Cheat sheet

ASFPM CFM Cheat Sheet

Floodplain Mapping

15–20%of exam

NFIP Regulatory Standards & Regulatory Administrative Procedures

35–45%of exam

Flood Insurance

8–12%of exam

Flood Hazard Mitigation

8–12%of exam

Emergency Preparedness, Response & Recovery

8–12%of exam

Natural and Beneficial Functions

4–8%of exam

Natural Floodplain FunctionsFloodwater storageWetland filtrationHabitat corridors

Overall Context of Floodplain Management

4–8%of exam

Quick Facts

Credential
Certified Floodplain Manager
Exam owner
Association of State Floodplain Managers
Format
120 multiple-choice questions
Time
3 hours
Passing score
84 of 120 correct (70%)
Materials
Closed book
Exam scope
National NFIP minimum standards
Current outline
January 2026 update

Locate, Then Measure

Map the site, profile the height.

FIRM locates the zoneFIS profile gives riverine BFE

FIRM vs FIS

FIRM

  • Shows effective flood zones
  • Locates cross sections and floodways

FIS

  • Explains methods and flood hazards
  • Supplies profiles and data tables

Map location, then read profile

Choose the Map Product

  1. Need parcel zone or floodway→Check effective FIRM and amendments
  2. Need a detailed riverine BFE→Read 1% FIS flood profile(Locate river station)
  3. Survey and map datums differ→Convert to a common datum
  4. Natural ground meets removal criteria→Request LOMA(FEMA determines eligibility)
  5. Fill meets map removal criteria→Request LOMR-F(FEMA determines eligibility)
  6. Completed project changes mapped hydraulics→Request LOMR(Submit as-built evidence)
  7. Proposed project would change hydraulics→Seek CLOMR when applicable(Conditional FEMA review)

Flood Zones

Base flood
1% annual chance of exceedanceIncludes equality
SFHA
Special Flood Hazard Area≥1% annual flood chance
Zone A
No mapped base flood elevations
Zone AE
Mapped base flood elevations
Zone AH
Shallow ponding with mapped elevations
Zone AO
Shallow sheet flowMapped depths where available
Zone VE
Coastal wave hazard with elevations
Shaded Zone X
Moderate mapped flood hazard
Unshaded Zone X
Minimal mapped flood hazard
Zone D
Undetermined flood hazard

Maps and Studies

FIRM
Flood Insurance Rate MapZones and boundaries
FIS
Flood Insurance StudyAnalyses and supporting data
BFE
Base Flood ElevationBase flood water surface
Riverine flood profile
Elevation versus stream distance
Floodway data table
Cross-section elevations and surcharge
Vertical datum
Common reference for elevation comparisons
Hydrology
Estimates flood discharge
Hydraulics
Estimates flood levels and velocities

Map Change Letters

LOMC
Letter of Map ChangeUmbrella term
LOMA
Amendment based on natural ground
LOMR-F
Revision based on placed fill
LOMR
Revision of effective flood mapping
CLOMR
Conditional review of proposed changesFollow with as-built revision

Floor or Frame

AE floors, VE frames.

AE residential lowest floorVE lowest horizontal structural member

AE vs VE Elevation

AE residential

  • Measure lowest floor including basement
  • Elevate at least to BFE

VE construction

  • Lowest horizontal structural member bottom
  • Use pilings or columns

Match the elevation reference point

Screen the Permit

  1. Proposed development in mapped SFHA→Require floodplain development permit
  2. Zone A lacks mapped BFE→Review and use available data
  3. New or substantially improved AE home→Elevate lowest floor to ≥ BFE
  4. AE nonresidential substantial improvement→Elevate or certify dry floodproofing(Target at least BFE)
  5. AO home lacks mapped depth→Elevate lowest floor ≥2 ft(Above highest adjacent grade)
  6. VE new building with BFE→Use piles or columns(Lowest horizontal member bottom ≥ BFE)
  7. Fill proposed within adopted floodway→Require no-rise analysis
  8. Floodway encroachment causes rise→Seek FEMA approval before permitting(Conditional revision under §65.12)
  9. Restoration ratio reaches 50%→Apply substantial improvement standards(Use full restoration cost)

Permit Desk

Permit trigger
Development includes grading and fill
Unnumbered Zone A
Use reasonably available hazard dataReview BFE and floodway data
Larger Zone A developments
Require base flood elevation dataOver 50 lots or 5 acres
Zone A size threshold
Apply whichever threshold is smaller
Riverine watercourse alteration
Notify state and adjacent communitiesBefore alteration or relocation
Altered watercourse
Preserve flood-carrying capacity
Elevation Certificate
Documents building and site elevations
Variance
Exceptional hardship plus minimum reliefApply all §60.6 tests

Value Before

Improvement before work, damage before loss.

Both use structure market valueBoth include exactly 50%

Substantial Improvement vs Damage

Substantial improvement

  • Use cost of proposed work
  • Use structure value before work

Substantial damage

  • Use full restoration cost
  • Use structure value before damage

Both trigger at ≥50%

Elevation and Foundations

AE residential lowest floor
At or above BFEIncludes basement
AE nonresidential structure
Elevate or certify dry floodproofingAt least to BFE
AO residential lowest floor
Mapped depth above highest adjacent gradeDefault 2 ft without depth
AE enclosure openings
Automatically admit and release floodwaterParking, access, storage only
Prescriptive flood openings
≥2 openings and ≥1 in²/ft²Opening bottoms ≤1 ft above grade
VE elevation reference
Lowest horizontal structural member bottomAt or above BFE
VE enclosures
Breakaway walls, lattice, or screeningParking, access, storage only
V-zone building support fill
Prohibited for supporting buildings
Service equipment
Protect against floodwater entry
Freeboard
Safety margin above flood elevation

Floodway Designation vs Encroachment

Floodway designation

  • Reserve channel and adjoining land
  • ≤1 ft base flood surcharge

Encroachment in adopted floodway

  • Test proposed development
  • Default is no base flood rise

Separate mapping from permit review

Floodway Limits

Regulatory floodway
Channel plus reserved adjoining land
Floodway selection
≤1 ft base flood surchargeFederal designation ceiling
AE before floodway designation
≤1 ft cumulative base flood riseExisting and anticipated development
Adopted floodway encroachment
Demonstrate zero base flood riseHydrologic and hydraulic analyses
Increase beyond applicable limit
Seek prior FEMA conditional approvalFollow 44 CFR §65.12

Substantial Damage Math

Substantial improvement (SI)
Improvement cost ÷ pre-work structure value≥50% triggers SI
Substantial damage (SD)
Restoration cost ÷ pre-damage structure value≥50% triggers SD
SD damage cause
Damage can have any origin
SD restoration estimate
Estimate full restoration to pre-damage condition
Land value
Exclude from structure market value
SD classification
Counts as substantial improvementRegardless of repairs performed
Substantial damage example
$60,000 ÷ $120,000 = 50%Restoration ÷ pre-damage structure value

Building vs Contents Coverage

Building coverage

  • Structure and covered fixtures
  • Single-family limit $250,000

Contents coverage

  • Covered belongings inside
  • Single-family limit $100,000

Coverage types have separate limits

Policy and Purchase Rules

SFIP
Standard Flood Insurance Policy
Mandatory purchase
Covered loans on SFHA buildingsParticipating NFIP community
Standard NFIP waiting period
30 days with exceptions
NFIP single-family building limit
$250,000Regular Program
NFIP single-family contents limit
$100,000Regular Program
ICC
Increased Cost of ComplianceUp to $30,000 if eligible
ICC eligible work
Elevation, floodproofing, relocation, demolition
CRS
Community Rating SystemVoluntary premium discount program
NFIP pricing
Property-specific flood risk and characteristics

Stay, Move, Remove

Raise it, move it, or clear the site.

ElevationRelocationAcquisition for open space

Dry vs Wet Floodproofing

Dry floodproofing

  • Keep floodwater out
  • Design for water loads

Wet floodproofing

  • Let floodwater enter and exit
  • Use flood damage-resistant materials

Match method to permitted use

Choose a Mitigation Measure

  1. Keep flood-prone home on site→Consider elevation
  2. Move usable building away→Consider relocation
  3. Permanently clear flood-prone parcel→Consider voluntary acquisition(Maintain open space)
  4. Seal eligible nonresidential building→Evaluate certified dry floodproofing(Check zone and loads)
  5. Compare avoided losses with costs→Run benefit-cost analysis

Mitigation Tools

Hazard mitigation
Long-term reduction of future losses
Elevation
Raise occupied floors and utilities
Relocation
Move structure to safer site
FEMA open-space acquisition
Voluntary buyout with perpetual open space
Dry floodproofing
Seal structure against floodwater entry
Wet floodproofing
Admit water to equalize pressure
Benefit-cost ratio
Present-value benefits ÷ present-value costs≥1.0 is cost-effective
Mitigation plan
Assess hazards and prioritize projects

Flood Watch vs Flash Flood Warning

Flood Watch

  • Flooding is possible
  • Prepare and monitor alerts

Flash Flood Warning

  • Flash flooding imminent or occurring
  • Move immediately to higher ground

Watch prepares, warning prompts action

Choose the Emergency Action

  1. Flood Watch issued→Get ready and monitor updates
  2. Flash Flood Warning in flood-prone area→Move immediately to higher ground
  3. Multiple agencies responding on scene→Coordinate through ICS
  4. Need federal declaration evidence→Conduct preliminary damage assessment
  5. Damaged building seeks repair permit→Screen for substantial damage

Emergency Operations and Recovery

EOP
Emergency Operations PlanRoles and coordinated actions
NIMS
National Incident Management SystemCommon incident management framework
ICS
Incident Command SystemOn-scene management structure
StormReady
National Weather Service readiness recognition
Flood Watch
Flooding is possible
Flash Flood Warning
Flash flooding imminent or occurring
Preliminary damage assessment
Supports disaster declaration decisions
Local substantial damage determination
Triggers floodplain compliance review
Individual Assistance
Support for eligible disaster survivors
Public Assistance
Aid for eligible public/nonprofit applicants
DRRA Section 1206
Reimburses eligible post-disaster enforcement costsBuilding codes and floodplain ordinances

Natural Floodplain Functions

Floodwater storage
Temporarily holds overflow
Conveyance
Carries floodwater downstream
Groundwater recharge
Infiltration replenishes aquifers
Wetland filtration
Retains sediment and some pollutants
Riparian vegetation
Stabilizes banks and limits erosion
Habitat corridors
Connect aquatic and terrestrial habitats

Federal Minimums vs Local Standards

Federal NFIP minimum

  • National exam baseline
  • Standards for participating communities

State or local standard

  • May require added freeboard
  • Apply stricter enacted requirements locally

Identify jurisdiction before choosing

Floodplain Management Roles

NFIP
National Flood Insurance Program
FEMA
Administers NFIP and issues maps
State NFIP coordinator
Supports communities with technical assistance
Participating community
Adopts and enforces local ordinance
Community ordinance
Implements applicable floodplain development standards
No Adverse Impact
Avoid shifting risk to others

Common Traps

Flood Recurrence

1% chance each year ≠ One flood every 100 years

Map Status

CLOMR conditional findings ≠ Effective map revision

AE Floodway Permit

Zero rise in adopted floodway ≠ One-foot floodway designation limit

Residential Floodproofing

AE residential lowest-floor elevation ≠ AE nonresidential dry floodproofing option

Substantial Damage Denominator

Pre-damage structure market value ≠ Combined land and building value

Disaster Assessments

Preliminary damage assessment for declaration ≠ Substantial damage determination for compliance

Insurance vs Permit

Flood insurance coverage ≠ Local development permit approval

Last Minute

  1. 1.Base flood has 1% annual chance
  2. 2.Use effective maps and amendments
  3. 3.Match datums before comparing elevations
  4. 4.AE residential elevation uses lowest floor
  5. 5.VE measures lowest horizontal member underside
  6. 6.Adopted floodway defaults to no-rise
  7. 7.Substantial damage includes exactly 50%
  8. 8.Damage ratio uses pre-damage structure value
  9. 9.NFIP waiting period usually 30 days
  10. 10.A Flood Watch means prepare
  11. 11.Flash Flood Warning means act immediately
  12. 12.Floodplains store and convey floodwater