8.1 Excavation Safety, Shoring, Battering & Underground Services (CR 13)
Key Takeaways
Construction Regulation 13(1) requires all excavation work to be supervised by a competent person appointed in writing and the ground stability to be evaluated before work begins.
CR 13(2)(b) bars anyone from working in an excavation that is not adequately shored or braced, unless it is sloped to the angle of repose or is stable ground with written permission (an engineer or technologist decides if doubt remains); there is no depth threshold.
CR 13(2)(d) prohibits placing loads, materials, plant or spoil near the edge where they may cause collapse unless shoring is provided; CR 13(2)(f) requires access no further than 6 m from any worker.
CR 13(2)(h) requires inspection daily before each shift and after blasting, an unexpected fall of ground, damage to supports, or rain, recorded in a register on site.
CR 13(2)(i) requires a barrier at least 1 m high and warning lights where the public may be endangered, and CR 13(2)(j) applies the General Safety Regulations' confined-space precautions to anyone entering an excavation.
1. Statutory Framework and Competent Supervision (CR 13(1))
Excavation work is among the most hazardous construction activities: trench collapses, strikes on buried electrical cables and gas mains, undermining of neighbouring structures, and toxic or oxygen-deficient atmospheres all cause deaths. CR 1 defines excavation work as the making of any man-made cavity, trench, pit or depression formed by cutting, digging or scooping. Any excavation work also requires a notification to the provincial director at least 7 days beforehand where no construction work permit applies (CR 4(1)(a)).
Construction Regulation 13(1) requires the contractor to:
- (a) ensure that all excavation work is carried out under the supervision of a competent person appointed in writing for that purpose; and
- (b) evaluate, as far as reasonably practicable, the stability of the ground before excavation work begins.
The Construction Health and Safety Manager should check the appointee's letter, training and experience, because every later duty in CR 13 depends on that person's judgement.
2. Preventing Collapse: Shoring, Bracing or Sloping (CR 13(2)(a)–(c))
A contractor performing excavation work:
- (a) must take reasonable and sufficient steps to prevent any person being buried or trapped by a fall or dislodgement of material;
- (b) may not require or permit anyone to work in an excavation that has not been adequately shored or braced, unless:
- (i) the sides are sloped to at least the maximum angle of repose measured from the horizontal (CR 1 defines the angle of repose as the steepest angle at which loose or fragmented material will remain stationary in a pile); or
- (ii) the excavation is in stable material, but only where the appointed competent person has given written permission after evaluating the site conditions, and, where any uncertainty about soil stability remains, the decision of a professional engineer or professional technologist competent in excavations is decisive and must be recorded in writing and signed by both; and
- (c) must ensure that the shoring or bracing is designed and constructed strongly enough to support the sides of the excavation.
There is no depth threshold in CR 13: a 1.2-metre trench in running sand can kill. US OSHA soil-type tables (Type A, B and C soils with set slope ratios) are sometimes quoted on South African sites, but they are not South African law; slopes and support must follow the competent person's evaluation and, where needed, geotechnical or engineering advice.
Typical support systems include hydraulic or screw-strutted trench shields and boxes, timber or steel close-sheeting with walings and struts, slide-rail systems for deeper excavations, soldier piles and lagging, and steel sheet piling where groundwater or running sand is present. Each must be installed before people enter the unsupported section.
3. Loads near the Edge and Adjacent Structures (CR 13(2)(d)–(e))
- (d) No load, material, plant or equipment may be placed or moved near the edge of an excavation where it may cause collapse and endanger anyone, unless precautions such as sufficient and suitable shoring or bracing are taken. The regulation sets no fixed distance; client specifications commonly require spoil to be kept at least 1 m back, and further for deep excavations, soft ground or heavy plant.
- (e) Where the stability of an adjoining building, structure or road is likely to be affected, steps must be taken to ensure its stability and the safety of persons (underpinning, sheet piling, monitoring).
CR 23(1)(g) adds that construction vehicles and mobile plant must be prevented from falling into excavations, for example by edge protection, crash barriers or stop blocks along approach routes.
4. Access and Egress (CR 13(2)(f))
Convenient and safe means of access must be provided to every excavation in which people work, and that access may be no further than 6 metres from the point where any worker in the excavation is working. Along a continuous trench, that means a ladder or ramp at least every 12 metres. Ladders should be secured at the top and bottom and extend about a metre above the edge to give a handhold.
5. Underground Services (CR 13(2)(g))
The contractor must ascertain, as far as reasonably practicable, the location and nature of electricity, water, gas or other services that may be affected, and, before starting excavation work that may affect them, take the steps necessary to make the circumstances safe (CR 24(a) imposes a matching duty for electrical cables). Good practice is a four-stage clearance:
- Records and wayleaves: obtain service records and wayleave approvals from the municipality, Eskom, telecommunications and pipeline owners, treating drawings as indicative.
- Detection: scan with a cable avoidance tool and signal generator (power, radio and signal modes), and ground-penetrating radar for non-metallic services.
- Exposure: expose services by hand digging with suitable tools or by vacuum excavation; keep mechanical excavation outside the distance specified in the wayleave conditions until the service is located.
- Protection: support exposed services across the trench and isolate live services through the owner's permit-to-work system where work must come close.
6. Inspection and Register (CR 13(2)(h))
Every excavation, including all bracing and shoring, must be inspected by the competent person appointed under CR 13(1):
- daily, before the start of each shift;
- after every blasting operation;
- after an unexpected fall of ground;
- after damage to supports; and
- after rain.
The results must be recorded in a register kept on site and made available on request to an inspector, the client, the client's agent, any other contractor or any employee. Tension cracks, bulging, seepage, slumping or strut movement mean immediate withdrawal of workers until the excavation is made safe.
7. Protecting the Public and Warning People (CR 13(2)(i) and (l))
Every excavation that is accessible to the public, adjacent to public roads or thoroughfares, or where people's safety may be endangered must be:
- adequately protected by a barrier or fence at least one metre high, as close to the excavation as practicable; and
- provided with warning illuminants or other clearly visible boundary indicators at night or when visibility is poor,
or other suitable and sufficient precautions must be taken where these are not practicable. Barrier tape is a visual warning, not a barrier. CR 13(2)(l) also requires warning signs next to any excavation where people are working, inspecting or testing.
8. Atmospheric Hazards (CR 13(2)(j))
Excavations can trap gases: hydrogen sulphide and carbon dioxide (heavier than air) near sewers and organic ground, carbon monoxide from engines near the edge, methane from landfill or gas mains, and solvent vapours on contaminated land. CR 13(2)(j) requires the precautions for confined spaces in the General Safety Regulations to be complied with by any person entering any excavation where they apply. Under General Safety Regulation 5, that means the air must be tested and evaluated by a competent person who certifies in writing that the space is safe; where oxygen is or may be below 20% by volume or a hazardous gas may be present, the space must be purged and ventilated (and isolated from pipes and communicating openings), or entrants must use approved breathing apparatus with a harness and lifeline and an attendant trained in resuscitation outside. Flammable gas may not exceed 25% of the lower explosive limit where the work creates no ignition source, or 10% for other work. Engines should never run in or close to an excavation.
9. Explosives (CR 13(2)(k))
Where excavation involves explosives, the contractor must appoint a person competent in the use of explosives for excavation, who must develop a method statement in accordance with the applicable explosives legislation.
10. Summary Matrix
| Duty | CR 13 reference | Key point |
|---|---|---|
| Competent supervisor appointed in writing | 13(1)(a) | Every excavation, any depth |
| Evaluate ground stability | 13(1)(b) | Before work begins |
| Shore, brace or slope | 13(2)(b)–(c) | Exceptions only for angle of repose or written-permission stable ground |
| Loads near edge | 13(2)(d) | Prohibited where they may cause collapse unless shored |
| Adjacent structures and roads | 13(2)(e) | Ensure their stability |
| Access | 13(2)(f) | No further than 6 m from any worker |
| Services | 13(2)(g) | Locate and make safe before work |
| Inspections | 13(2)(h) | Daily, after blasting, falls of ground, damaged supports, rain; register |
| Public protection | 13(2)(i), (l) | Barrier ≥1 m; warning lights; signs |
| Atmosphere | 13(2)(j) | General Safety Regulation confined-space precautions |
| Explosives | 13(2)(k) | Competent person; method statement |
A civil contractor is trenching a 2.8-meter deep sewer pipe trench through medium silty clay (Type B soil). To maximize cycle times, the site foreman deposits excavated spoil directly along the edge of the trench, creating a 1.8-meter high spoil heap whose toe rests 300 mm from the cut face. Additionally, a 22-tonne excavator operates with its tracks 800 mm from the trench lip. Which statutory provision of Construction Regulation 13 has been directly breached, and what is the primary geotechnical hazard?
The contractor has complied with Construction Regulation 13 because spoil heaps act as protective gravity berms that stabilize the trench crest against tension cracks.
The contractor has breached Construction Regulation 13(1)(a) solely because a 22-tonne excavator requires an ECSA-registered Lifting Machinery Inspector certificate to operate near excavations.
It breaches CR 13(2)(d): spoil and plant near the edge surcharge the wall, which is prohibited unless precautions such as shoring are taken.
The contractor has breached Construction Regulation 13 only if the trench depth exceeds 4.0 meters, which requires a registered professional geotechnical engineer on site.
During road widening operations in an urban area, a contractor needs to excavate a 1.6-meter deep stormwater culvert trench across an alignment where municipal as-built drawings show an energized 11kV electrical cable servitude. The earthworks team uses a 20-tonne hydraulic tracked backhoe excavator to dig within 1.0 meter of the marked alignment without prior scanning or hand digging, striking the cable and causing an explosive arc flash. Under Construction Regulation 13(2)(h) and standard industry clearance protocols, what was the required procedure?
Mechanical excavation is permitted within utility servitudes provided the Excavation Supervisor conducts a continuous gas test under General Safety Regulation 5.
The contractor satisfied their legal obligations by reviewing the municipal as-built drawings, which transfer full liability for cable strikes to the local municipality under Section 37(2) of the OHS Act.
Mechanical excavation is legally permitted up to 500 mm from energized high-voltage cables provided the backhoe bucket is fitted with rubber teeth and the operator wears 1000V insulating gloves.
CR 13(2)(g): locate the cable and make it safe before digging, by detecting and hand- or vacuum-exposing it and keeping plant away.
Workers are installing precast concrete pipes inside a continuous 2.2-meter deep, shored trench that extends 60 meters in length through an old industrial chemical site. The contractor provides a single access ladder at the extreme eastern end of the trench. Workers report smelling sweet, pungent solvent fumes at the trench invert. What statutory non-compliances under Construction Regulation 13 and General Safety Regulation 5 must the Construction Health and Safety Manager immediately address?
It breaches CR 13(2)(f) (access within 6 m of every worker) and CR 13(2)(j), which requires GSR 5 precautions because vapour may be present.
The contractor must convert the excavation into an open quarry under the Mine Health and Safety Act to bypass the 6-meter ladder travel distance rule.
The contractor has complied with access rules because one ladder per 60 meters is permitted, but the workers must be issued standard paper dust respirators to filter chemical solvent fumes.
The contractor only needs to install an emergency escape siren at the western end and continue work until the daily shift concludes.
Sections you finish are checked off in the contents.