8.2 Erosion, Sediment Control & Storm Water Management

Key Takeaways

  • Temporary erosion and sediment (E&S) controls stay in place and are maintained until permanent stabilization is achieved — removing them early, even after grading looks finished, is a compliance failure.
  • Silt fence is a perimeter control that intercepts sheet flow and settles out sediment; it is trenched and keyed into the ground and is not a substitute for controlling erosion at its source.
  • Sediment behind a silt fence should be removed, or a second fence added, once buildup reaches roughly one-third to one-half of the fence height to avoid overloading the fabric.
  • Inlet protection keeps sediment-laden runoff from entering the storm drain system directly through a catch basin or grate before the contributing area is stabilized.
  • Check dams are spaced so the toe of the upstream dam sits at the same elevation as the crest of the next dam downstream, which ponds water between them and cuts channel velocity; final stabilization generally means uniform perennial vegetative cover reaching about 70% of the surrounding undisturbed area's density.
Last updated: July 2026

Every phase of highway construction that exposes soil — clearing, grading, utility trenching, drainage installation — creates a risk that rainfall will carry sediment off the site and into a stream, storm drain, or adjacent property. Erosion and sediment (E&S) control is not a one-time installation the inspector checks off; it is a system of temporary best management practices (BMPs) that has to be installed correctly, maintained through the life of construction, and kept in place until the disturbed area is permanently stabilized.

Perimeter Control: Silt Fence

Silt fence is a permeable fabric barrier staked along the downhill edge of a disturbed area. It works by slowing sheet flow enough that suspended sediment settles out before the water passes through the fabric — it is a sediment trap, not an erosion preventer, and it does nothing to stop the soil loss happening upslope of it. Correct installation matters as much as placement: the fabric is trenched and keyed into the ground (commonly a minimum of about 6 inches) so water cannot simply flow underneath it, and the fence follows the contour rather than running straight downhill, which would concentrate flow instead of spreading it out.

Maintenance is where silt fence most often fails inspection. Sediment trapped behind the fence should be removed — or a second fence installed — once the buildup reaches roughly one-third to one-half of the fence's height. Left longer, the accumulated sediment adds hydraulic load against the fabric, increasing the risk of a blowout that releases everything the fence had trapped in one event. An inspector walking a site after a rain event checks fence height clearance, looks for undercutting or end-runs where water has found a way around the fence, and confirms the fence is still functional rather than buried, torn, or collapsed. Fence that has failed structurally — leaning posts, torn fabric, a washed-out end run — is repaired or replaced immediately rather than left to catch the next storm in a degraded state, because a partially failed BMP can give a false sense of protection while sediment moves past it unnoticed.

Inlet Protection

Once storm drain structures are in the ground, inlet protection keeps sediment-laden runoff from entering the pipe network directly through an open grate or curb inlet before the contributing drainage area is stabilized. Common methods include fabric drop-inlet protection stretched over or around the grate, gravel-bag or block-and-gravel barriers built around the inlet opening, and excelsior or straw-wattle rings. Inlet protection is removed only after the area draining to that structure is stabilized — pulling it early because the pipe "is already installed" defeats its purpose, since the pipe and everything downstream of it is exactly what the device is protecting.

Check Dams in Channels and Ditches

Where a temporary or permanent ditch carries concentrated flow, check dams — small barriers built from rock, sandbags, or fiber rolls across the channel — slow velocity enough to let sediment drop out before it travels further downstream. The governing spacing rule: dams are placed so the toe (downstream base) of the upstream dam sits at the same elevation as the crest (overflow point) of the next dam downstream. That geometry lets water pond in the reach between dams, which is what actually reduces velocity — dams spaced too far apart leave a length of unprotected, faster-flowing channel between them. Rock and fiber-roll check dams are also keyed into the channel bottom and side slopes to prevent water from eroding a bypass around the ends of the structure.

Sequencing: Temporary Until Permanent

A recurring theme across every BMP in this section is that temporary controls stay in place until permanent stabilization is achieved — they are not removed once grading looks complete or once a contractor has moved to the next phase. Under the federal Construction General Permit framework that most state DOT E&S programs mirror, final stabilization generally means uniform, perennial vegetative cover reaching roughly 70% of the density of the vegetation on undisturbed areas nearby (or an approved non-vegetative cover, such as riprap or pavement, on areas that will not be vegetated). Until that threshold is documented, temporary BMPs remain the only thing standing between exposed soil and the receiving drainage system, and an inspector who signs off on their removal too early is accepting a compliance and erosion risk on the project's behalf. In practice this means an inspector tracks stabilization progress area by area rather than treating the whole site as one pass/fail condition — the slope that was seeded first may already qualify for BMP removal while a haul road opened last week is nowhere close, and pulling controls on a site-wide schedule instead of an area-by-area one is a common inspection shortcut that does not hold up.

Inspector's E&S Field Checklist

  • Confirm BMPs match the approved erosion and sediment control (or SWPPP) plan for that phase of work, not just "something" installed at the right general location.
  • Check silt fence trenching, staking, and contour placement; measure sediment buildup against the one-third to one-half height trigger.
  • Verify inlet protection is present at every structure receiving runoff from disturbed ground, and intact after storm events.
  • Confirm check dam spacing and keying, and look for channel scour bypassing the dams.
  • Document BMP installation, maintenance, and removal dates — removal is tied to documented stabilization, not to the construction schedule.
Test Your Knowledge

During a routine erosion-control inspection, sediment has visibly built up behind a run of silt fence. At what point does that buildup typically need to be removed, or a second fence added, to keep the fence from failing?

A
B
C
D
Test Your Knowledge

A designer is laying out rock check dams down a roadside ditch. Which spacing rule keeps the flow velocity reduced in the reach between two adjacent dams?

A
B
C
D