Skilled Trades9 min read

AMPP CIP Level 1 Practical Exam Stations and Lab Drills

See AMPP’s eight CIP Level 1 practical stations, what to write down at each one, and how to rehearse the final ten-minute review.

OpenExamPrep TeamNovember 17, 2026

✓Key Facts

  • •AMPP’s closed-book CIP Level 1 practical exam consists of eight hands-on stations worth 100 points in total.
  • •AMPP administers the CIP Level 1 practical on the final day of its Basic Coatings Inspector course.
  • •AMPP allows candidates a maximum of 10 minutes at each station on the CIP Level 1 practical exam.
  • •AMPP’s CIP Level 1 practical gives candidates 10 additional minutes for calculations and review without access to instruments.
  • •Environmental testing, anchor profile, and Type II dry film thickness account for 60 points of AMPP’s CIP Level 1 practical.
  • •AMPP’s CIP Level 1 practical tests Type I magnetic pull-off and Type II constant-pressure thickness gauges at separate stations.
  • •AMPP’s CIP Level 1 practical has separate stations for high-voltage DC and low-voltage wet-sponge holiday detection.
  • •AMPP’s CIP retake policy requires candidates who fail the Level 1 practical to register again for the associated course.
  • •AMPP reports the CIP Level 1 practical outcome as pass or fail in its Certification Portal.

AMPP gives the CIP Level 1 practical exam on the final day of the Coating Inspector Program course. It’s closed book, with eight hands-on stations worth 100 points. Allow for up to 10 minutes at each station and another 10 minutes at the end for calculations and review. You can finish arithmetic in that last window if you have the readings. Instrument use ends with the stations. AMPP posts the result as pass or fail in its Certification Portal. AMPP certification page · AMPP practical exam guide

If lab time is tight, start with environmental testing, anchor profile, and Type II dry film thickness. Together they account for 60 of the 100 points. Run each through to a written result, then rehearse the other five stations. The practical is one of two required exams. See the CIP Level 1 exam guide for the separate theory test and credential requirements. AMPP theory preparation guide

The eight CIP Level 1 practical exam stations

The order and points below come from the English practical guide in AMPP’s current directory. The last column gives a practice target for each station. During the exam, follow the station instructions for the actual method, readings and format. AMPP exam guide directory

StationPointsWhat to practice recording
1. Environmental test20Air and steel temperatures, relative humidity, dew point, and the steel-to-dew-point difference
2. Anchor profile with comparators and replica tape20Comparator type and grade, tape grade, reader mode, and profile result with units
3. High-voltage DC holiday detection10Test voltage and the locations of any indications on the practice panel
4. Type I magnetic pull-off coating thickness10Raw readings, base metal reading if applicable, and the corrected dry film thickness
5. Low-voltage wet-sponge holiday detection10Detector check and the location of each repeatable indication
6. Wet film thickness5Last wetted and first dry comb markings, with units
7. Type II constant-pressure probe coating thickness20Reference check, units, and individual dry film thickness readings by location
8. Soluble salts5Test location, method and result, including the difference between conductivity and surface density

Where to spend your first lab repetitions

Station 1. Keep the steel temperature and air temperature distinct

Label both temperatures before taking readings. The margin you compare with the exercise requirement is surface temperature minus dew point. Record air temperature and relative humidity alongside the steel temperature so you can identify the conditions at the time of the test. If an electronic meter displays the difference, use a practice round to calculate it from the two individual readings and check that the units agree. With a psychrometer in class, ask to practice using the wet- and dry-bulb readings to obtain relative humidity and dew point. Use the assigned limit for the exercise. On a coating job, the governing project documents establish the applicable limits. DeFelsko environmental measurements · AMPP coating specification guidance

Station 2. Write down what the profile instrument actually measured

A surface-profile comparator gives you a reference for grading blast roughness. Match the comparator to the abrasive where the method calls for it, then record the comparator and the grade you observe. With replica tape, pick the appropriate grade, practice making an even impression, and record how the reader handles the backing. Some readers incorporate the backing correction. If the display already gives a corrected profile, copy that value with its units. When the exercise supplies a raw total and asks for a backing correction, apply it once. Follow any additional conversion steps prescribed for the tape and instrument used in the lab. Elcometer comparator manual · Testex replica tape instructions

Stations 4 and 7. Rehearse two different dry film thickness checks

On the Type I mechanical gauge, you read the thickness at the point when the magnet releases. Verify the gauge on the appropriate reference. If your method calls for a base metal reading on representative bare steel, save it separately and apply the prescribed correction to the coated readings. In this setup, the correction is made to the recorded result. FHWA coatings lab manual

On the Type II electronic gauge, verify the readings against the reference called for by the method. Practice any adjustment your instructor specifies for the substrate and then use the probe to take readings at labeled locations. Record the values and units as you go. If a station asks for an average, keep the inputs together by location and retain them even if you work out the average during review. A reference check tells you whether the gauge reads a known thickness accurately. An adjustment sets up the gauge for a particular measurement condition. In the lab, ask what to do when the reference check fails and rehearse that decision before measuring the panel. DeFelsko coating-thickness gauge checks

Holiday detection, wet film thickness and salts

Stations 3 and 5. Keep the two holiday detector routines distinct

A holiday is a gap through the protective coating that leaves the substrate exposed. The practical has a dedicated high-voltage DC station and a separate low-voltage wet-sponge station. Use supervised lab time to practice identifying which instrument you have, checking it on the training setup, and recording where it responds. Keep any powered high-voltage rehearsal under the instructor’s supervision. Use the specified test setting and the instrument’s safe setup and shutdown procedure. For the wet sponge, practice tracing the path from the damp sponge through a discontinuity to the conductive substrate and back through the ground lead. If you hear an alarm during a drill, mark where it occurred so your instructor can verify your finding. AMPP holiday terminology · DeFelsko high-voltage manual · DeFelsko wet-sponge manual

Station 6. Capture the wet-film comb’s two endpoints

Read the comb while the marks from the fresh coating are clear. Identify the last wetted tooth and the adjacent dry tooth on the same scale. The two markings bracket the approximate wet film thickness. Save both in practice so you can report the interval or the particular value requested by the prompt. This measurement concerns the film immediately after application. You use a dry film gauge for the finished coating. Elcometer wet-film comb guide · AMPP wet-film terminology

Station 8. Check the units on a soluble-salt test

If the lab uses a Bresle-type extraction, the liquid picks up water-soluble salts from a defined area. Practice identifying the background conductivity, the conductivity of the recovered solution and the result the meter reports. A reading in µS/cm is conductivity. A reading in mg/m² is mass per unit area. If the prompt supplies a limit in mg/m², you need the surface-density result from the assigned method. Record the location and sample result while you still have them in front of you. DeFelsko soluble salt tester manual

A ten-minute station rehearsal

Start with one untimed run on each instrument in the lab. Have a partner or instructor identify the first step you missed or the first point where a reading became unreliable. Correct that step, then try the same skill on a different marked location or practice panel with a ten-minute timer.

  1. Minute 0–1. Read the task. Identify what you must deliver, how many results the task requests, and the units it expects. Note whether it provides a limit or asks for observations only.
  2. Minutes 1–8. Set up and verify the equipment as instructed. Take and record each observation or measurement as it happens. If you lose time on a lab run, identify whether the delay came from finding the correct instrument setting, taking the measurement or working out what to record.
  3. Minutes 8–10. Finish the measurement work and check the record against the task. Is the location clear? Did you write the units? Can you tell a raw value from an adjusted one? Leave the instrument as directed.
  4. After rotating. In a multi-station rehearsal, set aside one final ten-minute window to calculate or check results using only the information you already captured. Label any unavailable measurement as a gap in your practice log and repeat that station at your next lab opportunity.

These time splits are for practice. During a timed lab, follow the safe working sequence even if it takes the full window. Before the next repeat, fix the first missed step and rerun the station from the start.

Try this paper drill before class

Copy the practice observations below. Then give yourself ten minutes to write the results as if the instruments were already put away. The numbers and limits are invented for practice.

StationPractice observations and task
Environmental testSteel is 16 °C, air is 22 °C, and dew point is 14 °C. The exercise requires steel at least 3 °C above dew point. Calculate the margin and compare.
Anchor profileThe reader displays 3.3 mils as a corrected profile. The tape backing is listed as 2.0 mils. Record the profile to report.
Type I dry film thicknessThe gauge reading is 8.1 mils. The exercise asks you to subtract a 0.7-mil base metal reading. Record the corrected result.
Type II dry film thicknessThree readings at one location are 7.2, 7.5 and 7.8 mils. The probe is already set for the measurement, and the prompt asks for their mean.
Wet film thicknessThe last wetted comb tooth is marked 175 µm and the next dry tooth is marked 200 µm. Report the bracket.
Soluble saltsThe display gives 18 µS/cm as the conductivity change and 22 mg/m² as the surface density. The exercise limit is 25 mg/m². Select the result and compare.

Check your answers. The environmental margin is 2 °C, which falls 1 °C short of the exercise requirement. The corrected profile is 3.3 mils. The Type I result is 7.4 mils after subtracting the base metal reading. The Type II mean is 7.5 mils. The comb brackets the wet film thickness between 175 and 200 µm. The salt surface density is 22 mg/m², which is 3 mg/m² below the exercise limit.

For the two holiday detector stations, sketch a panel and ask a partner to point to two simulated alarms while you mark and label the locations. For the classroom repeat, have your instructor check whether your recorded marks match the indications on the lab panel. Grade your rehearsal by whether each result has a location or sample ID, the relevant units, and enough information to reconstruct any calculation. An incorrect result tells you which step to repeat.

If you need to retake the practical

If you only failed the practical and already passed the theory exam, AMPP says you can keep the theory pass. Contact AMPP Customer Support to arrange the retake. The CIP-specific retake policy requires registration for the associated course again, and the July 2026 fee schedule lists the practical exam fee as included in the course fee. Ask AMPP for the cost, any available discount, and the next course date that works with your certification deadline. AMPP exam FAQ · AMPP retake policy · AMPP fee schedule

Before your next lab, use the free CIP Level 1 study guide to review the particular instrument or measurement you missed. Use the free CIP Level 1 practice questions to check written recall. Then repeat the lab task on a fresh location and see whether someone else can work out exactly what you measured from your record.

AMPP CIP Level 1Basic Coatings InspectorPractical ExamCoating InspectionDry Film ThicknessSurface Profile

Related Articles

Stay Updated

Get free exam tips and study guides delivered to your inbox.

Free exam tips & study guides. Unsubscribe anytime.