB 70 for the specialty paper (RMB 200 total)

Keys to Passing

  • Work through all 100 available questions
  • Review every answer and explanation
  • Track weak areas and revisit them
  • Use our AI tutor for tough concepts

Grade-2 Constructor Study Tips from Top Performers

1Master CPM Float Computations: Memorize Total Float (TF = LS - ES = LF - EF) and Free Float (FF = min(ES_j) - EF_i). Practice calculating critical paths and identifying how activity delays impact total project duration.
2Internalize Earned Value Formulas: Drill Planned Value (PV), Earned Value (EV), Actual Cost (AC), Cost Variance (CV = EV - AC), Schedule Variance (SV = EV - PV), Cost Performance Index (CPI = EV/AC), and Schedule Performance Index (SPI = EV/PV).
3Memorize Decree 493 Accident Classification: Remember the 4 tiers: Special Major (>=30 deaths, >=100 injuries, >=100M RMB loss), Major (10-29 deaths, 50-99 injuries, 50M-100M RMB loss), Larger (3-9 deaths, 10-49 injuries, 10M-50M RMB loss), and General (<3 deaths, <10 injuries, <10M RMB loss), plus the 1-hour reporting rule and 30-day casualty tracking window.
4Understand Dangerous Part-Project Thresholds (Decree No. 37): Learn which operations require expert panel demonstration (excavation depth >=5m, formwork height >=8m, formwork span >=18m, total formwork load >=15 kN/m2, concentrated line load >=20 kN/m, scaffolding height >=50m).
5Master GB 50300 Acceptance Hierarchy: Know the sequence from Inspection Batch (检验批) -> Sub-item (分项) -> Sub-division (分部) -> Unit Project (单位工程), along with main control item 100% compliance and general item >=80% compliance rules.
6Practice the 28-Day Claim Rule: Learn that the contractor must submit a formal claim intention notice within 28 days of the claim event, follow up with a detailed substantiation report within 28 days thereafter, and the supervising engineer has 28 days to respond.

Frequently Asked Questions

What is the Grade-2 Constructor (二级建造师) qualification and what is its practice scope?

The Grade-2 Constructor (二级建造师) is a statutory professional qualification in China governed by provincial Housing and Urban-Rural Development Departments (省住建厅) and Human Resources and Social Security Departments (省人社厅) under the unified syllabus of MOHURD and MOHRSS. Licensed Grade-2 constructors are legally authorized to serve as Project Managers (项目经理) on small- and medium-scale construction projects within their registered administrative province, lead site construction operations, and stamp official construction management deliverables.

How does the Grade-2 Constructor differ from the Grade-1 Constructor?

Grade-1 Constructors (一级建造师) hold a nationwide qualification that authorizes them to serve as project managers on large, medium, and small construction projects across all provinces in China without geographic restriction. Grade-2 Constructors (二级建造师) are qualified to lead small- and medium-scale projects, and their initial practice registration is primarily effective within the province where the certificate was issued (though inter-provincial mutual recognition is increasingly adopted under national guidelines).

What is the examination structure, passing threshold, and score validity cycle?

The examination comprises three papers: (1) Construction Project Management (建设工程施工管理, 100 pts, 2.0 hrs), (2) Construction Regulations & Related Knowledge (建设工程法规及相关知识, 100 pts, 2.0 hrs), and (3) Professional Engineering Management & Practice (专业工程管理与实务, 120 pts, 2.5 hrs across 6 tracks: Building, Municipal, Highway, Water, Mining, MEP). Scores are valid on a rolling 2-year cycle; candidates taking all subjects must pass all three within two consecutive examination years. Provincial authorities determine annual passing score cutoffs, typically between 50% and 60% of total points.

What key national codes, standards, and decrees are evaluated on the exam?

Core standards and regulations evaluated include the PRC Construction Law (中华人民共和国建筑法), PRC Bidding and Tendering Law (招标投标法), State Council Decree No. 493 (Regulations on the Reporting and Investigation of Production Safety Accidents), MOHURD Decree No. 37 (Safety Management of Dangerous Part-Projects), GB 50300-2013 (Unified Standard for Construction Quality Acceptance of Building Engineering), JGJ 59-2011 (Standard for Construction Safety Inspection), and standard construction contract terms (GF-2017-0201).

Why is this OpenExamPrep practice question bank presented in English?

This practice module provides 100 high-yield multiple-choice questions in English designed to build conceptual mastery for bilingual project managers, international engineering practitioners, and professionals studying Chinese construction standards. It preserves official Chinese terminology, standard code designations (e.g., GB 50300, JGJ 59, Decree 493), and statutory definitions in parentheses alongside clear English explanations.