Key Takeaways

  • NEC 90.1 defines the code's sole legal mandate as the practical safeguarding of persons and property from electrical hazards, explicitly stating it is not a design manual or instruction guide for untrained persons.
  • Under NEC 90.2(B)(5), utility installations are exempt from NEC enforcement only if they meet the strict three-prong exclusive control test: utility ownership/operation, exclusive control, and location on dedicated easements or public rights-of-way.
  • The Authority Having Jurisdiction (AHJ) holds statutory power under NEC 90.4 to interpret rules, approve equipment, and grant written special permission for alternative methods that maintain equivalent safety.
  • Mandatory rules ('shall'/'shall not') require strict compliance, permissive rules ('shall be permitted'/'shall not be required') allow design options or exceptions, and Informational Notes provide non-enforceable guidance (NEC 90.5).
  • Comprehensive plan review requires synchronizing the NEC with IBC Chapter 27 (power/emergency), IBC Section 714 (firestop penetrations), IECC Section C405 (energy/lighting controls), and IBC 107.3.4 (deferred submittals).
Last updated: August 2026

1.1 Scope, Administration & the Plans Examiner's Role

Executive Overview for Plans Examiners: The International Code Council (ICC) Electrical Plans Examiner (E3) certification tests an examiner's ability to verify that electrical construction documents comply with the adopted codes before a single conduit is bent or wire is pulled. The primary reference is the National Electrical Code (NEC / NFPA 70), supplemented by model building codes such as the International Building Code (IBC), International Energy Conservation Code (IECC), and International Fire Code (IFC). Navigating jurisdictional boundaries, understanding statutory administrative authority, distinguishing mandatory from permissive code rules, and managing deferred submittals form the cornerstone of domain administration.


1. NEC Article 90: Philosophy, Purpose, and Mandate

To conduct a legally sound and technically rigorous plan review, the plans examiner must understand the exact scope and limitations established in NEC Article 90 (Introduction).

+-----------------------------------------------------------------------------------+
|                             NEC ARTICLE 90 FOUNDATION                             |
+-----------------------------------------------------------------------------------+
|  90.1(A) Practical Safeguarding: Severe hazards from use of electricity           |
|  90.1(B) Adequacy: Code provides minimum safety; NOT a design specification       |
|  90.1(C) Intention: NOT an instruction manual for untrained persons               |
|  90.2(A) Scope Covered: Public/private premises, yards, lots, industrial, grid    |
|  90.2(B) Scope Excluded: Utility exclusive control, vehicles, watercraft, mines   |
|  90.4    AHJ Authority: Interpretation, approval, special permission, variances   |
|  90.5    Rule Types: Mandatory ('shall'), Permissive ('permitted'), Informational |
+-----------------------------------------------------------------------------------+

Practical Safeguarding vs. Design Manual (NEC 90.1)

  • NEC 90.1(A) Practical Safeguarding: The purpose of the NEC is the practical safeguarding of persons and property from hazards arising from the use of electricity. Electrical hazards primarily include electric shock, electrocution, electrical burns, arc-flash thermal injuries, arc-blast pressure waves, and electrical ignition of combustible materials or structures.
  • NEC 90.1(B) Adequacy: The code contains provisions considered necessary for safety. Compliance with these rules will result in an installation that is essentially free from hazard but not necessarily efficient, convenient, or adequate for good service or future expansion of electrical use. Plans examiners cannot reject a plan set merely because a design lacks spare breaker capacity or extra receptacle convenience, provided the minimum code-prescribed loads and safety requirements are satisfied.
  • NEC 90.1(C) Intention: The NEC is not intended as a design specification or an instruction manual for untrained persons. Plans examiners assume drawings are prepared by or under the supervision of qualified electrical design professionals (e.g., Registered Professional Engineers or licensed master electricians, as mandated by state licensing statutes).

2. Jurisdictional Scope & The Utility Exclusive Control Test (NEC 90.2)

One of the most frequent jurisdictional disputes during commercial and industrial plan review centers on whether a specific electrical installation falls under the enforcement purview of the local building department (NEC) or the regulated electric utility (National Electrical Safety Code / NESC / IEEE C2).

Covered Installations (NEC 90.2(A))

The NEC covers the installation of electrical conductors, equipment, and raceways; signaling and communications conductors, equipment, and raceways; and optical fiber cables and raceways for:

  1. Public and private premises, including buildings, structures, mobile homes, recreational vehicles, and floating buildings.
  2. Yards, lots, parking lots, carnivals, and industrial substations.
  3. Installations of conductors and equipment that connect to the supply of electricity.
  4. Installations used to export electric power from vehicles and premises wiring systems to utility grids or other energy distribution systems (e.g., bidirectional EV charging, microgrids, solar PV, and battery energy storage systems).

Non-Covered Installations (NEC 90.2(B))

The NEC does not cover:

  1. Installations in ships, watercraft (other than floating buildings), railway rolling stock, aircraft, or automotive vehicles (other than mobile homes and RVs).
  2. Installations underground in mines and self-propelled mobile surface mining machinery.
  3. Installations of communications equipment under the exclusive control of communications utilities located outdoors or in building spaces used exclusively for such installations.
  4. Installations under the exclusive control of an electric utility.

The 3-Prong Utility Exclusive Control Test (NEC 90.2(B)(5))

For an installation to be legally exempt from NEC enforcement under the utility exemption, the examiner must apply the strict three-prong exclusive control test:

Utility Exemption=[Utility Owned/Operated][Exclusive Control][Public ROW or Dedicated Utility Easement]\text{Utility Exemption} = [\text{Utility Owned/Operated}] \land [\text{Exclusive Control}] \land [\text{Public ROW or Dedicated Utility Easement}]

Test ElementRequirementPlan Review Verification
1. Ownership & OperationMust be owned, operated, and maintained by a legally recognized electric utility entity.Private submetering, privately owned step-down transformers, or tenant-owned wiring are NEVER exempt.
2. Exclusive ControlMust be under the sole, locked, or restricted access and operational control of the utility.If private electrical contractors or non-utility personnel maintain or service the equipment, it fails this test.
3. Location / EasementMust be located outdoors on public rights-of-way, dedicated utility easements, or designated utility property/substations.Installations on private customer property outside designated easements fall strictly under the NEC.

Plan Review Trap — Site Lighting: A developer submits site plans showing outdoor parking lot lighting poles installed on private commercial property. The developer argues the poles are exempt because the utility will provide power directly from an overhead transformer. Verdict: Unless the utility owns, operates, and retains exclusive control over the luminaires under a formal utility easement, the branch circuits, underground raceways, grounding conductors, and pole handhole bonding must fully comply with NEC Articles 210, 225, 250, and 410.


3. AHJ Statutory Authority, Interpretations & Code Language (NEC 90.4 & 90.5)

Authority Having Jurisdiction (AHJ) Powers (NEC 90.4)

The plans examiner acts as a legal representative of the Authority Having Jurisdiction (AHJ). Under NEC 90.4, the AHJ has the legal responsibility and authority for:

  • NEC 90.4(A) Enforcement: Enforcing the code and issuing formal approvals or rejection notices.
  • NEC 90.4(B) Interpretations & Approvals: Rendering formal interpretations of code rules and approving equipment and materials as meeting the requirements of the code (pursuant to NEC 110.2 and 110.3).
  • NEC 90.4(C) Special Permission: Granting written permission for the use of alternative methods, materials, or waivers of specific requirements where equivalent safety is demonstrated. Special permission is defined in Article 100 as the written consent of the Authority Having Jurisdiction.
  • NEC 90.4(D) Custom Equipment & New Products: For unique, custom-built industrial equipment or emerging technologies not yet listed by a Nationally Recognized Testing Laboratory (NRTL), the AHJ may evaluate product safety based on engineering data, manufacturer test records, or field evaluations by an accredited third-party agency.

Mandatory Rules, Permissive Rules & Explanatory Material (NEC 90.5)

Understanding the legal grammar of the NEC is vital when writing enforceable plan review comments:

+---------------------------------------------------------------------------------+
|                       NEC 90.5 CODE GRAMMAR & LEGAL WEIGHT                       |
+---------------------------------------------------------------------------------+
|  MANDATORY RULES (90.5(A))    |  'shall' or 'shall not'                         |
|                               |  -> Strict, non-negotiable legal requirement     |
+-------------------------------+-------------------------------------------------+
|  PERMISSIVE RULES (90.5(B))   |  'shall be permitted' or 'shall not be required'|
|                               |  -> Legally recognized options or exceptions     |
+-------------------------------+-------------------------------------------------+
|  INFORMATIONAL NOTES (90.5(C))|  'Informational Note: ...'                      |
|                               |  -> Non-enforceable explanatory material only    |
+---------------------------------------------------------------------------------+
  • Mandatory Rules (90.5(A)): Characterized by the words shall or shall not. These are absolute legal requirements. Example: "Enclosures for overcurrent devices shall be mounted in a vertical position unless that is shown to be impracticable." (NEC 240.33).
  • Permissive Rules (90.5(B)): Characterized by the words shall be permitted or shall not be required. These identify design choices or exceptions to mandatory rules. Example: "Branch circuits supplying lighting units that are installed in ceiling cavities shall be permitted to be wired with Type MC cable."
  • Explanatory Material (90.5(C)): Informational Notes contain non-enforceable reference material, cross-references, or industry background. A plan examiner cannot issue a plan review correction notice citing only an Informational Note.

4. Multi-Code Synchronization (IBC, IECC, IFC)

An electrical plan review is never conducted in isolation. The plans examiner must cross-reference the NEC with the adopted family of International Codes (I-Codes):

                         +-----------------------------+
                         |   ELECTRICAL PLANS REVIEW   |
                         +--------------+--------------+
                                        |
         +-----------------+------------+------------+-----------------+
         |                 |                         |                 |
         v                 v                         v                 v
  +--------------+  +--------------+          +--------------+  +--------------+
  |   NEC 2023   |  |  IBC CH 27   |          |  IECC C405   |  |    IFC 12    |
  | (NFPA 70)    |  | & SEC 714    |          | (Energy)     |  | (Fire/ESS)   |
  | Electrical   |  | Firestop &   |          | Lighting &   |  | Standby &    |
  | Systems      |  | Life Safety  |          | Power Density|  | Battery ESS  |
  +--------------+  +--------------+          +--------------+  +--------------+

1. International Building Code (IBC) Chapter 27 & Section 714

  • IBC Chapter 27 (Electrical): Mandates emergency and standby power systems (IBC 2702), secondary power supplies for high-rise buildings, elevator disconnect operation (IBC 3005), and emergency voice/alarm communications.
  • IBC Section 714 (Penetrations & Firestopping): When electrical raceways, cables, or busways penetrate fire-resistance-rated walls, floors, or smoke barriers, they must be protected by an approved through-penetration firestop system listed under ASTM E814 or UL 1479.
    • F-Rating: Must match the fire-resistance rating of the assembly (e.g., 2-hour F-rating for a 2-hour wall).
    • T-Rating: Limits temperature rise on the unexposed surface to $325^\circ\text{F}$ above ambient, required for floor penetrations outside fire-rated shafts.
    • Membrane Penetrations (IBC 714.4.2): Maximum 100 sq. inches of electrical outlet boxes per 100 sq. ft. of wall area. Outlet boxes on opposite sides of a rated wall must be horizontally separated by at least 24 inches unless protected by listed firestop putty pads or listed metallic outlet boxes.

2. International Energy Conservation Code (IECC) Section C405

  • Interior Lighting Power Allowance (IECC C405.3.2): Enforces maximum Lighting Power Density (LPD in Watts/sq. ft.) using either the Building Area Method or Space-by-Space Method.
  • Automatic Lighting Controls (IECC C405.2): Mandates occupancy sensors in offices, classrooms, conference rooms, restrooms, and storage rooms to automatically turn lighting off within 20 minutes of occupants leaving.
  • Daylight Responsive Controls (IECC C405.2.3): Required for luminaires located in sidelit and toplit daylight zones.
  • Automatic Receptacle Control (IECC C405.10): At least 50% of all 125V, 15A and 20A receptacles in private offices, open offices, conference rooms, and print rooms must be automatically controlled to de-energize when spaces are unoccupied.

3. International Fire Code (IFC) Chapter 12

  • Stationary Energy Storage Systems (ESS) (IFC 1207 / NFPA 855): Imposes maximum energy capacity limits (typically 50 kWh or 250 kWh per group), spacing requirements (minimum 3 ft between battery groups and between groups and walls), thermal runaway containment, deflagration explosion venting, and dedicated fire suppression.
  • Emergency and Standby Power Systems (IFC 1203 / NFPA 110): Specifies runtime durations (Class), power restoration transfer times (Type 10 = 10 seconds for emergency egress; Type 60 = 60 seconds for legally required standby), and fuel storage capacity.

5. Phased Submittals & Deferred Submittals (IBC 107.3.4)

On large commercial projects, developers frequently request permits before the complete electrical engineering package is fully drafted. The plans examiner must enforce the administrative protocols of IBC Section 107.3.4.

+-----------------------------------------------------------------------------------+
|                    IBC 107.3.4 DEFERRED SUBMITTAL LEGAL FLOW                      |
+-----------------------------------------------------------------------------------+
|  1. PERMIT APPLICATION: Registered Design Professional (RDP) lists all deferred   |
|     items on the main structural/architectural plan cover sheet.                  |
|                                                                                   |
|  2. SHOP DRAWING SUBMITTAL: Specialty contractor prepares deferred drawings       |
|     (e.g., Fire Alarm, Solar PV/ESS, Smoke Control Wiring).                       |
|                                                                                   |
|  3. RDP IN RESPONSIBLE CHARGE REVIEW: RDP audits shop drawings, verifies          |
|     compatibility with building systems, and applies formal REVIEW STAMP.         |
|                                                                                   |
|  4. AHJ SUBMITTAL & APPROVAL: Documents submitted to AHJ. Work CANNOT proceed on  |
|     deferred items until the AHJ issues written approval.                         |
+-----------------------------------------------------------------------------------+

Rules for Deferred Submittals

  1. Prior AHJ Authorization: Deferred submittals are permitted only with prior approval of the building official.
  2. RDP Schedule on Plans: The cover sheet of the primary permit drawing set must include a clear schedule listing all deferred submittal items.
  3. RDP Review Stamp is Mandatory: Submittals cannot be routed directly from an electrical subcontractor to the building department. The Registered Design Professional (RDP) in responsible charge must first review, coordinate, and apply an approval stamp stating that the deferred documents conform to the approved design intent.
  4. Prohibition of Installation: It is unlawful to install deferred systems on the construction site prior to the plans examiner issuing a formal permit revision or written approval.

0. Exam Logistics a Plans Examiner Must Confirm Before Studying

The E3 is an open-book examination, and the single most consequential registration decision is the code year. ICC currently offers the Electrical Plans Examiner (E3) exam against either the 2020 NEC or the 2023 NEC, and the candidate selects which version to sit when registering. The approved references are NFPA 70, National Electrical Code, in the edition matching the exam version chosen, plus Ugly's Electrical References (any edition).

ItemCurrent ICC specification
Exam IDE3 — Electrical Plans Examiner
Format70 multiple-choice questions
Time limit3.5 hours (3:30)
Book policyOpen book
Approved referencesNFPA 70 (NEC), 2020 or 2023 edition per the exam version selected; Ugly's Electrical References (any edition)
ScoringNational Certification exams use a scale score set at 75
DeliveryIn-person test center or ICC PRONTO online remote proctoring

[!IMPORTANT] This guide is written to the 2023 NEC. If your jurisdiction has adopted the 2020 NEC and you register for the 2020 version of E3, a number of the section numbers used throughout this guide will not match your codebook — Article 220 in particular was reorganized in the 2023 edition, so the 2020 numbers 220.11, 220.12, 220.18, 220.42, 220.43, and 220.44 became 220.5(C), 220.42, 220.11, 220.45, 220.46, and 220.47 respectively. Verify the code year on your registration confirmation before you tab your book.

[!CAUTION] ICC permits copyrighted, bound books at the test administration, including the listed approved references. Training materials — presentations, study guides, and practice questions — are not permitted. All exam questions are based solely on the approved reference list, and only those references may be used as the basis for appealing a question. Tabbing and highlighting your own codebook is allowed; carrying this guide into the exam room is not.


Loading diagram...
Plan Examiner Jurisdictional & Submittal Workflow (NEC 90.2 / IBC 107.3.4)
Test Your Knowledge

A commercial shopping center site plan includes exterior pole-mounted luminaires situated throughout a private parking lot. The developer claims the lighting installation is exempt from the NEC because the local electric utility provides electric service directly from a street transformer. Which of the following determinations by the electrical plans examiner is legally correct under NEC 90.2?

A
B
C
D
Test Your Knowledge

During a commercial plan review, a plans examiner encounters a note on the electrical lighting drawings that conflicts with an Informational Note in NEC Article 210. How should the plans examiner treat the Informational Note under NEC 90.5?

A
B
C
D
Test Your Knowledge

An electrical contractor submits fire alarm and battery energy storage system (ESS) shop drawings directly to the building department as a deferred submittal after the main building permit was issued. Under IBC Section 107.3.4, what must occur before the plans examiner can review and approve these drawings?

A
B
C
D
Test Your Knowledge

An electrical plan review of a 4-story commercial office building indicates electrical metallic tubing (EMT) raceways penetrating a 2-hour fire-resistance-rated shaft enclosure. According to IBC Section 714, what specific rating and certification must be detailed on the submitted drawings for this through-penetration?

A
B
C
D