General Requirements
22%of exam
PlanningEstimatingSafetyCodesControls
Procurement + Contracts
27%of exam
Site Construction
13%of exam
SoilsExcavationGradingDrainageErosion
Trade Coordination
38%of exam
ConcreteMasonryMetalsWoodMEP
Quick Facts
- Exam
- NASCLA commercial
- Provider
- PSI
- Format
- Open book
- Questions
- 115
- Time
- 5.5 hours
- Pass
- 70 percent
- Score
- 81 correct
Float vs Delay
Float
- Available slack
- May absorb slip
Delay
- Schedule impact
- May need change
Critical path controls
Exam Strategy
- Open book
- Fast lookup required
- Tabs
- Find references quickly
- Index
- Use under pressure
- Time budget
- About three minutes
- Math
- Show units
- Flagging
- Return later
- Priority
- Contracts first
Project Controls
- Critical path
- Controls finish date
- Float
- Allowable slippage
- Baseline
- Approved plan
- Lookahead
- Near-term schedule
- Takeoff
- Measure quantities
- Unit price
- Cost per unit
- Contingency
- Risk reserve
Contract Flow
Bid, bond, build, change, close.
BidBondBuildChangeClose
Bid vs Performance
Bid bond
- Before award
- Protects bid reliance
Performance bond
- After award
- Protects completion
Timing distinguishes them
Document Picker
- Before bid change→Addendum
- Clarify conflict→RFI
- Show product data→Submittal
- Fabrication detail→Shop drawing
- Change agreed→Change order
- Change directed→CCD
- Payment requested→Pay application
- Work nearly done→Punch list
Bidding + Bonds
- Invitation
- Solicits bids
- Addendum
- Prebid change
- Bid bond
- Protects owner
- Performance bond
- Guarantees completion
- Payment bond
- Protects subs
- Bid opening
- Public result
- Responsible bidder
- Qualified bidder
Closeout
Punch, correct, document, warrant, final.
PunchCorrectDocumentWarrantFinal
RFI vs Submittal
RFI
- Asks clarification
- Information gap
Submittal
- Shows proposed item
- Review before work
Question versus review
Contract Admin
- Change order
- Formal modification
- CCD
- Directed change
- RFI
- Request clarification
- Submittal
- Review before install
- Shop drawing
- Fabrication detail
- Allowance
- Undefined cost reserve
- Lien waiver
- Payment rights release
Substantial vs Final
Substantial
- Owner can use
- Punch list remains
Final
- All work complete
- Closeout delivered
Use before perfect
Site Safe
Classify, protect, access, inspect, control.
ClassifyProtectAccessInspectControl
Site Picker
- Trench hazard→Protective system
- Soil unknown→Classify soil
- Water present→Dewatering plan
- Slope needed→Grade stakes
- Sediment risk→Erosion control
- Backfill placed→Compact lifts
- Concrete placed→Cure concrete
- Envelope leak→Check flashing
Safety + Site
- Competent person
- Corrects hazards
- PPE
- Personal protection
- Excavation
- Cave-in hazard
- Soil class
- Protective system driver
- Access
- Safe egress
- Erosion
- Control sediment
- Compaction
- Increase density
Slump vs Strength
Slump
- Fresh consistency
- Workability check
Strength
- Hardened capacity
- Cylinder test
Do not confuse
Concrete + Masonry
- Slump
- Fresh workability
- Curing
- Maintain moisture
- Rebar
- Tension reinforcement
- Control joint
- Planned crack
- CMU
- Concrete masonry unit
- Mortar
- Bonds units
- Grout
- Fills cells
Metals + Wood
- Structural steel
- Frame members
- Bolt
- Mechanical fastener
- Weld
- Fused connection
- Joist
- Floor support
- Stud
- Wall vertical
- Sheathing
- Panel skin
- Lumber grade
- Strength classification
Envelope + MEP
- Flashing
- Water diversion
- Vapor retarder
- Moisture control
- Insulation
- Thermal resistance
- Roofing
- Weather barrier
- HVAC
- Air systems
- Plumbing
- Water systems
- Electrical
- Power systems
Common Traps
Open Book Overconfidence
Lookup must be fast ≠ Practice reference routes
Document Mixups
RFI asks questions ≠ Submittal shows products
Bond Timing
Bid before award ≠ Performance after award
Schedule Math
Critical path matters ≠ Float can vanish
Trade Detail Depth
General contractor level ≠ Coordinate disciplines
Last Minute
- 1.Tab official references
- 2.Practice index lookup
- 3.Review contract documents
- 4.Drill bond purposes
- 5.Memorize site safety
- 6.Check unit conversions
- 7.Separate completion stages
- 8.Manage question pacing
Same family resources
Explore More NASCLA Accredited Examinations
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
More From This Family
Videos and articles for deeper review.
