7.2 Utah State Construction Registry (SCR): Filings & Preliminary Notices

Key Takeaways

  • The State Construction Registry is created by Utah Code § 38-1a-201 inside Title 38, Chapter 1a (Preconstruction and Construction Liens); it is overseen by the Division of Professional Licensing with the assistance of a contracted designated agent under § 38-1a-202.
  • Title 38, Chapter 1b is titled 'Government Construction Projects' and governs only government work — its notice of commencement under § 38-1b-201 has no private-project counterpart.
  • On a private project, the city, county, or town that issues a building permit must transmit the permit information to the registry within 15 days under § 38-1a-205(1)(a), and the original contractor must conspicuously post a copy of the permit at the project site.
  • Under Utah Code § 38-1a-501(1)(a) a claimant who does not contract directly with the owner must file a preliminary notice with the registry within 20 days of commencing construction work; a late notice takes effect only five days after filing, and it has no effect at all if filed more than 10 days after a notice of completion.
  • Utah Code § 38-1a-506 requires a notice of intent to obtain final completion at least 45 days before a notice of completion on nonresidential projects longer than 120 days with an original contract price over $500,000 and no payment bond, and preliminary claimants must amend within 20 days.
Last updated: September 2026

Utah State Construction Registry (SCR): Filings & Preliminary Notices

Quick Reference: The Utah State Construction Registry (SCR) is created by Utah Code § 38-1a-201, inside Title 38, Chapter 1a (Preconstruction and Construction Liens). It is overseen by the Division of Professional Licensing (DOPL) with the assistance of a contracted designated agent (§ 38-1a-202) and serves as the central repository for all required construction notices. Key filings: on a private project the permitting city, county, or town transmits building permit information to the registry within 15 days of issuing the permit (§ 38-1a-205); on a government project the original contractor, owner, or owner-builder files a notice of commencement within 15 days after physical construction work commences (§ 38-1b-201); a preliminary notice is filed within 20 days of commencing work (§ 38-1a-501); a notice of intent to obtain final completion is filed at least 45 days before a notice of completion on qualifying commercial jobs (§ 38-1a-506); and a notice of completion is filed under § 38-1a-507. A late preliminary notice takes effect only 5 days after filing, permanently barring lien claims for everything furnished before that effective date.


1. Statutory Purpose & Administration of the SCR

Prior to the creation of the State Construction Registry, Utah construction projects operated under an opaque "hidden lien" system. Property owners and construction lenders rarely knew which specialty subcontractors or material suppliers were working on a site. When a general contractor diverted funds, owners faced surprise mechanics' liens from unknown suppliers delivered via certified mail.

To solve this vulnerability, the Utah Legislature created the State Construction Registry (SCR) in Utah Code § 38-1a-201, inside Title 38, Chapter 1a. The SCR is an automated, web-based electronic database that, by statute, must be overseen by the division with the assistance of the designated agent, provide a central repository for all required notices, accept both electronic filings and filings by alternate means such as U.S. mail or telefax, deliver electronic notification to up to three email addresses per interested person, and print date- and time-stamped receipts. The division is the Division of Professional Licensing (DOPL) within the Utah Department of Commerce, and § 38-1a-202 directs the division to contract with an approved third-party vendor that serves as the designated agent and actually operates the site.

Chapter Trap: Title 38, Chapter 1b is titled Government Construction Projects. It borrows the registry and applies parallel notice rules to state, county, city, town, school district, and special district work. It is not where the SCR is created, and its notice of commencement requirement does not reach private jobs. If a question mentions a private commercial or residential project, the controlling chapter is 1a.

┌────────────────────────────────────────────────────────────────────────┐
│               UTAH STATE CONSTRUCTION REGISTRY (SCR)                   │
├────────────────────────────────────────────────────────────────────────┤
│ Administered by: DOPL (Utah Department of Commerce)                    │
│ Created By:      § 38-1a-201 (Ch. 1a); Ch. 1b = government projects    │
│ Accessibility:   24/7 Electronic Public Portal (www.scr.utah.gov)      │
├────────────────────────────────────────────────────────────────────────┤
│ Core Functions:                                                        │
│ 1. Centralizes project building permits and commencement notices.      │
│ 2. Mandates electronic preliminary notices from all trade tiers.      │
│ 3. Eliminates paper mailings and formal process service for notices.   │
│ 4. Provides real-time email alerts to owners, lenders, and GCs.        │
│ 5. Shortens lien windows via electronic Notice of Completion.          │
└────────────────────────────────────────────────────────────────────────┘

Benefits Across Project Participants

  • For Property Owners: Complete transparency into every entity furnishing labor or materials on their real estate, preventing double-payment surprises.
  • For General Contractors: Real-time visibility into lower-tier subcontractors and material vendors to verify joint check requirements and lien waiver compliance before disbursing progress payments.
  • For Subcontractors & Suppliers: A reliable, low-cost ($6 standard state fee) electronic method to preserve statutory mechanics' lien and payment bond rights without expensive legal service.
  • For Construction Lenders & Title Insurers: A definitive public record to verify outstanding payment exposures before approving construction loan disbursements.

2. Key SCR Filings: Procedural Hierarchy & Deadlines

The SCR process follows a logical sequence mirroring the progression of a building project from initial permitting to certificate of occupancy.

┌─────────────────────────────────────────────────────────────────────────┐
│                     SCR FILING CHRONOLOGY                               │
├─────────────────────────────────────────────────────────────────────────┤
│ 1. Building Permit Issued by Local Municipality                         │
│                             │                                           │
│ PRIVATE JOB — within 15 days of ISSUING the permit:                     │
│                             ▼                                           │
│         City/County transmits permit info (§ 38-1a-205(1)(a))           │
│         GC posts a copy of the permit at the site (§ 38-1a-205(2))      │
│                                                                         │
│ GOVERNMENT JOB — within 15 days of PHYSICAL WORK STARTING:              │
│                             ▼                                           │
│         Notice of Commencement (§ 38-1b-201)                            │
│         (Filed by original contractor, owner, or owner-builder)         │
│                             │                                           │
│ Within 20 Days of Mobilizing: ▼                                         │
│                     Preliminary Notice (§ 38-1a-501)                    │
│                     (Filed by Subcontractor / Supplier)                 │
│                             │                                           │
│ During Construction (If Refinancing):                                   │
│                     Notice of Intent to Finance (§ 38-1a-601)           │
│                     └──► Claimant files Notice of Remaining to Complete │
│                             │                                           │
│ At Least 45 Days Before Final Completion (Commercial >$500k, >120 days):│
│                     Notice of Intent to Complete (§ 38-1a-506)          │
│                     └──► Claimants file remaining balance within 20 days│
│                             │                                           │
│ Upon Final Completion:      ▼                                           │
│                     Notice of Completion (§ 38-1a-506)                  │
│                     (Shortens lien recording window from 180 to 90 days)│
└─────────────────────────────────────────────────────────────────────────┘

Comprehensive SCR Filing Breakdown Matrix

Filing InstrumentGoverning StatuteWho Typically FilesStatutory DeadlinePrimary Legal Purpose & Effect
Building permit transmission (private projects)§ 38-1a-205(1)(a)The county, city, or town that issues the permitWithin 15 days after issuing the building permitPuts the private project into the registry and supplies the permit entry number that preliminary notices link to. The original contractor must also post a copy of the permit at the site.
Notice of Commencement (government projects only)§ 38-1b-201Original contractor, owner, or owner-builderWithin 15 days after commencement of physical construction work at the siteEstablishes the government project on the SCR and triggers assignment of the unique project number.
Preliminary Notice (Pre-Notice)§ 38-1a-501Subcontractors, sub-subcontractors, equipment lessors, material suppliersWithin 20 calendar days after first furnishing labor or materialsEssential prerequisite to perfect a construction lien; preserves lien rights back to the first day of work.
Notice of Intent to Complete§ 38-1a-506Property Owner or General ContractorAt least 45 calendar days before filing Notice of CompletionMandatory on commercial nonresidential projects >$500k, duration >120 days, without a payment bond; flushes out unpaid balances.
Notice of Remaining to Complete§ 38-1a-506 / § 38-1a-602Preliminary notice claimants holding unpaid balancesWithin 20 calendar days after Notice of Intent to Complete or FinanceDiscloses remaining contract value and unpaid sums to owner, GC, or prospective lender to preserve lien priority and claims.
Notice of Intent to Finance§ 38-1a-601Property Owner or Construction LenderAt least 14 calendar days prior to anticipated loan closingAlerts preliminary claimants that a loan is closing; forces claimants to state unpaid balances.
Notice of Completion§ 38-1a-506Property Owner, General Contractor, or LenderUpon or after final project completionOfficially marks completion; cuts the lien recording window from 180 days to 90 days.

3. Getting a Project Into the Registry: Two Different Tracks

Utah does not use one universal "notice of commencement." How a project enters the registry depends on whether it is private or governmental, and the exam tests the difference.

Track 1 — Private Projects: Building Permit Transmission (§ 38-1a-205)

For a private project there is no notice of commencement at all. Instead:

  • The county, city, or town issuing the building permit must, no later than 15 days after issuing the permit, input the building permit application and transmit the permit information to the registry electronically (§ 38-1a-205(1)(a)(i)).
  • The jurisdiction may collect the permit fee but may not spend or use it until it has complied with that transmission duty (§ 38-1a-205(1)(a)(ii)) — a real enforcement lever, because it puts the city's own revenue at risk.
  • The permit applicant is responsible for the accuracy of the information in the building permit (§ 38-1a-205(1)(b)).
  • At the time the permit is obtained, each original contractor must conspicuously post a copy of the building permit at the project site (§ 38-1a-205(2)).

The practical effect is that the permit's entry number becomes one of the identifiers a subcontractor can use to link its preliminary notice to the right project under § 38-1a-501(1)(h)(vii)(D).

Track 2 — Government Projects: Notice of Commencement (§ 38-1b-201)

On a government project — state, county, city, town, school district, special district, special service district, community reinvestment agency, or other political subdivision — the original contractor, owner, or owner-builder must file a notice of commencement with the registry no later than 15 days after commencement of physical construction work at the site. Note the trigger: physical work starting, not permit issuance.

The notice must include the owner's and original contractor's names, addresses, and email addresses; the surety and payment bond information, or a statement that no payment bond was required; the project property address or a description of its location; and the government project-identifying information. The designated agent assigns each government project a unique project number, and duplicate notices are combined and relate back to the earliest-filed one.

The Government-Project Excusal (§ 38-1b-201(7) and § 38-1b-202(8))

If the notice of commencement on a government project is not filed within the 15-day window:

  • Sections 38-1b-202 and 38-1b-203 do not apply to the project (§ 38-1b-201(7)), which switches off the government preliminary notice and notice of completion machinery.
  • A person who provides construction work before the notice of commencement is filed need not file a preliminary notice to preserve rights, if the notice of commencement is filed more than 15 days after that person began work (§ 38-1b-202(8)).

Exam Trap: This excusal is a government-project rule. It does not rescue a subcontractor who blows the 20-day preliminary notice deadline on a private job. On private work the § 38-1a-501 deadline runs from the day the claimant commences construction work, whatever the permitting jurisdiction did or failed to do.


4. Preliminary Notice (§ 38-1a-501): The 20-Day Rule & 5-Day Penalty

The Preliminary Notice is the absolute bedrock of mechanics' lien preservation in Utah. Any contractor, subcontractor, materialman, or equipment lessor who does not contract directly with the property owner must file an electronic Preliminary Notice on the SCR.

The Standard 20-Day Deadline

Under Utah Code § 38-1a-501(1), a claimant must file a preliminary notice on the SCR within 20 calendar days after the date the claimant first commences work, performs labor, or furnishes materials or equipment to the construction project site.

When filed within this initial 20-day window, the preliminary notice is fully retroactive: it protects and preserves the claimant's lien rights for all labor, services, materials, and equipment furnished from day one through project completion.

Day 1: Subcontractor mobilizes and begins rough plumbing
  │
  ├── Within 20 Calendar Days: Sub files Preliminary Notice on SCR
  │     └── RESULT: 100% of labor and materials protected from Day 1 onward.
  │
  └── LATE FILING (Day 35): Sub files Preliminary Notice on Day 35
        └── THE 5-DAY RULE TRIGGERS:
              • Notice becomes effective on Day 40 (Day 35 + 5 calendar days).
              • Days 1 through 39: ALL LIEN RIGHTS PERMANENTLY FORFEITED.
              • Day 40 onward: Protected under construction lien law.

The 5-Day Rule for Late Preliminary Notices (§ 38-1a-501(1)(c)(ii))

If a subcontractor or supplier misses the 20-day deadline, they are not completely shut out from the project, but they suffer a severe statutory penalty under what Utah practitioners call the 5-Day Rule:

Statutory Rule (Utah Code § 38-1a-501(1)(c)): A claimant who misses the 20-day window may still file, but under § 38-1a-501(1)(c)(ii) that claimant "may not claim a construction lien for construction work the person provides to the construction project before the date that is five days after the preliminary notice is filed."

The Absolute Cutoff (§ 38-1a-501(1)(d)): A preliminary notice has no effect at all if it is filed more than 10 days after the filing of a notice of completion under § 38-1a-507. Once a notice of completion posts, the late-filing escape hatch closes in ten days. And under § 38-1a-501(1)(e), a person who fails to file a preliminary notice as required may not claim a construction lien — period.

Critical Mathematical Application of the 5-Day Rule

Understanding the exact timeline calculation under the 5-Day Rule is vital for exam success and contract administration:

  1. Step 1: Determine the date the claimant first mobilized or delivered materials (e.g., April 1).
  2. Step 2: Determine the date the late preliminary notice was submitted to the SCR (e.g., May 10).
  3. Step 3: Calculate the effective date: Add exactly 5 calendar days to the filing date (May 10 + 5 days = May 15).
  4. Step 4: Analyze coverage: All labor, materials, and services furnished between April 1 and May 14 are completely barred from lien protection. The claimant can only assert a mechanics' lien for labor and materials furnished on or after May 15.

5. Notice of Intent to Complete (45-Day Rule), Notice of Intent to Finance & Notice of Completion

Three specialized filings on the SCR dramatically impact financial exposure, downstream verification, and litigation timing during the project lifecycle.

A. Notice of Intent to Complete: The 45-Day Commercial Rule (§ 38-1a-506)

To prevent prime contractors and owners from ambushing trade contractors by prematurely filing a Notice of Completion, the Utah Legislature enacted the Notice of Intent to Complete (formally titled Notice of Intent to Obtain Final Completion) under Utah Code § 38-1a-506.

Qualifying Project Criteria

An owner or original contractor is statutorily required to file a Notice of Intent to Complete on the SCR if all of the following conditions are met:

  1. Project Type: The project is a commercial nonresidential construction project registered on the SCR;
  2. Contract Duration: The completion of performance under the original contract is greater than 120 calendar days;
  3. Contract Value: The total original construction contract price exceeds $500,000; and
  4. No Payment Bond: The owner or original contractor has not obtained a payment bond in accordance with Utah Code § 14-2-1.
┌────────────────────────────────────────────────────────────────────────┐
│         THE 45-DAY NOTICE OF INTENT TO COMPLETE WORKFLOW (§ 38-1a-506) │
├────────────────────────────────────────────────────────────────────────┤
│ Commercial Nonresidential Project (>120 Days, >$500k, No Payment Bond) │
│                                │                                       │
│               At least 45 CALENDAR DAYS before filing                  │
│               Notice of Completion (or final completion):              │
│                                │                                       │
│       Owner or Original Contractor files NOTICE OF INTENT TO COMPLETE  │
│                                │                                       │
│               SCR broadcasts alerts to all Preliminary Claimants       │
│                                │                                       │
│       Within 20 CALENDAR DAYS after Notice of Intent to Complete:      │
│       Subcontractors & Suppliers MUST file an amendment /              │
│       NOTICE OF REMAINING TO COMPLETE specifying:                      │
│       • Good faith estimate of total remaining balance                 │
│       • Name of contracting party / hiring contractor                  │
│       • All known disputed amounts and extra work claims               │
│                                │                                       │
│       After 45 days elapse: Owner/GC may file NOTICE OF COMPLETION.    │
│       *If Owner/GC fails to file 45-day notice, they CANNOT shorten    │
│        the lien recording window from 180 days to 90 days!*            │
└────────────────────────────────────────────────────────────────────────┘

Downstream Subcontractor Duties (The 20-Day Response Window)

Once a Notice of Intent to Complete is filed on the SCR, any subcontractor or supplier that has filed a preliminary notice must file an amendment or Notice of Remaining to Complete within 20 calendar days after the filing date. The claimant must disclose:

  • A good-faith estimate of the total dollar amount remaining due to complete its subcontract scope;
  • Identification of the contractor or subcontractor with whom the claimant has a direct agreement; and
  • A detailed statement of all known amounts or categories of work currently in dispute.

Consequence of Owner/GC Failure to File

Utah Code § 38-1a-506(8) says plainly that "failure to comply with the requirements established in this section does not affect any other requirement or right under this chapter," so skipping the notice of intent does not by itself void a later notice of completion. What the section actually gives an unpaid claimant is a different set of levers: the right to demand a statement of adequate assurance within 10 days of filing the balance statement (§ 38-1a-506(4)), the right to sue for injunctive or declaratory relief if adequate assurance is refused or genuinely disputed (§ 38-1a-506(5)(a)), the possibility of a court ordering the owner or contractor to post security — cash, a bond, an irrevocable letter of credit, property, or financing (§ 38-1a-506(5)(b)) — and a mandatory award of reasonable attorney fees to the prevailing party (§ 38-1a-506(7)). A claimant who never filed a preliminary notice gets none of these rights (§ 38-1a-506(9)), and a claimant who inflates its balance statement faces a civil penalty of the greater of twice the overstatement or the actual damages caused (§ 38-1a-506(6)).

B. Notice of Intent to Finance (§ 38-1a-601)

When an owner secures a construction loan, refinances an existing facility, or converts an interim loan to permanent financing during construction, lenders demand clear title. Under Utah Code § 38-1a-601, the owner or lender may file an electronic Notice of Intent to Finance on the SCR at least 14 calendar days prior to closing.

  • Triggering the Notice of Remaining to Complete: Once filed, the SCR automatically emails an alert to every party that has submitted a preliminary notice on the project.
  • The 20-Day Response Mandate (§ 38-1a-602): Any preliminary claimant that has not been paid in full and wishes to preserve priority against the new lender must file a Notice of Remaining to Complete within 20 calendar days after the Notice of Intent to Finance is filed. The notice must specify the total dollar balance due to date and the estimated value of labor and materials remaining to be furnished under the contract.
  • Consequence of Default: If a claimant fails to file a Notice of Remaining to Complete within 20 days, its lien claim is statutorily subordinated to the new mortgage or trust deed, rendering the lien virtually worthless if the property is over-leveraged.

C. Notice of Completion (§ 38-1a-506)

Upon final project completion, the owner, general contractor, or lender may file a Notice of Completion on the SCR. This filing acts as a procedural accelerator:

  • Cuts Recording Window in Half: A standard construction lien can be recorded up to 180 calendar days from final project completion. A valid Notice of Completion instantly compresses this timeframe to 90 calendar days from the date the Notice of Completion is filed on the SCR.
  • Precondition on Qualifying Commercial Projects: On commercial projects exceeding $500,000 and lasting over 120 days without a bond, the Notice of Completion is invalid unless preceded by the timely 45-day Notice of Intent to Complete.
  • Automated Alerts: The SCR broadcasts notice to all registered trade contractors. Trade contractors who fail to monitor their SCR email notifications frequently miss this shortened 90-day window, resulting in complete lien forfeiture.

6. Searching, Tracking, and Managing SCR Filings

Navigating the SCR electronic database is an essential operational duty for project managers and estimators. To file a preliminary notice or monitor project filings, users utilize specific search and tracking protocols.

Linking Filings to the Master Project

A government project is assigned a unique SCR Project Number by the designated agent when the notice of commencement is filed (§ 38-1b-201(4)). A private project is identified instead by the tax parcel identification number of each parcel, the entry number of a previously filed notice of construction loan or preliminary notice, or the building permit entry number (§ 38-1a-501(1)(h)(vii)). Trade contractors must link their preliminary notices to the correct master record; under § 38-1a-501(2)(b) a claimant substantially complies simply by linking to the original contractor's preliminary notice using its entry number. Search mechanisms include:

  1. Building Permit Number: The most direct, error-free search query.
  2. Jobsite Address: Physical street address (subject to municipality spelling variations).
  3. Tax Parcel Identification Number (Serial Number): Highly reliable county parcel format.
  4. Owner or General Contractor Legal Name: Searchable business entity registries.

The "Auto-Track" Feature

General contractors, title agents, and subcontractors can activate the SCR's Auto-Track function for any project record. Once tracked, the SCR automatically dispatches real-time email notifications whenever a subsequent filing occurs—such as a preliminary notice from an unknown lower-tier vendor, a Notice of Intent to Finance, a Notice of Intent to Complete, or a Notice of Completion. This ensures management never misses an administrative clock.


7. Realistic Exam Scenario Analyses

Scenario 1: The 5-Day Rule Arithmetic

  • Case: An HVAC subcontractor begins ductwork installation on a new commercial retail building in Salt Lake City on March 1. The HVAC contractor performs continuous work through April 30, billing $30,000 for March labor and $45,000 for April labor. Due to an administrative oversight, the HVAC contractor forgets to file a preliminary notice until April 10 (40 days after commencing work). In May, the general contractor becomes insolvent and refuses to pay the $75,000 invoice. The HVAC contractor seeks to file a construction lien for the full $75,000.
  • Analysis: Under Utah Code § 38-1a-501(1)(b), because the preliminary notice was filed after the initial 20-day window, it did not take effect immediately upon filing. It became effective five calendar days after filing, on April 15 (April 10 + 5 days). The contractor permanently forfeited all lien rights for labor and materials furnished prior to April 15. The contractor may only claim a mechanics' lien for work performed from April 15 through April 30. The entire $30,000 March billing and the first half of April ($22,500) are completely unprotectable by lien.

Scenario 2: Private vs. Government — Who Gets Excused

  • Case A (private): A developer pulls a building permit in St. George for a private mini-storage facility, and the city never transmits the permit information to the registry. A structural steel supplier delivers $85,000 in beams on June 1 and never files a preliminary notice. In November the developer defaults and the supplier records a construction lien. The supplier argues the city's failure excuses its own.
  • Analysis A: The lien fails. On a private project the preliminary notice deadline in § 38-1a-501(1)(a) runs from the day the claimant commences providing construction work, and nothing in Chapter 1a conditions that deadline on the permitting jurisdiction's § 38-1a-205 transmission duty. Section 38-1a-501(1)(e) is categorical: a person who fails to file a preliminary notice as required "may not claim a construction lien." The supplier's remedy is a breach of contract claim against the party it dealt with, not a lien.
  • Case B (government): The same supplier delivers beams on June 1 to a county public works project. The original contractor does not file a notice of commencement until August 15 — well past 15 days after physical work began. The supplier never files a preliminary notice.
  • Analysis B: Here the supplier is protected. Section 38-1b-202(8) excuses a person who provides construction work before the notice of commencement is filed from filing a preliminary notice, where the notice of commencement is filed more than 15 days after that person began work. Section 38-1b-201(7) independently switches off §§ 38-1b-202 and 38-1b-203 when the notice of commencement is untimely. The excusal is a government-project rule and does not travel to private work.

Scenario 3: The 45-Day Notice of Intent to Complete Trap

  • Case: A general contractor builds a $1,800,000 commercial office building in Sandy, Utah under a prime contract with a 240-day performance schedule. The owner did not require a payment bond. On October 15, the project reaches final inspection and the GC immediately files a Notice of Completion on the SCR. The GC never filed a Notice of Intent to Complete. A plumbing subcontractor who filed a timely preliminary notice is owed $68,000. On January 20 (97 days after October 15), the plumbing contractor records a Notice to Hold and Claim a Construction Lien with the Salt Lake County Recorder. The GC claims the lien is void because it was recorded more than 90 days after the Notice of Completion.
  • Analysis: Under Utah Code § 38-1a-506, because this was a commercial nonresidential project exceeding $500,000 with a duration exceeding 120 days and no payment bond, the GC was legally required to file a Notice of Intent to Complete on the SCR at least 45 calendar days before filing a Notice of Completion. Because the GC failed to file the required 45-day notice, the GC was legally barred from filing a Notice of Completion. The prematurely filed Notice of Completion is null and void, meaning the statutory recording window did not shorten to 90 days. The plumbing contractor retained the full 180 days from final completion, making the lien recorded on Day 97 timely and valid.
Test Your Knowledge

On a PRIVATE Utah construction project, which entity must put the project into the State Construction Registry, and by when?

A
B
C
D
Test Your Knowledge

A drywall subcontractor files an SCR Preliminary Notice 45 days after first commencing framing and sheetrock work on a commercial office building in Utah. Under the '5-Day Rule' (Utah Code § 38-1a-501(1)(b)), when does the preliminary notice become effective?

A
B
C
D
Test Your Knowledge

Under Utah Code § 38-1a-506, on a commercial nonresidential project exceeding $500,000 with a duration over 120 days and no payment bond, what filing must the owner or original contractor make on the SCR at least 45 calendar days before filing a Notice of Completion?

A
B
C
D
Test Your Knowledge

To preserve 100% of mechanics' lien rights from the very first day of performing work or furnishing materials on a Utah construction project, within how many days must a trade contractor file an electronic Preliminary Notice on the SCR?

A
B
C
D