6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work

Key Takeaways

  • Nevada mechanics' and materialmen's liens are created by statute in NRS 108.221 to 108.246 and secure payment for work, materials or equipment used to improve private property.

  • Under NRS 108.2214, a lien claimant is anyone who provides work, material or equipment worth $500 or more for an improvement, including contractors, laborers, suppliers, equipment lessors, architects, engineers, surveyors and geologists.

  • Under NRS 108.222(2), a contractor or professional who must be licensed to perform the work has a lien only if it is licensed to perform that work.

  • Under NRS 108.22172, the lien attaches to the owner's land and improvements plus the space around them needed for their convenient use and occupation, and it secures the unpaid contract price or fair market value.

  • Public property cannot be liened; claimants on Nevada public works over $100,000 use the payment bond required by NRS 339.025 and must sue within 1 year after last furnishing (NRS 339.055).

Last updated: September 2026

Statutory Foundation of Nevada Lien Law

A mechanics' or materialmen's lien is a statutory security interest in real property for those who supply work, materials or equipment to improve it. In Nevada the right comes from NRS 108.221 to 108.246, substantially rewritten in 2003 and amended since. (The Nevada Constitution has no separate mechanics' lien clause; the remedy is statutory.)

Purpose

The lien prevents unjust enrichment: an owner should not keep improvements without paying the people who built them. Most subcontractors and suppliers have no contract with the owner, so the lien gives them an in rem right against the property itself, not just a contract claim against whoever hired them.

Exam Focus: Nevada lien rights depend on following the statute's notice and timing steps. Know who must give each notice, to whom, and by when.


Who May Claim a Lien (NRS 108.2214 and 108.222)

A lien claimant is any person who provides work, material or equipment with a value of $500 or more to be used in or for the construction, alteration or repair of any improvement, property or work of improvement (NRS 108.2214). The statute lists:

  1. Contractors and builders, including the prime contractor.
  2. Subcontractors at any tier.
  3. Laborers and artisans, and potential claimants under NRS 608.150 such as union trust funds for unpaid labor.
  4. Materialmen (material suppliers).
  5. Lessors or renters of equipment.
  6. Architects, engineers, land surveyors and geologists who perform services in relation to the improvement.

What the Lien Secures (NRS 108.222(1))

  • Agreed Price: If the parties agreed on a price or pricing method, the lien secures the unpaid balance of that price.
  • No Agreed Price: For work without an agreed price, including additional or changed work, the lien secures the fair market value, including a reasonable allowance for overhead and profit.
  • Where It Attaches: The lien is on the property, the improvements, and any construction disbursement account established under NRS 108.2403.
ClaimantContract With the Owner?Notice of Right to Lien Needed? (NRS 108.245)
Prime contractorYesNo
Supplier selling directly to the ownerYesNo
First- or lower-tier subcontractorNoYes
Supplier or equipment lessor to a contractorNoYes
Person performing only laborNoNo
Architect, engineer, surveyor, geologistDependsYes, if not contracting directly with the owner

The Licensing Condition (NRS 108.222(2))

The statute says: "If a contractor or professional is required to be licensed pursuant to the provisions of NRS to perform the work, the contractor or professional will only have a lien pursuant to subsection 1 if the contractor or professional is licensed to perform the work."

This links to Chapter 624:

  • Unlicensed Work: An unlicensed contractor performing work that requires a license has no lien for that work.
  • Collection Suits: NRS 624.320 separately bars a collection action unless the contractor proves it was licensed at all times during performance and when the job was bid.
  • Wrong Classification: Work outside the license classification is not work the contractor is "licensed to perform," and NRS 624.3015 treats it as a ground for discipline.
  • Over the Limit: A bid or contract above the monetary limit is void (NAC 624.640(1)), which undermines any claim based on it.
Was the claimant required to hold a license for this work?
   |-- No (e.g., a supplier) ---------------------> Licensing condition does not apply
   |-- Yes --> Was it licensed to perform the work?
                 |-- Yes --> Lien available (if notices and deadlines are met)
                 |-- No ---> No lien (NRS 108.222(2)); collection suit barred (NRS 624.320)

What Property the Lien Covers (NRS 108.22172 and 108.22188)

  • Property: The owner's land, real property or mining claim for which the work was provided, including all buildings, improvements and fixtures, and a convenient space on, around and about the same, or so much as may be required for the convenient use and occupation thereof.
  • Work of Improvement: The entire structure or scheme of improvement as a whole, whether under one prime contract or several. There are special rules when separate buildings are built on separate lots.

Owners, Lessees and Disinterested Owners

  • General Rule (NRS 108.234(1)): Every improvement is deemed made at the instance of each owner having an interest in the property, and each owner's interest is subject to recorded liens.
  • Disinterested Owner Exception: An owner that did not contract for or cause the work can protect its interest by recording a notice of nonresponsibility within 3 days after learning of the work (Section 6.2).
  • Lessee Duties (NRS 108.2403): Before a lessee improves leased property, it must record a notice of posted security. It must also either fund a construction disbursement account administered by a construction control for at least the prime contract amount, or record a surety bond of 1.5 times the prime contract. A lessor whose lessee fails to do this is not a disinterested owner, so the lessor's interest can be liened.

Public Property and the Payment Bond Alternative

Public property is not subject to mechanics' liens; liens cannot be foreclosed against a public school, fire station or state highway. Instead, Nevada requires payment bonds on public works (NRS Chapter 339):

  • When Required: Before a public works contract exceeding $100,000 is awarded (other than NRS Chapter 408 highway contracts), the contractor must furnish a performance bond and a payment bond, each in an amount the contracting body fixes but not less than 50% of the contract amount (NRS 339.025).
  • Who May Sue: A claimant not paid in full 90 days after its last labor or materials may sue on the payment bond (NRS 339.035(1)).
  • Notice From Remote Claimants: A claimant that contracted only with a subcontractor must give the prime contractor written notice within 30 days after first furnishing. It must give a second written notice of the amount claimed within 90 days after last furnishing, by registered or certified mail (NRS 339.035(2)).
  • Deadline to Sue: 1 year after the claimant last performed labor or furnished materials (NRS 339.055).
FeaturePrivate Mechanics' Lien (NRS 108)Public Works Payment Bond (NRS 339)
PropertyPrivately ownedState, county, city, school district
SecurityThe real property (in rem)Surety payment bond
ThresholdClaimant provided $500 or morePublic contract over $100,000
Early NoticeNotice of right to lien; covers 31 days before it is given (NRS 108.245)30 days after first furnishing, for claimants without a contract with the prime
Claim DeadlineRecord lien within 90 days (40 days after a notice of completion)Second notice within 90 days after last furnishing
Suit Deadline6 months after recording (NRS 108.233)1 year after last furnishing (NRS 339.055)
Test Your Knowledge

An unlicensed framer completes $45,000 of framing on a Reno office building and is not paid by the general contractor. What remedy does NRS 108.222(2) leave the framer?

A

A mechanics' lien, because the framing improved the owner's property whether or not the framer was licensed.

B

No lien, because a contractor needing a license has a lien only if licensed; NRS 624.320 also bars its suit.

C

A lien, as long as the framer obtains a contractor's license before it files the foreclosure action.

D

A lien against the general contractor's license bond only, since the owner never contracted with the framer.

Test Your Knowledge

A concrete subcontractor is not paid for foundation work on a new Clark County School District school. The contract was over $100,000. What is its remedy?

A

Record a mechanics' lien against the school parcel within 90 days after its last work on the foundation.

B

Record a lis pendens against the school and ask the court to order a sheriff's sale of the property.

C

Claim on the prime's NRS 339.025 payment bond, give the required notices, and sue within 1 year.

D

Ask the State Contractors Board to order the school district to pay the subcontractor directly.

Test Your Knowledge

Under NRS 108.22172, what does the 'property' subject to a Nevada mechanics' lien include?

A

The land with its buildings, improvements, and fixtures, plus the space needed for their convenient use.

B

Only the materials and fixtures the claimant installed, never the land beneath the improvement.

C

Every parcel of land the owner holds anywhere in the county, whether or not it was improved.

D

Only the tenant's leasehold interest in the land, never the owner's underlying fee interest.

Sections you finish are checked off in the contents.