Construction
20%of exam
Geotechnical
20%of exam
Structural
20%of exam
Transportation
20%of exam
Water Resources & Environmental
20%of exam
Quick Facts
- Exam
- NCEES PE Civil
- Format
- CBT, 80 questions
- Time
- 9-hour appointment
- Pass score
- Not published (scaled)
- Disciplines
- 5, pick one
- Level
- Professional licensure
- Reference
- Open-book handbook
- Blueprint
- April 2024 specs
CPM Forward and Backward Pass
Forward finds ES/EF, backward finds LS/LF
Loose vs Compacted Volume
Loose (swell)
- After excavation from bank
- Volume increases
- Factor greater than 1
Compacted (shrink)
- After compaction in place
- Volume decreases
- Factor less than 1
Both measured versus bank
Earthwork & Volumes
- Bank volume
- In-place undisturbed soil volume
- Swell factor
- Loose volume over bank volume
- Shrinkage factor
- Compacted volume over bank volume
- Load factor
- Bank volume over loose volume
- Cut/fill balance
- Match earthwork volumes on-site
Total Float vs Free Float
Total float
- Delays entire project finish
- Equals LS minus ES
Free float
- Delays only next activity
- Uses successor's early start
Project-wide vs local delay
CPM Scheduling
- ES/EF
- Early start and early finish
- LS/LF
- Late start and late finish
- Total float
- Late start minus early start
- Free float
- Delay without affecting successor
- Critical path
- Zero-float longest activity path
Estimating & Economics
- Quantity takeoff
- Measure plan quantities method
- Net present value
- Discounted future cash flow
- Break-even analysis
- Cost equals revenue point
- Earned value
- Budgeted cost of work done
- Productivity rate
- Output per labor hour
Temporary Structures & Safety
- Formwork
- Temporary concrete casting mold
- Falsework
- Supports wet concrete or erection
- Shoring
- Vertical excavation support system
- OSHA Type A/B/C
- Soil stability classifications
- 5-ft excavation rule
- OSHA protective system trigger depth
USCS Soil Symbol Logic
Gravel/sand coarse; silt/clay fine soils
Total Stress vs Effective Stress
Total stress
- Includes soil and water weight
- Symbol sigma total
Effective stress
- Grain-to-grain contact stress
- Total stress minus pore pressure
Subtract pore water pressure
Foundation Type Selection
- Shallow, good soil, low load→Spread footing(Bearing capacity governs design)
- Poor soil, high load→Deep foundation(Piles or drilled shafts)
- Very deep bedrock only→Drilled shaft(Cast-in-place, large capacity)
- Vibration-sensitive adjacent site→Drilled shaft(Avoid pile driving vibration)
- Lateral load dominant case→Check lateral capacity(p-y curve analysis)
- Uplift or tension load→Anchor or helical pile(Tension resistance needed)
Soil Classification (USCS)
- GW/GP
- Well-graded or poorly graded gravel
- SW/SP
- Well-graded or poorly graded sand
- ML/CL
- Low-plasticity silt or clay
- MH/CH
- High-plasticity silt or clay
- Plasticity index PI
- Liquid limit minus plastic limit
Bearing Capacity Equation Terms
qult = cNc + qNq + 0.5γBNγ
Shallow vs Deep Foundation
Shallow foundation
- Spread or mat footings
- Governed by bearing capacity
Deep foundation
- Piles or drilled shafts
- Skin friction plus end bearing
Load depth to bearing soil
Bearing Capacity & Settlement
- Terzaghi equation
- qult = cNc+qNq+0.5γBNγ
- Nc, Nq, Nγ
- Bearing capacity factors
- FS bearing
- qult divided by qallow value
- Consolidation settlement
- Time-dependent clay compression process
- Void ratio e
- Void volume over solid volume
Earth Pressure & Retaining Walls
- Ka
- Active earth pressure coefficient
- Kp
- Passive earth pressure coefficient
- K0
- At-rest earth pressure coefficient
- MSE wall
- Mechanically stabilized earth wall
Deep Foundations & Slope Stability
- Skin friction
- Pile shaft side resistance
- End bearing
- Pile tip resistance
- Drilled shaft
- Cast-in-place deep foundation
- Liquefaction
- Saturated sand loses strength
LRFD Load Combination Memory Aid
1.2D + 1.6L usually governs gravity
ASD vs LRFD
ASD
- Service-level loads used
- One combined safety factor
- Required for wood design
LRFD
- Factored loads and resistance
- Separate load and resistance factors
- Common for steel and concrete
Service loads vs factored loads
ASD vs LRFD Method Picker
- Wood design (PE Civil)→ASD(NCEES mandates wood ASD)
- Steel or concrete design→LRFD or ASD(AISC and ACI both allow)
- Retaining wall design→ASD or LRFD(Per NCEES geotechnical spec)
- Deep foundation capacity calc→ASD or LRFD(Candidate's choice, be consistent)
- Bridge design per AASHTO→LRFD(AASHTO LRFD 8th edition)
- Unsure which factor applies→Check question's given units(Nominal vs factored values)
Loads & Load Combinations
- ASCE 7
- Minimum design loads standard
- LRFD combo
- 1.2D + 1.6L governs
- ASD combo
- D + L governs
- Tributary area
- Load-collection floor area
- Seismic load
- Mass times acceleration response
Beam Mechanics & Sections
- Shear diagram
- Slope of moment diagram
- Moment diagram
- Integral of shear diagram
- Section modulus S
- Moment of inertia over c
- Flexure stress
- f = Mc/I formula
- Max deflection
- PL cubed over 48EI
Concrete & Steel Design
- ACI 318
- Concrete design code
- Flexure phi factor
- 0.9 for tension-controlled sections
- AISC Manual
- Steel design reference book
- Development length
- Rebar embedment for bond
Horizontal Curve Point Labels
PC, PI, PT mark curve points
Sag vs Crest Vertical Curve
Crest curve
- High point of curve
- Daytime stopping sight distance
Sag curve
- Low point of curve
- Headlight sight distance governs
Grade change direction differs
Geometric Design
- Curve radius R
- Center to curve distance
- Tangent length T
- PC to PI distance
- Middle ordinate M
- Curve to chord offset
- SSD
- Stopping sight distance
- Superelevation e
- Curve cross-slope rate
Traffic Capacity & Signals
- LOS
- Level of service A-F
- v/c ratio
- Volume over capacity ratio
- PHF
- Peak hour factor
- HCM
- Highway Capacity Manual reference
- Clearance interval
- Yellow plus all-red time
Pavement & Drainage Design
- ESAL
- Equivalent single axle load
- CBR
- California bearing ratio
- Structural number SN
- Flexible pavement thickness index
- Rigid pavement
- PCC slab, AASHTO design
Water Treatment Train Order
Coagulate, flocculate, settle, filter, disinfect
Rational vs SCS/NRCS Method
Rational method
- Small watersheds under 200 acres
- Peak flow rate only
- Simple, fast hand calculation
SCS/NRCS method
- Larger, complex watersheds
- Full runoff hydrograph shape
- Curve number based on soil
Watershed size drives method
Runoff / Hydrology Method Picker
- Small urban watershed (<200 ac)→Rational method(Q=CiA formula)
- Larger or complex watershed→SCS/NRCS method(Curve number based)
- Need full hydrograph shape→Unit hydrograph(Time-distributed flow)
- Storm sewer sizing→Rational plus Manning's(Peak flow, pipe size)
- Detention pond sizing→Hydrograph routing(Inflow vs outflow)
- Stream water quality issue→TMDL analysis(Load allocation study)
Hydrology
- Rational method
- Q = CiA formula
- Runoff coefficient C
- Fraction of rainfall runoff
- Time of concentration Tc
- Longest flow path time
- SCS/NRCS method
- Curve number runoff model
- Design storm
- Return period rainfall event
Manning's vs Hazen-Williams
Manning's equation
- Open-channel gravity flow
- Uses roughness coefficient n
Hazen-Williams
- Pressurized closed-pipe flow
- Uses C coefficient value
Open channel vs pressure pipe
Hydraulics: Open and Closed Conduit
- Manning's equation
- Open-channel velocity flow formula
- Hazen-Williams
- Pressure pipe flow formula
- Darcy-Weisbach
- Head loss friction formula
- Bernoulli equation
- Energy conservation in flow
- Froude number
- Sub vs supercritical flow indicator
Water & Wastewater Treatment
- Coagulation/flocculation
- Particle clumping treatment step
- Sedimentation
- Gravity settling treatment step
- Disinfection
- Pathogen inactivation treatment step
- BOD
- Biochemical oxygen demand
Common Traps
Bank Volume vs Loose Volume
Bank means in-place soil ≠ Loose means after excavation swell
ASD vs LRFD Load Factors
ASD uses service-level loads ≠ LRFD uses factored loads
Total Stress vs Effective Stress
Total includes water weight ≠ Effective subtracts pore pressure
Total Float vs Free Float
Total delays whole project ≠ Free delays only next activity
Rational Method vs SCS Method
Rational suits small watersheds ≠ SCS suits larger watersheds
Wood Design vs Steel or Concrete
Wood must use ASD only ≠ Steel and concrete allow either
Swell Factor vs Shrinkage Factor
Swell is loose over bank ≠ Shrinkage is compacted over bank
Last Minute
- 1.80 questions, 9-hour appointment
- 2.No separate breadth section now
- 3.Choose one discipline exam only
- 4.Wood design always uses ASD
- 5.Steel and concrete allow either
- 6.Rational method: small watershed peak flow
- 7.SCS method: larger watershed hydrograph
- 8.Manning's for open channel flow
- 9.Hazen-Williams for pressure pipe flow
- 10.Effective stress equals total minus pore
- 11.Know handbook table locations cold
- 12.Practice using only electronic reference