Earthwork
15-25%of exam
Asphalt Pavement Construction
10-20%of exam
Concrete Structure Construction
15-25%of exam
Drainage
9-19%of exam
Utilities & Incidental Construction
6-16%of exam
Site Layout & Controls
5-15%of exam
Responsibilities
5-15%of exam
Quick Facts
- Exam
- NICET HCI Level II
- Credential
- Associate Engineering Technician
- Questions
- 164
- Time
- 270 min
- Fee
- $315
- Pass
- Scaled 500 of 700
- Delivery
- Pearson VUE, in-person
- References
- FP-24 only (no MUTCD)
- Blueprint
- Dec 3 2025 draft
Proctor Effort Mnemonic
Bigger hammer, more layers, higher max density
T99 vs T180 Proctor
T99 (Standard)
- 5.5 lb hammer, 12 in
- 3 layers, 25 blows
- Embankment reference effort
T180 (Modified)
- 10 lb hammer, 18 in
- 5 layers, 25 blows
- Base/subgrade reference effort
Heavier effort raises max density
Field Density Test Picker
- Need fast in-place result→Nuclear gauge (T310)(Daily standard count required)
- No gauge access available→Sand cone (T191)(Calibrated sand volume)
- Checking base or subgrade→Reference T180 (Modified)(Higher effort, lower OMC)
- Checking general embankment fill→Reference T99 (Standard)(Lower effort baseline)
- Lift fails density spec→Rework, then retest same spot(Never test a new spot)
- Result marginal at target→Compare vs written spec range(Never eyeball a pass)
Soil & Aggregate ID
- Gravel
- Retained on No.4 sieve
- Sand
- No.4 to No.200 sieve
- Silt
- Fine, low plasticity
- Clay
- Fine, plastic when wet
- A-1 to A-3
- Best subgrade soils
- A-6 / A-7
- Worst subgrade, clayey
Embankment vs Subgrade
Embankment
- General bulk fill lifts
- ~8 in loose lift
- 90-95% T99 target
Subgrade
- Final layer under pavement
- Proof-rolled before paving
- 95-100% T99/T180 target
Bulk fill vs finish layer
Excavation Protective System Picker
- Excavation 5 ft or deeper→Protective system required(Unless stable rock)
- Open area, room to slope→Sloping or benching(Default 1.5H:1V, no data)
- Narrow trench, walls stay→Shoring(Aluminum hydraulic or timber)
- Utility trench, tight ROW→Shielding (trench box)(Protects workers inside box)
- No soil classification done→Competent person classifies first(Type A, B, or C)
Proctor Compaction (T99/T180)
- T99 hammer
- 5.5 lb, 12 in drop
- T99 layers
- 3 layers, 25 blows
- T180 hammer
- 10 lb, 18 in drop
- T180 layers
- 5 layers, 25 blows
- OMC
- Moisture at peak density
- Dry density
- Wet density ÷ (1+w)
- One-point check
- Uses family of curves
Nuclear Gauge vs Sand Cone
Nuclear Gauge (T310)
- Fast, nondestructive reading
- Daily standard count needed
- Licensed operator required
Sand Cone (T191)
- Destructive test hole
- Calibrated sand fills hole
- No license needed
Speed vs no radioactive source
Field Density & Acceptance
- T310
- Nuclear gauge method
- T191
- Sand cone method
- %Compaction
- Field ÷ lab max ×100
- Embankment target
- 90-95% of T99
- Subgrade target
- 95-100% of T99/T180
- Base target
- 95-100% of T180
- Moisture window
- ±2% of optimum
Embankment & Subgrade Build
- Loose lift
- ~8 in (6 in compacted)
- Benching
- Steps cut into slopes
- Proof roll
- 15+ ton tandem truck
- Fail sign
- Rut over 1 in
- Undercut
- Remove, replace soft spot
- Avg end area
- (A1+A2)÷2 × L÷27
Erosion & Sediment Control
- Silt fence key-in
- 6 in min trench depth
- Sediment trigger
- 1/3-1/2 fence height
- Check dam spacing
- Toe meets next crest
- Inlet protection removal
- After area stabilized
- Final stabilization
- ~70% vegetative density
- BMP rule
- Temporary until permanent cover
HMA Roller Sequence
Break, knead, finish: steel, rubber, steel
Prime Coat vs Tack Coat
Prime Coat
- Applied to granular base
- Applied once per project
- Cures 24-48 hours
Tack Coat
- Applied to existing/HMA lift
- Applied at every lift
- Must break brown to black
Base bond vs lift bond
HMA Delivery Ticket Check
- Mix ID doesn't match JMF→Reject the load(Wrong design, don't place)
- Temp below placement minimum→Reject or verify with probe(Heat loss during haul)
- Ticket missing or unsigned→Reject, hold for paperwork
- Ticket matches JMF and temp→Accept into paver hopper
- Mat cools below ~175-185°F→Stop rolling that area(More rolling won't help)
HMA Materials, JMF & Coats
- Aggregate share
- 92-96% of HMA weight
- PG XX-YY
- Hot / cold temp grade
- JMF
- Approved single mix reference
- Tack coat rate
- 0.03-0.10 gal per SY
- Tack break
- Brown fades to black
- Prime cure time
- 24-48 hours typical
- Dense-graded HMA
- Standard travel-lane mix
- SMA / OGFC
- Rut-resist / friction course
Rice Test & Density Acceptance
- Gmm (Rice)
- Zero-air-voids max gravity
- T209 vacuum
- ~30 mmHg, 15±2 min
- %Gmm formula
- Core Gsb ÷ Gmm ×100
- Core method
- T166, destructive sample
- Gauge method
- T355, daily calibration
- Typical min %Gmm
- Low-to-mid 90s
HMA Placement & Rolling
- Plant temp range
- ~275-325°F typical
- Compaction cutoff
- ~175-185°F, too stiff
- Breakdown roll
- Steel, right behind paver
- Intermediate roll
- Pneumatic, kneads the mat
- Finish roll
- Steel, removes roller marks
- Joint overlap
- 1-2 in, hot side
Concrete Fresh Test Trio
Slump workability, air durability, yield accuracy
Air-Entrained vs Non-Entrained
Air-Entrained
- Admixture adds microbubbles
- ~4-8% target air content
- Freeze-thaw protection
Non-Entrained
- No air admixture used
- Entrapped air only
- Not for exposed pavement
Durability need drives choice
Concrete Fresh-Property Test Picker
- Check workability, consistency→Slump test (C143)(Not a strength proxy)
- Check freeze-thaw durability→Air content (C231 pressure)(~4-8% typical target)
- Aggregate is highly porous→Volumetric method (C173)(Pressure method invalid here)
- Check batching accuracy→Unit weight / yield (C138)(Flags under-yield error)
- Check 28-day acceptance→Cylinder compressive break (C39)
Concrete Mix & Materials
- Type I cement
- General use
- Type II cement
- Sulfate resistant
- Type III cement
- High early strength
- Type IV cement
- Low heat, mass concrete
- Type V cement
- High sulfate resistance
- w/c ratio
- Lower w/c = stronger
- Severe-exposure w/c cap
- ~0.40-0.45 max
Driven Pile vs Drilled Shaft
Driven Pile
- Hammered to depth
- Blow count / PDA check
- Brooming signals over-driving
Drilled Shaft
- Augered or drilled hole
- Tip cleanliness is critical
- Tremie if wet or cased
Capacity check method differs
Slump, Air Content & Yield
- Slump cone
- 8x4x12 in, 3 layers
- Slump meaning
- Workability, not strength
- Air method
- C231 pressure meter
- Air target range
- ~4-8% by agg size
- Unit weight
- Batch weight ÷ volume
- Design yield
- 27 cubic ft per CY
Cylinders, Strength & Curing
- Cylinder size
- 6x12 in (or 4x8)
- Rod consolidation
- Slump over 3 in
- Initial cure
- 60-80°F, up to 48 hrs
- Break ages
- 7-day and 28-day
- 7-day ratio
- ~60-75% of 28-day
- Min cure period
- 7 days or 70% f'c
- Cold weather rule
- Below 40°F, needs 500 psi
Rebar, Forms, Piles & Shafts
- Grade 60 bar
- 60,000 psi min yield
- Class B splice
- 1.3x dev length, default
- Cover, cast on earth
- 3 in minimum
- Cover, formed/weather
- 2 in for #6+
- Formwork strip
- Strength-based, not calendar
- Driven pile check
- Blow count or PDA
- Drilled shaft key risk
- Tip cleanliness matters most
Pipe, Bedding & Backfill
- Bedding
- Uniform support, full barrel
- Haunching
- Compact up to spring line
- Point load
- Rock or void under pipe
- Initial backfill
- Both sides, lifts together
- Cover before traffic
- ~12 in over crown
- Backfall
- Low spot mid-run defect
Drainage Slope & Structures
- Slope formula
- Drop ÷ length ×100
- Too-flat risk
- Ponding, sediment buildup
- Too-steep risk
- Scour, eroded outlet
- Catch basin
- Sump traps sediment
- Manhole placement
- Junctions, bends, long runs
Utility Locate Color Code
Red electric, yellow gas, blue water, orange comm
Utility Locate Colors (APWA)
- Red
- Electric power, cable
- Yellow
- Gas, oil, steam
- Orange
- Communication, signal lines
- Blue
- Potable water
- Green
- Sewer, drain lines
- Purple
- Reclaimed water, irrigation
- White
- Proposed excavation limits
- Pink
- Temp survey, unidentified
Guardrail & ADA Curb Ramps
- MGS rail height
- 31 in top of rail
- Old rail standard
- 27 in, now replaced
- Ramp running slope
- 1:12 (8.33%) max
- Ramp cross slope
- 1:48 (~2%) max
- Side flare limit
- 1:10 maximum
- Detectable warning
- Truncated domes required
Sidewalks, Signs & Restoration
- Curb/gutter check
- Line, grade, cross slope
- Sidewalk joints
- Match flatwork spec rules
- Restoration item
- Seeding and mulching
- Sign height, urban
- 7 ft min, curb
- Sign height, rural
- 5 ft min, no curb
Stationing, Offsets & Stakes
- 1 station
- 100 linear feet
- Offset direction
- Face increasing stationing
- Hub-and-tack
- Exact point, 0.01 ft
- Guard stake
- Carries station, offset, cut/fill
- Cut
- Existing higher, remove material
- Fill
- Existing lower, add material
Leveling & Slope Calculation
- HI
- Known elevation + backsight
- Unknown elevation
- HI minus foresight
- % Slope
- Rise ÷ run ×100
- Cross slope target
- ~2% typical lane
- Ditch min slope
- ~0.5-1%
- Elevation precision
- Nearest 0.01 ft
TTC Zone Order
Warn, Turn, Work, Return: the four TTC areas
Acceptance vs Verification (IA)
Acceptance Sampling
- Set testing frequency
- Compared to spec limits
- Decides contractor pay
Verification (IA) Sampling
- Audits the testing system
- Split-sample comparison
- Does not decide pay
Pays contractor vs trusts tester
MUTCD TTC Zone Sequence
- Driver approaching the work→Advance warning area(Signs alert road users)
- Redirecting traffic out of path→Transition area / taper(Speed plus offset driven)
- Work is actually happening→Activity area(Work, traffic, buffer space)
- Returning drivers to normal lanes→Termination area(Downstream taper, END sign)
MUTCD TTC Zone Terms
- Advance warning area
- Alerts drivers ahead
- Transition area
- Taper redirects path
- Activity area
- Work, traffic, buffer space
- Buffer space
- Clear vehicle recovery zone
- Termination area
- Returns to normal path
- Taper length
- Speed + offset judgment
Documentation & Payment
- Daily diary
- Every calendar day, no exceptions
- Nonconformance record
- Factual, dated, located, cited
- Force account log
- Signed by both parties daily
- Acceptance sampling
- Decides contractor pay
- IA/verification sampling
- Checks test system, not pay
- Payment eligibility
- Measured AND accepted
Safety & OSHA Excavation
- Minimum PPE
- Hard hat, hi-vis, boots
- Hi-vis Class 3
- Over 50 mph or night
- 5-ft rule
- Protective system required
- Competent person
- Classifies soil, inspects daily
- Spoil setback
- 2 ft from trench edge
- Egress rule
- Within 25 ft, 4 ft+ deep
- Default max slope
- 1.5H:1V, no soil data
Common Traps
Slump vs Strength
Slump = workability only ≠ Strength = 28-day break
Prime vs Tack Surface
Prime = granular base ≠ Tack = existing pavement/lift
Acceptance vs IA Testing
Acceptance testing decides pay ≠ IA testing checks testers
Means/Methods vs Result
Inspector verifies the result ≠ Contractor owns means/methods
Embankment vs Subgrade Target
Embankment targets 90-95% T99 ≠ Subgrade targets 95-100%
Retest Location Rule
Retest the failed spot ≠ Never a new easy spot
Nuclear Gauge vs Sand Cone
Gauge needs daily count ≠ Cone needs no license
Addendum vs Change Order
Addendum = before contract award ≠ Change order = after award
Last Minute
- 1.T99: 5.5 lb hammer, 3 layers
- 2.T180: 10 lb hammer, 5 layers
- 3.Compaction% = field ÷ lab max
- 4.Tack coat breaks brown to black
- 5.Cold mat: rolling can't add density
- 6.Slump tests workability, never strength
- 7.Air target: roughly 4-8% by size
- 8.7-day and 28-day cylinder breaks
- 9.OSHA: protection required at 5 ft
- 10.TTC order: warning, transition, activity, termination
- 11.APWA colors: red, yellow, blue, orange
- 12.MGS guardrail: 31 in top-of-rail
- 13.ADA ramp caps at 8.33% slope
- 14.Retest failed spots, never new ones
- 15.Force account log signed same day
- 16.Inspector authority comes from contract only
Explore More NICET Certifications
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
More From This Family
Videos and articles for deeper review.
