3.4 Change Orders, Allowances, and Unit Pricing
Key Takeaways
- A change order is a written, signed amendment; never perform extra work on a verbal direction if you expect to be paid.
- Change-order pricing is direct cost plus contract-capped overhead and profit, often 10 percent each on self-performed work.
- An allowance is a placeholder dollar sum for material cost; install labor, overhead, and profit usually stay in the base bid.
- Unit prices pay the actual installed quantity at the bid rate and may allow renegotiation when quantities swing beyond about 15 to 25 percent.
- Distinguish allowance (dollar placeholder), unit price (rate per unit), and contingency (reserve for the unforeseen).
Change Orders, Allowances, and Unit Pricing
Few commercial projects finish exactly as bid. Contracts therefore build in mechanisms to price changed, undefined, or variable-quantity work: the change order, the allowance, and unit pricing. The NASCLA exam tests both the contract mechanics and the arithmetic, because mishandling these is a leading source of disputes and unpaid work.
Change Orders
A change order (CO) is a written, signed amendment to the contract that modifies the scope, price, or schedule. The governing rule: get it in writing and signed before performing the work. Verbal directions and unsigned field tickets are the top cause of payment disputes.
A CO price typically equals direct cost of the change + agreed overhead and profit markup. Contracts often cap CO markup, for example 10 percent overhead plus 10 percent profit on self-performed work and a lower percentage on subcontracted change work (commonly 5 percent on a sub's marked-up price).
Constructive Changes and the Paper Trail
Not all changes arrive as tidy COs. A constructive change occurs when the owner's act or direction effectively changes the work without a formal order, for example requiring inspection beyond the spec. Protect entitlement with the documents in order:
| Document | Purpose |
|---|---|
| RFI (Request for Information) | Resolve a drawing/spec conflict |
| CCD (Construction Change Directive) | Owner orders work to proceed before price is settled |
| Change Order | Final signed price/time/scope amendment |
Always follow the notice provisions and time limits in the contract or claims may be waived.
Allowances
An allowance is a dollar amount placed in the bid for work or materials not yet selected, such as a 12,000 lighting allowance or a 6 dollar per SF flooring allowance. The contractor includes that figure in the contract sum and reconciles it when the owner makes the actual selection.
Key exam point: the standard allowance covers material/equipment cost delivered to the site; labor to install, overhead, and profit are normally carried in the base bid, not the allowance, unless the contract says otherwise. When actual cost differs, a CO adjusts the contract sum up or down by the difference.
Unit Pricing
A unit price is a pre-agreed price per unit of work used when the exact quantity is unknown at bid time, common for earthwork, rock excavation, undercut/import fill, and piling. The owner pays for the quantity actually installed at the bid unit rate.
Worked example: Unit price for rock excavation = 45 dollars per CY. The plan estimated 200 CY but field conditions yield 260 CY. Payment = 260 x 45 = 11,700, an increase of 60 CY x 45 = 2,700 over the estimated 9,000. Many contracts allow renegotiation if actual quantity varies beyond a threshold (often +/- 15 to 25 percent) of the estimate.
Allowance vs. Unit Price vs. Contingency
These three are commonly confused on the exam:
- Allowance = a placeholder dollar sum for an undefined material/selection, reconciled by CO.
- Unit price = a fixed rate per measured unit, paid on actual installed quantity.
- Contingency = the contractor's or owner's reserve for unforeseen costs, not tied to a specific selection or unit.
A frequent trap question gives an allowance overrun and asks for the adjustment: the contract sum changes only by the difference between the allowance and the actual reconciled cost, processed as a change order.
A contract carries a 200 CY estimate for unsuitable-soil removal at a unit price of 38 dollars per CY. Actual removal measures 250 CY. What does the owner owe for this work?
Under a standard contract, before performing extra work directed by the owner, the contractor should obtain a:
Change Order Mechanics and Pricing Methods
A change order (CO) is a written, signed amendment altering scope, price, or time. Price a CO by one of three methods: lump sum (negotiated), unit price (rate × measured quantity), or time-and-materials (cost + agreed markup). A CO adjusts the contract sum and may extend the contract time. Performing changed work on an oral directive risks non-payment where the contract requires written authorization.
Allowances and Their True-Up
An allowance is a placeholder dollar amount in the contract for an item not yet selected (e.g., "$10/SF tile allowance"). At selection, the actual cost is reconciled: if the owner picks $14/SF tile, a CO adds the difference; if they pick $7/SF, the contract sum is reduced (a credit/deductive CO). The exam point: allowances cover material cost as specified — verify whether labor and overhead are included or added separately, a frequent dispute.
Unit Pricing and Worked Example
Unit prices are pre-agreed rates for adding/deleting quantities of uncertain-quantity work (rock excavation, undercut, piles). Example: Contract carries unit price $45/CY for rock removal; field measures 120 CY of unforeseen rock → CO add = 120 × 45 = $5,400. Unit prices avoid renegotiating each occurrence and should state whether they include overhead and profit.
Common Exam Traps
- Trap: Proceeding on a verbal change without written authorization.
- Trap: Assuming an allowance includes labor and markup when it may be material-only.
- Trap: Forgetting a change order can add time, not just money.
- Trap: Applying a unit price to the wrong measured quantity or unit.
A contract carries a $12/SF flooring allowance. The owner selects flooring costing $18/SF for a 500 SF area. What change order results?
Constructive Changes and Documentation
A constructive change occurs when the owner's actions (defective plans, denied access, added inspections) effectively alter the work without a formal CO — the contractor must give prompt written notice to preserve a claim. Track changed-work costs with daily reports, photos, and segregated cost codes so the claim is provable. The exam stresses documentation: an entitlement that is real but undocumented is, in practice, unrecoverable, and late notice can waive an otherwise valid claim.