Soil Mechanics
8-11%of exam
Site Layout & Development
6-10%of exam
Material Properties
6-10%of exam
Estimating Quantities & Costs
8-11%of exam
Project Planning & Scheduling
9-14%of exam
Production & Quality Control
9-14%of exam
Structural Mechanics
9-14%of exam
Hydraulics & Hydrology
5-8%of exam
Construction Operations & Methods
11-18%of exam
Support of Construction Loads
12-19%of exam
Health & Safety
5-8%of exam
Quick Facts
- Exam
- PE Civil Construction
- Questions
- 80
- Time
- 8 hrs (9-hr appt)
- Pass Score
- Not published
- Format
- CBT, Pearson VUE
- Fee
- $400
- Level
- PE licensure depth exam
- Blueprint
- April 2024
Rankine Earth Pressure
Ka smallest, Kp largest, K0 in between
Total Stress vs Effective Stress
Total stress
- Includes pore water pressure
- Full overburden weight
Effective stress
- Total minus pore pressure
- Controls soil shear strength
Total minus pore equals effective
Soil Mechanics Formulas
- Ka
- (1-sinφ)/(1+sinφ)Active
- Kp
- (1+sinφ)/(1-sinφ)Passive
- Effective stress
- Total stress minus pore pressure
- FS (slope)
- Resisting force over driving force
- Bearing capacity
- Ultimate soil support pressure
- Consolidation settlement
- Time-dependent clay compression
Layout & Curve Basics
- HI
- Elevation plus backsight reading
- New elevation
- HI minus foresight reading
- R
- 5729.58 divided by degreeArc def
- PC/PT
- Curve start and end
- Potholing
- Field-verify utility depth
- Benchmark
- Known reference elevation point
Material Properties
- Slump test
- Concrete workability measure
- W/C ratio
- Lower ratio, higher strength
- Air entrainment
- Freeze-thaw durability protection
- Atterberg limits
- Soil plasticity classification test
- USCS
- Unified soil classification system
- Prestressed steel
- Pre- or post-tensioned strand
Earned Value Formulas
CV=EV-AC, SV=EV-PV, CPI=EV/AC, SPI=EV/PV
CPI vs SPI
CPI
- Cost performance measure
- EV divided by AC
SPI
- Schedule performance measure
- EV divided by PV
Cost efficiency vs schedule efficiency
Estimating & Economics
- Swell
- Loose volume exceeds bank
- Shrinkage
- Compacted volume below bank
- Load factor
- Bank volume over loose volume
- Mass haul diagram
- Cumulative cut minus fill
- NPV
- Discounted future cash flows
- Break-even point
- Cost equals revenue point
Earned Value Management
- PV
- Planned value, BCWS
- EV
- Earned value, BCWP
- AC
- Actual cost, ACWP
- CV
- EV minus AC
- SV
- EV minus PV
- CPI
- EV divided by AC
- SPI
- EV divided by PV
- EAC
- BAC divided by CPI
Total Float vs Free Float
Total float
- Delay without project delay
- Equals LS minus ES
Free float
- Delay without successor delay
- Local activity slack only
Project delay vs next activity
Schedule Analysis Selection
- Repetitive units like paving or piping→Line of balance
- Complex activity logic ties→CPM network analysis
- Need shorter overall duration→Crash the critical path
- Resource demand is overallocated→Level the resources
- Simple small straightforward project→Bar or Gantt chart
CPM Scheduling
- ES/EF
- Forward-pass activity times
- LS/LF
- Backward-pass activity times
- Total float
- LS minus ES
- Free float
- Delay without delaying successor
- Critical path
- Longest path, zero float
- Crashing
- Shorten duration, add cost
- FS/SS/FF/SF
- Precedence relationship types
Resource & Linear Scheduling
- Resource leveling
- Smooths peak resource demand
- Line of balance
- Repetitive-unit production scheduling
- Time-cost tradeoff
- Balances duration against cost
- Bar chart
- Simple activity-timeline display
- Precedence diagram
- Activity-on-node network method
QA/QC Field Control
- Proctor test
- Maximum density reference standard
- Nuclear density gauge
- Field compaction verification tool
- Concrete maturity
- Strength from temperature-time
- Cylinder break
- 28-day strength verification
- Bolt torque check
- Verifies clamping force
- Weld inspection
- NDT acceptance criteria check
Provided Design Standards
- ACI 347R
- Formwork design guide
- ACI SP-4
- Formwork for concrete
- AISC Manual
- Steel construction manual
- ASCE 37-14
- Construction loads standard
- PCA EB001
- Concrete mixtures guide
- CFR 1926
- OSHA construction safety rules
Structural Mechanics Basics
- Dead load
- Permanent structure weight
- Construction load
- Temporary erection-phase load
- Bending stress
- Mc divided by I
- Shear stress
- VQ divided by Ib
- Deflection check
- Serviceability limit state
- Combined stress
- Axial plus bending superposition
Hydraulics & Hydrology
- Rational method
- Q equals C, i, A
- Manning's equation
- Open-channel flow velocity
- Time of concentration
- Longest travel-time path
- Detention pond
- Temporarily stores peak runoff
- SCS/NRCS method
- Curve-number runoff estimate
- Culvert
- Cross-drainage conveyance structure
Swell vs Shrinkage
Swell
- Loose volume expands
- Excavated soil increases
Shrinkage
- Compacted volume decreases
- Falls below bank volume
Loose state vs compacted state
Earthwork Method Selection
- Cut volume exceeds fill need→Waste to spoil area
- Site needs additional fill material→Import from borrow pit
- Optimizing haul cost and distance→Build mass haul diagram
- Groundwater enters open excavation→Install dewatering system
- Deep small-diameter foundation needed→Drilled shaft or pile
Equipment & Earthwork Operations
- Cut/fill analysis
- Balances earthwork volumes
- Borrow pit
- Imported off-site fill source
- Crane capacity
- Read from load chart
- Outrigger load
- Ground-bearing pressure check
- Dewatering
- Wellpoint or sump control
- Deep foundation install
- Pile or drilled shaft
Temporary Works Sequence
Form, then Falsework, then Shore, then Reshore
Formwork vs Falsework
Formwork
- Shapes fresh concrete
- Resists lateral pressure
Falsework
- Supports structure temporarily
- Used before strength gain
Concrete shape vs structure support
Temporary Structure Selection
- Support wet concrete→Formwork(Shapes fresh concrete)
- Support structure before strength gain→Falsework
- Support excavated soil face→Shoring
- Remove forms before full cure→Reshoring
- Resist lateral wind or seismic→Bracing
- Deep unstable-soil excavation wall→Trench box or sheeting
Temporary Structures
- Formwork
- Shapes and contains concrete
- Falsework
- Temporary structural support system
- Shoring
- Supports excavation or structure
- Reshoring
- Support after early stripping
- Bracing
- Provides lateral stability
- Support of excavation
- Retains adjacent soil face
- Form pressure
- Rises with pour rate
Shoring vs Bracing
Shoring
- Supports excavation walls
- Vertical or lateral loads
Bracing
- Provides lateral stability
- Resists wind or seismic
Soil support vs overall stability
OSHA Trigger Depths
5 ft dig, 6 ft fall, 20 ft engineer
OSHA Trigger Depth/Height
- Excavation reaches 5 feet deep→Protective system required
- Excavation exceeds 20 feet deep→PE-designed system required
- Working at 6 feet high→Fall protection required
- Scaffold platform 10 feet high→Fall protection required
- Ground movement risk exists→Protect regardless of depth
OSHA Construction Thresholds
- Fall protection
- Required at 6 feet
- Excavation protection
- Required at 5 feet
- PE-designed system
- Required beyond 20 feet
- Competent person
- Daily excavation inspections required
- Soil Type A/B/C
- Most to least stable
- Scaffold fall protection
- Required at 10 feet
- MUTCD Part 6
- Temporary traffic control rules
Common Traps
Swell ≠ Shrinkage
Swell: loose volume grows ≠ Shrinkage: compacted volume shrinks
Total Float ≠ Free Float
Total: whole-project delay slack ≠ Free: next-activity delay slack
Formwork ≠ Falsework
Formwork: shapes wet concrete ≠ Falsework: supports temporary structure
CPI ≠ SPI
CPI: measures cost efficiency ≠ SPI: measures schedule efficiency
Total Stress ≠ Effective Stress
Total: includes pore pressure ≠ Effective: controls soil strength
Active Pressure ≠ Passive Pressure
Active: soil moves away ≠ Passive: soil pushed inward
Equated Score ≠ Fixed Percentage
NCEES uses equated scoring ≠ No published cutoff percentage
Last Minute
- 1.80 questions, 8 exam hours
- 2.9-hour appointment includes tutorial and break
- 3.No fixed passing score published
- 4.Support of Loads weighs most
- 5.Operations and Methods rank second
- 6.Fall protection required at 6ft
- 7.Excavation protection required at 5ft
- 8.PE-designed system required beyond 20ft
- 9.Critical path equals zero float
- 10.CV equals EV minus AC
- 11.SPI equals EV over PV
- 12.Swell expands; shrinkage compacts volume
Explore More PE Exams
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
More From This Family
Videos and articles for deeper review.
