9.6 System Acceptance Testing, Commissioning & Maintenance Records

Key Takeaways

  • System acceptance testing requires 100% functional verification of every initiating device, notification appliance, auxiliary control interface, secondary power supply and communication pathway prior to final sign-off.
  • Auxiliary emergency control functions — elevator Phase I recall, elevator power shutdown by shunt trip, HVAC shutdown, magnetic door release and electrically locked egress door release — must be functionally tested by operating the initiating device and observing the controlled equipment.
  • In Texas the closeout document is the installation certificate required by 28 TAC § 34.617, completed in lieu of the record-of-completion form required by the adopted standard unless the local AHJ requires otherwise.
  • Retention differs by document: service, maintenance and testing records 2 years (§ 34.616(d)); the certifying company’s installation certificate copy for the life of the system or 10 years, whichever occurs first (§ 34.617(2)); the installation inspection form 5 years from system certification (§ 34.618); one- and two-family drawings not less than 1 year (§ 34.619(f)).
  • Texas uses adhesive labels, not punched tags: white installation (inside the panel cover, § 34.620), white service (§ 34.621), blue inspection/test (§ 34.622), yellow non-compliance (§ 34.623) and red inoperable/impaired (§ 34.624).
Last updated: August 2026

System Acceptance Testing, Commissioning & Maintenance Records

The final phase of a fire alarm project is System Acceptance Testing and Commissioning. Prior to turning a newly installed or modified system over to the building owner and securing a Certificate of Occupancy (CO) from the local building official, the installation contractor must verify that 100% of the system components, circuits, and integrated auxiliary controls operate in strict accordance with the approved construction documents, NFPA 72, NEC Article 760, and local municipal codes.

In Texas, the commissioning process culminates in the installation certificate required by 28 TAC § 34.617 — the form TDI publishes as SF035 — and the white installation label affixed inside the control panel cover under § 34.620. Understanding the technical testing protocols, the auxiliary control interfaces, and the recordkeeping rules in 28 TAC §§ 34.616(d), 34.617, 34.618 and 34.619 is vital for passing the PSI TFM11 and TFM12 examinations.


1. 100% System Acceptance Testing Protocols

Acceptance testing is not a random sampling; NFPA 72 Chapter 14 mandates 100% comprehensive functional verification of every single device, appliance, circuit, and interface before the system can be certified:

+---------------------------------------------------------------------------------------------------+
|                         100% ACCEPTANCE TESTING VERIFICATION SCOPE                                |
|                                                                                                   |
|   [INITIATING DEVICES]        ===> 100% of Pull Stations, Smoke, Heat, Duct, Waterflow, Tampers   |
|   [NOTIFICATION APPLIANCES]   ===> 100% of Horns, Strobes (sync check), Speakers (intelligibility)|
|   [EMERGENCY CONTROL RELAYS]  ===> 100% of Fan Shutdowns, Damper Closures, Door Holders, Recalls  |
|   [POWER SUPPLIES & BACKUP]   ===> 100% Verification of AC Power Loss & Battery Standby Duration  |
|   [SIGNAL TRANSMISSION]       ===> 100% Verification of Supervising Station Receipt <= 90 Seconds |
|   [CIRCUIT INTEGRITY]         ===> Open, Short, Ground Fault Verification on all Class A/B/X loops|
+---------------------------------------------------------------------------------------------------+

Key Acceptance Testing Steps:

  1. Circuit Fault Simulation: Technicians must simulate opens, grounds, and short-circuit fault conditions on every Initiating Device Circuit (IDC), Signaling Line Circuit (SLC), and Notification Appliance Circuit (NAC) to verify that the FACP annunciates the correct trouble condition within 200 seconds (NFPA 72 10.19.1) without dropping active alarms.
  2. Primary & Secondary Power Switching: Primary 120VAC power must be disconnected at the dedicated branch circuit breaker to verify seamless automatic transfer to battery power without generating false alarms or dropping system programming.
  3. Sound Pressure & Strobe Synchronization: Sound levels must be measured with an ANSI Type 2 Sound Level Meter (A-weighted, slow response) to confirm compliance with audible audibility thresholds ($+15\text{ dBA}$ above average ambient or $+5\text{ dBA}$ above maximum ambient lasting 60 seconds). Strobe flash synchronization across entire viewing fields must be visually confirmed.

2. Integrated Auxiliary Life Safety Controls & Interfaces

Modern fire alarm systems interface with critical building mechanical, vertical transportation, and security subsystems. During acceptance testing, every auxiliary control function must be operated and verified:

+---------------------------------------------------------------------------------------------------+
|                      AUXILIARY LIFE SAFETY CONTROL INTERFACE MATRIX                               |
|                                                                                                   |
|   +-------------------------------------------------------------------------------------------+   |
|   | [1. ELEVATOR EMERGENCY OPERATIONS (ASME A17.1 / NFPA 72 21.3)]                            |   |
|   | • Phase I Designated Level Recall: Smoke detector in elevator lobby (floors 2+)           |   |
|   | • Phase I Alternate Level Recall: Smoke detector in designated/primary floor lobby        |   |
|   | • Elevator Machine Room / Hoistway Smoke: Recalls car to primary floor + Fire Hat Flashes|   |
|   | • Hoistway / Machine Room Heat Detector: Shunt trip power BEFORE sprinkler activates      |   |
|   +-------------------------------------------------------------------------------------------+   |
|                                                 |                                                 |
|                                                 v                                                 |
|   +-------------------------------------------------------------------------------------------+   |
|   | [2. HVAC SMOKE CONTROL & DAMPER CLOSURE (NFPA 90A / NFPA 72 21.7)]                        |   |
|   | • Duct smoke detectors (supply > 2,000 CFM, return > 15,000 CFM) shut down supply fans    |   |
|   | • Smoke dampers close automatically upon duct detector or general alarm activation        |   |
|   +-------------------------------------------------------------------------------------------+   |
|                                                 |                                                 |
|                                                 v                                                 |
|   +-------------------------------------------------------------------------------------------+   |
|   | [3. EGRESS & DOOR HOLDER RELEASE (NFPA 101 / NFPA 72 21.8)]                               |
|   | • Magnetic door holders de-energize (fail-safe) upon general alarm or local smoke         |   |
|   | • Access-controlled egress doors unlock immediately upon alarm, power loss, or manual push|   |
+---------------------------------------------------------------------------------------------------+

Elevator Recall & Shunt Trip Specifics:

  • Designated Floor Recall: When a smoke detector activates in any elevator lobby other than the designated primary egress floor (typically Level 1), the elevator must recall non-stop to the designated primary floor and park with doors open.
  • Alternate Floor Recall: When a smoke detector in the designated primary floor lobby activates, the elevator must recall to the approved alternate level (e.g., Level 2 or basement) so firefighters do not discharge passengers into smoke.
  • Elevator Shunt Trip (ASME A17.1): Where elevator machine rooms or hoistways are equipped with automatic fire sprinklers, a fixed-temperature heat detector with a lower temperature rating and higher sensitivity (or listed shunt trip module) must disconnect the main electrical power to the elevator prior to sprinkler discharge, preventing car free-fall or erratic electrical brake behavior.

3. Closeout Documentation and the Texas Installation Certificate

Upon successful completion of acceptance testing, a complete closeout package is assembled and turned over.

+-------------------------------------------------------------------------+
|                    CLOSEOUT DOCUMENTATION PACKAGE                       |
|                                                                         |
|   |-- Texas installation certificate (Form SF035)      28 TAC 34.617    |
|   |-- Record (as-built) drawings incl. sequence of                      |
|   |   operation, delivered to the owner                28 TAC 34.619(c) |
|   |-- Completed installation inspection form           28 TAC 34.618    |
|   |-- Battery standby and alarm load calculations      NFPA 72 Ch. 10   |
|   |-- NAC voltage-drop calculations to the last                         |
|   |   appliance, verified at the lowest regulated                       |
|   |   output voltage the panel is listed to deliver    NFPA 72 Ch. 18   |
|   |-- Input/output sequence of operation matrix        NFPA 72 Ch. 7    |
|   |-- Manufacturer cut sheets and operating manuals    NFPA 72 Ch. 7    |
|   `-- Site-specific software backup and passwords                       |
|       provided to the owner on request, subject to                      |
|       the firm's liability waiver                      28 TAC 34.616(b)(6)
|                                                                         |
|   NOTE: 28 TAC 34.619(e) - plans, manuals and documents shall NOT be     |
|         stored inside fire alarm panels.                                |
+-------------------------------------------------------------------------+

The Texas installation certificate (28 TAC § 34.617)

  • Required after completion of the installation, modification, or addition of a system or single station detector unit, except for a one- or two-family residence.
  • Completed in the format provided by the state fire marshal, in lieu of the installation form required by the adopted standard, unless required otherwise by the local AHJ. TDI publishes the form as SF035, Fire Alarm Installation Certificate.
  • Must identify the standards applicable to the installation and certify compliance; where a § 34.616(b)(4) variance applies, the specific variance and the authority for it must be identified.
  • Presented to the owner or the owner's representative, or posted near the main control panel.
  • Distribution: original at the site of installation; one copy retained by the certifying company for the life of the system or ten years, whichever occurs first; one copy sent to the local AHJ within 10 days after completion of installation.
  • Under § 34.616(b)(1) the certifying licensee must be present for the final acceptance test and must be licensed under the ACR number of the firm responsible for the installation.

4. Texas Record Retention — Four Different Clocks

DocumentRuleRetentionClock starts
Service, maintenance and testing records§ 34.616(d)2 years minimum
Installation certificate — certifying company copy§ 34.617(2)Life of the system or 10 years, whichever occurs firstCompletion of installation
Installation inspection form§ 34.6185 years, kept at the licensed firm's officeDate of system certification
One- and two-family dwelling drawings§ 34.619(f)Not less than 1 yearCompletion of the installation

Records of service, maintenance and testing must be available for examination by the state fire marshal or the state fire marshal's representative (§ 34.616(d)), and every registration application includes written authorization for the SFMO to enter, examine and inspect the applicant's premises (§ 34.613(a)(2)).

Administrative sanctions for non-compliance are imposed as provided in Government Code § 417.010 (28 TAC § 34.625(c)) and may include suspension, revocation, refusal to issue or renew, a cease and desist order, an administrative penalty, or restitution. Neither Chapter 6002 nor Subchapter F states a per-day penalty amount.


5. Texas Labels at Closeout (28 TAC §§ 34.620–34.624)

Texas documents system status with adhesive labels, approximately three inches high by three inches wide, each headed "DO NOT REMOVE BY ORDER OF TEXAS STATE FIRE MARSHAL" in all capitals in at least 10-point bold face type.

LabelRuleColorPlacementTime in place
Installation§ 34.620White, black letteringInside the control panel coverPermanent installation record
Service§ 34.621White, black letteringInside or outside the coverAt least 2 years
Inspection/Test§ 34.622Blue, black letteringInside or outside the coverAt least 5 years
Yellow§ 34.623Yellow, black letteringOutside the coverUntil corrected and a service label certifies the correction
Red§ 34.624Red, black letteringOutside the coverUntil corrected and a service label certifies the correction

Closeout sequencing. Section 34.620(a) prohibits attaching a yellow or red label for the installation of a new system or new equipment used in an extension, alteration or modification. Section 34.622(c) permits an inspection/test label on a new installation only after the system has been accepted by the local AHJ.

Notification deadlines.

EventDeadlineRule
Yellow label attached → written notice to owner and AHJ5 business days§ 34.623(c)
Red label, system inoperable → oral noticeImmediately§ 34.624(c)
Red label, system inoperable → written noticeNext business day§ 34.624(c)
Red label, fault or impairment → written notice3 business days§ 34.624(c)
Yellow or red label removed → notice to AHJ5 business days§§ 34.623(d), 34.624(d)

[!CAUTION] Who may remove a label. A yellow or red label remains in place until the conditions are corrected and a service label is attached certifying that the corrections were made, with the removed label's color and date marked on the service label (§ 34.621(b)). Labels may be removed by a licensed employee or agent of a registered firm, an employee of the State Fire Marshal's Office, or an authorized representative of a governmental agency with appropriate regulatory authority. Under § 34.616(b)(2), the licensee attaching a label must be licensed under the ACR number of the primary registered firm.

Test Your Knowledge

A licensed technician finds a commercial fire alarm system completely inoperable during a service call. Which Texas label applies, and what notification is required?

A
B
C
D
Test Your Knowledge

A registered firm asks how long it must keep the completed installation inspection form required by 28 TAC § 34.618. What is the correct answer?

A
B
C
D
Test Your Knowledge

When an elevator machine room or hoistway is equipped with automatic fire sprinklers, what safety mechanism must activate to shut down main electrical power to the elevator prior to sprinkler discharge under ASME A17.1 and NFPA 72?

A
B
C
D
Test Your Knowledge

Which document certifies in Texas that a newly installed or modified commercial fire alarm system complies with the applicable standards, and which rule requires it?