7.3 Real-World Transaction Scenarios & Exam Review
Key Takeaways
A scenario may combine statutory carpet-area measurement, the separate-account deposit rule, transaction documentation, delay interest and allottee remedies; verify each rule’s assumptions.
Under Section 18, an eligible delayed-possession allottee may withdraw and seek refund with applicable interest, or continue and receive interest for every month of delay until possession.
Section 62 addresses an agent’s failure to comply with Sections 9 or 10: INR 10,000 for each day of default, cumulatively up to 5% of the cost of the property whose sale or purchase was facilitated.
The Maharashtra model agreement provides a 3% carpet-area variation cap and a same-unit-rate adjustment; a reduction within that cap carries the stated excess-payment refund and interest terms.
MahaRERA conciliation is an amicable promoter–allottee process requiring acceptance and signed settlement terms; do not invent an official exam weight or a guaranteed 60-day decision.
7.3 Real-World Transaction Scenarios & Exam Review
Quick Summary: Read a scenario in stages: identify the person and project, check the legal obligation and its boundary, then calculate using stated dates, amounts and contractual assumptions. A mathematically correct answer can still apply the wrong rule.
1. Delay Interest and Refund under Section 18
Scenario: An allottee signs a registered agreement on 15 January 2022 for an INR 1 crore apartment. INR 40 lakh has been paid before the promised possession date of 31 December 2024. The promoter fails to hand over by that date. For this illustration only, assume the applicable SBI highest MCLR is 8.5% and remains constant; this is not a statement of today’s market rate. Delay begins 1 January 2025.
Maharashtra Rule 18 specifies SBI highest MCLR plus two percentage points:
For an allottee who continues in the project, Section 18 provides interest for every month of delay until possession. Assume the full INR 40 lakh remains the applicable paid balance throughout a complete month and the exercise uses annual interest divided by 12:
This arithmetic assumes that monthly method; Rule 18 alone supplies the rate, not a universal simple/compound or partial-month day-count convention. If the paid balance changes or only part of a month is involved, state the applicable calculation method and dates before computing.
An eligible allottee who withdraws may seek refund of amounts paid with applicable interest and compensation as provided by the Act. When computing a refund claim from separate instalments, use each actual receipt date and the relevant repayment date. The scenario lacks those individual dates, so it does not invent a cumulative interest total. Compensation depends on the applicable adjudication; it is not an automatic extra amount calculated from the interest rate.
2. Carpet-Area Variation and Defect Liability
Scenario: The agreement states 100 sq. metres at an agreed INR 2,00,000 per sq. metre, giving INR 2 crore. After completion and grant of the occupancy certificate, final carpet area is confirmed at 98 sq. metres. This is a 2% reduction, within the Maharashtra model agreement’s 3% variation cap. Assume the buyer has already paid for the full original area.
Clause 1(g) of the model agreement calls for recalculation at the same agreed unit rate. It states that a reduction within the cap requires refund of excess money within 45 days, with annual interest at the rule-prescribed rate from the date the excess amount was paid. Interest is not limited to the period after missing the refund deadline. These are clause 1(g)’s model terms. Separately, Maharashtra Rule 19 requires a refund payable under the Act, Rules or Regulations, with applicable interest and compensation if any, within 30 days from when it becomes due and payable. Do not use the model’s 45-day wording as a blanket extension of a mandatory refund deadline: identify the applicable obligation and due date, read the executed agreement alongside the governing rule, and establish the remedy where a variation exceeds the cap. Section 2(k) defines carpet area; it does not, by itself, fix a price per square metre for every transaction.
Under Section 14(3), a structural defect or defect in workmanship, quality, services, or the promoter’s relevant agreement obligations, brought to the promoter’s notice within five years from handing over possession, must be rectified within 30 days without further charge. Failure gives the aggrieved allottee the compensation remedy provided by the Act. Do not treat every later leak or ordinary wear as a proven covered defect without establishing its cause and the applicable obligation.
3. Misrepresentation, Agent Liability and Conciliation
Scenario: An agent facilitates sales in a phase legally required to be registered but not registered, using an edited number from another phase. Five proposed buyers each supply an INR 2 lakh advance cheque: 5 × INR 2 lakh = INR 10 lakh in proposed advances. This does not establish the total property cost or the maximum penalty.
- Verify whether the phase has its own required registration. Marketing a required-but-unregistered phase breaches the relevant Section 10(a) duty; false registration representations also engage the relevant unfair-trade-practice duty.
- Section 62: INR 10,000 for each day of failure to comply with Section 9 or 10, cumulatively up to 5% of the cost of the property whose sale or purchase was facilitated. Do not substitute the token advances for that statutory cost base.
- Registration suspension or revocation and any separate wrongdoing follow their applicable grounds and process. Do not present automatic cancellation or an automatic criminal sentence as the mathematical result of this scenario.
Conciliation Is a Consensual Promoter–Allottee Route
MahaRERA’s published guidance describes an allottee submitting a conciliation request, the promoter accepting, payment and assignment to a bench, then discussion with impartial assistance. The forum includes consumer and promoter-association representatives. The described forum admits promoter–allottee disputes within RERA’s purview; it is not automatically the route for every dispute solely against an agent.
If the parties agree, they sign settlement terms, which are final and binding once signed by all parties and authenticated as described. A failure to comply allows the other party to approach MahaRERA. Do not invent a guaranteed 60-day adjudication or imply that a unilateral request is already an imposed settlement.
4. Core Rules with Their Boundaries
| Concept | Reference | Rule and boundary |
|---|---|---|
| Carpet area | Section 2(k) | Includes partition-wall footprints; excludes external walls, shafts and exclusive balcony/verandah/open terrace. Do not count walls twice. |
| Separate project account | Section 4(2)(l)(D) | 70% of amounts realised from allottees is deposited for land and construction costs; withdrawals follow completion proportion and required certificates. |
| Size exemption | Section 3(2)(a) | Land at most 500 sq. metres OR at most 8 apartments across all phases, subject to reduced appropriate-government limits. |
| Pre-agreement advance | Section 13(1) | No more than 10% of cost before entering a written, registered agreement for sale. |
| Applicable interest rate | Maharashtra Rule 18 | SBI highest MCLR plus two percentage points; state the applicable rate/date and calculation method. |
| Defect remedy | Section 14(3) | Covered defect notified within five years from possession; rectify within 30 days without charge. |
| Specified-sum banking modes | Income-tax Act, 2025, Section 185 | INR 20,000 or more under the receipt/outstanding/aggregate tests triggers prescribed modes for non-exempt cases; possible penalty under Section 450. |
| Resident-property TDS | Section 393(1), Table 3(i) | Normal valid-PAN 1% on higher consideration/stamp-duty value if either is at least INR 50 lakh; current Form 141 Schedule B. |
| Agent default penalty | RERA Section 62 | INR 10,000 per default day, capped cumulatively at 5% of the applicable property cost. |
| Record retention | PMLA Section 12 | Transaction records: five years from transaction. Identity/account records: five years after later relationship-end/account-close. |
5. Revision Strategy
- Distinguish a rental tenant from a leasehold purchaser and covered parking from open parking.
- Understand the 70% deposit and controlled withdrawals. The remaining 30% is not automatically freely available profit. Current MahaRERA model documentation identifies designated collection, separate and transaction accounts.
- Establish whether a project is required to register before applying the agent’s registration-related duty. Exempt projects are not converted into required projects by the fact that an agent is involved.
- Use the correct statutory trigger: INR 20,000 is not permitted cash; INR 50 lakh is reached at equality for the relevant TDS value tests; the 10% advance test operates before the registered agreement.
- Use the applicable stamp-duty value, instrument, jurisdiction, transaction date and concession. Do not assume one universal 6% or 7% charge for all Maharashtra cities and buyers.
- Practise factual and scenario questions across the listed official syllabus. The chart below is an author’s example allocation of revision time, not published examination-domain weights or a prediction of question counts.
Primary sources: Current RERA Act, Sections 4, 10, 13, 14, 18 and 62; Maharashtra model agreement, clause 1(g); MahaRERA conciliation guidance; model allotment letter; current tax and FIU sources cited in Section 7.2.
If a promoter fails to complete or give possession of an apartment by the date specified in the Agreement for Sale, what primary remedy is available to the allottee under Section 18 of RERA?
Withdraw and seek refund with applicable interest, or continue and receive monthly delay interest
Continue and claim delay interest only after the promoter eventually delivers possession
Withdraw and seek principal only, because statutory interest applies only to buyers who continue
Accept an automatic one-year extension before any Section 18 delay remedy can arise
Under Section 14(3) of RERA, what is the duration of the defect liability period during which the promoter must rectify structural or workmanship defects without extra charge?
1 year from booking date
2 years from agreement registration
3 years from building plan sanction
5 years from the date of handing over possession
Which description matches the published MahaRERA Conciliation Forum procedure for an admissible promoter–allottee dispute?
The forum imposes a settlement on the promoter immediately after the allottee files a request
The promoter accepts the request; impartial conciliators assist the parties toward signed settlement terms
The forum issues a binding appellate judgment reviewing an Authority order without party agreement
The promoter’s acceptance is presumed once the allottee files the conciliation request
An agent continues a covered Section 9 default after registration expires. Which Section 62 penalty rule applies?
INR 10,000 once, irrespective of how long the default continues
INR 10,000 per day, capped at 10% of all commission earned by the agent
INR 10,000 per default day, cumulatively capped at 5% of the applicable property cost
INR 20,000 per day, cumulatively capped at 5% of the advances collected
Sections you finish are checked off in the contents.
You've completed this section
Continue exploring other exams