Cheat sheet

PE Civil Construction Cheat Sheet

Soil Mechanics

8-11%of exam

Lateral PressureEffective StressBearing CapacitySlope Stability

Site Layout & Development

6-10%of exam

Staking & BenchmarksHorizontal CurvesVertical CurvesUtility Verification

Material Properties

6-10%of exam

Concrete MixSoil ClassificationSteel TypesWood Types

Estimating Quantities & Costs

8-11%of exam

Quantity TakeoffCost EstimatingEngineering EconomicsEarned Value

Project Planning & Scheduling

9-14%of exam

CPM NetworkFloatResource LevelingTime-Cost Tradeoff

Production & Quality Control

9-14%of exam

Material TestingConcrete PlacementWeld & Bolt QCCompaction

Structural Mechanics

9-14%of exam

LoadsStaticsStress & DeflectionStructural Systems

Hydraulics & Hydrology

5-8%of exam

Runoff MethodsOpen-Channel FlowDetention PondsCulverts

Construction Operations & Methods

11-18%of exam

Cranes & RiggingDewateringEquipment SelectionCut & Fill

Support of Construction Loads

12-19%of exam

FormworkFalseworkShoringBracing

Health & Safety

5-8%of exam

OSHA ThresholdsFall ProtectionExcavation SafetyWork Zone Safety

Quick Facts

Exam
PE Civil Construction
Questions
80
Time
8 hrs (9-hr appt)
Pass Score
Not published
Format
CBT, Pearson VUE
Fee
$400
Level
PE licensure depth exam
Blueprint
April 2024

Rankine Earth Pressure

Ka smallest, Kp largest, K0 in between

Ka: active minimumKp: passive maximumK0: at-rest value

Total Stress vs Effective Stress

Total stress

  • Includes pore water pressure
  • Full overburden weight

Effective stress

  • Total minus pore pressure
  • Controls soil shear strength

Total minus pore equals effective

Soil Mechanics Formulas

Ka
(1-sinφ)/(1+sinφ)Active
Kp
(1+sinφ)/(1-sinφ)Passive
Effective stress
Total stress minus pore pressure
FS (slope)
Resisting force over driving force
Bearing capacity
Ultimate soil support pressure
Consolidation settlement
Time-dependent clay compression

Layout & Curve Basics

HI
Elevation plus backsight reading
New elevation
HI minus foresight reading
R
5729.58 divided by degreeArc def
PC/PT
Curve start and end
Potholing
Field-verify utility depth
Benchmark
Known reference elevation point

Material Properties

Slump test
Concrete workability measure
W/C ratio
Lower ratio, higher strength
Air entrainment
Freeze-thaw durability protection
Atterberg limits
Soil plasticity classification test
USCS
Unified soil classification system
Prestressed steel
Pre- or post-tensioned strand

Earned Value Formulas

CV=EV-AC, SV=EV-PV, CPI=EV/AC, SPI=EV/PV

CV: cost varianceSV: schedule varianceCPI: cost efficiencySPI: schedule efficiency

CPI vs SPI

CPI

  • Cost performance measure
  • EV divided by AC

SPI

  • Schedule performance measure
  • EV divided by PV

Cost efficiency vs schedule efficiency

Estimating & Economics

Swell
Loose volume exceeds bank
Shrinkage
Compacted volume below bank
Load factor
Bank volume over loose volume
Mass haul diagram
Cumulative cut minus fill
NPV
Discounted future cash flows
Break-even point
Cost equals revenue point

Earned Value Management

PV
Planned value, BCWS
EV
Earned value, BCWP
AC
Actual cost, ACWP
CV
EV minus AC
SV
EV minus PV
CPI
EV divided by AC
SPI
EV divided by PV
EAC
BAC divided by CPI

Total Float vs Free Float

Total float

  • Delay without project delay
  • Equals LS minus ES

Free float

  • Delay without successor delay
  • Local activity slack only

Project delay vs next activity

Schedule Analysis Selection

  1. Repetitive units like paving or pipingLine of balance
  2. Complex activity logic tiesCPM network analysis
  3. Need shorter overall durationCrash the critical path
  4. Resource demand is overallocatedLevel the resources
  5. Simple small straightforward projectBar or Gantt chart

CPM Scheduling

ES/EF
Forward-pass activity times
LS/LF
Backward-pass activity times
Total float
LS minus ES
Free float
Delay without delaying successor
Critical path
Longest path, zero float
Crashing
Shorten duration, add cost
FS/SS/FF/SF
Precedence relationship types

Resource & Linear Scheduling

Resource leveling
Smooths peak resource demand
Line of balance
Repetitive-unit production scheduling
Time-cost tradeoff
Balances duration against cost
Bar chart
Simple activity-timeline display
Precedence diagram
Activity-on-node network method

QA/QC Field Control

Proctor test
Maximum density reference standard
Nuclear density gauge
Field compaction verification tool
Concrete maturity
Strength from temperature-time
Cylinder break
28-day strength verification
Bolt torque check
Verifies clamping force
Weld inspection
NDT acceptance criteria check

Provided Design Standards

ACI 347R
Formwork design guide
ACI SP-4
Formwork for concrete
AISC Manual
Steel construction manual
ASCE 37-14
Construction loads standard
PCA EB001
Concrete mixtures guide
CFR 1926
OSHA construction safety rules

Structural Mechanics Basics

Dead load
Permanent structure weight
Construction load
Temporary erection-phase load
Bending stress
Mc divided by I
Shear stress
VQ divided by Ib
Deflection check
Serviceability limit state
Combined stress
Axial plus bending superposition

Hydraulics & Hydrology

Rational method
Q equals C, i, A
Manning's equation
Open-channel flow velocity
Time of concentration
Longest travel-time path
Detention pond
Temporarily stores peak runoff
SCS/NRCS method
Curve-number runoff estimate
Culvert
Cross-drainage conveyance structure

Swell vs Shrinkage

Swell

  • Loose volume expands
  • Excavated soil increases

Shrinkage

  • Compacted volume decreases
  • Falls below bank volume

Loose state vs compacted state

Earthwork Method Selection

  1. Cut volume exceeds fill needWaste to spoil area
  2. Site needs additional fill materialImport from borrow pit
  3. Optimizing haul cost and distanceBuild mass haul diagram
  4. Groundwater enters open excavationInstall dewatering system
  5. Deep small-diameter foundation neededDrilled shaft or pile

Equipment & Earthwork Operations

Cut/fill analysis
Balances earthwork volumes
Borrow pit
Imported off-site fill source
Crane capacity
Read from load chart
Outrigger load
Ground-bearing pressure check
Dewatering
Wellpoint or sump control
Deep foundation install
Pile or drilled shaft

Temporary Works Sequence

Form, then Falsework, then Shore, then Reshore

Form: shapes concreteFalsework: supports structureShore: supports excavationReshore: after stripping

Formwork vs Falsework

Formwork

  • Shapes fresh concrete
  • Resists lateral pressure

Falsework

  • Supports structure temporarily
  • Used before strength gain

Concrete shape vs structure support

Temporary Structure Selection

  1. Support wet concreteFormwork(Shapes fresh concrete)
  2. Support structure before strength gainFalsework
  3. Support excavated soil faceShoring
  4. Remove forms before full cureReshoring
  5. Resist lateral wind or seismicBracing
  6. Deep unstable-soil excavation wallTrench box or sheeting

Temporary Structures

Formwork
Shapes and contains concrete
Falsework
Temporary structural support system
Shoring
Supports excavation or structure
Reshoring
Support after early stripping
Bracing
Provides lateral stability
Support of excavation
Retains adjacent soil face
Form pressure
Rises with pour rate

Shoring vs Bracing

Shoring

  • Supports excavation walls
  • Vertical or lateral loads

Bracing

  • Provides lateral stability
  • Resists wind or seismic

Soil support vs overall stability

OSHA Trigger Depths

5 ft dig, 6 ft fall, 20 ft engineer

5ft: excavation protection6ft: fall protection20ft: PE-designed system

OSHA Trigger Depth/Height

  1. Excavation reaches 5 feet deepProtective system required
  2. Excavation exceeds 20 feet deepPE-designed system required
  3. Working at 6 feet highFall protection required
  4. Scaffold platform 10 feet highFall protection required
  5. Ground movement risk existsProtect regardless of depth

OSHA Construction Thresholds

Fall protection
Required at 6 feet
Excavation protection
Required at 5 feet
PE-designed system
Required beyond 20 feet
Competent person
Daily excavation inspections required
Soil Type A/B/C
Most to least stable
Scaffold fall protection
Required at 10 feet
MUTCD Part 6
Temporary traffic control rules

Common Traps

Swell ≠ Shrinkage

Swell: loose volume grows Shrinkage: compacted volume shrinks

Total Float ≠ Free Float

Total: whole-project delay slack Free: next-activity delay slack

Formwork ≠ Falsework

Formwork: shapes wet concrete Falsework: supports temporary structure

CPI ≠ SPI

CPI: measures cost efficiency SPI: measures schedule efficiency

Total Stress ≠ Effective Stress

Total: includes pore pressure Effective: controls soil strength

Active Pressure ≠ Passive Pressure

Active: soil moves away Passive: soil pushed inward

Equated Score ≠ Fixed Percentage

NCEES uses equated scoring No published cutoff percentage

Last Minute

  1. 1.80 questions, 8 exam hours
  2. 2.9-hour appointment includes tutorial and break
  3. 3.No fixed passing score published
  4. 4.Support of Loads weighs most
  5. 5.Operations and Methods rank second
  6. 6.Fall protection required at 6ft
  7. 7.Excavation protection required at 5ft
  8. 8.PE-designed system required beyond 20ft
  9. 9.Critical path equals zero float
  10. 10.CV equals EV minus AC
  11. 11.SPI equals EV over PV
  12. 12.Swell expands; shrinkage compacts volume
Same family resources

Explore More PE Exams

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.