2.1 Florida Construction Lien Law (F.S. 713) & Notice to Owner Rules

Key Takeaways

  • A Notice to Owner (NTO) must be served on the property owner before commencing work or within 45 days of first furnishing labor, services, or materials, and strictly prior to final payment to the direct contractor.
  • A Notice of Commencement (NOC) must be recorded in the county public records by the property owner before commencing work for improvements exceeding $5,000, establishing the priority date for all subsequent construction liens.
  • A Claim of Lien must be recorded in county public records within 90 days of the last date of furnishing labor, services, or materials to the jobsite, excluding warranty or remedial repair work.
  • The statutory timeframe to enforce a recorded Claim of Lien is 1 year from the recording date, which can be shortened to 60 days via a Notice of Contest of Lien or 20 days via a Summons to Show Cause.
  • Direct roofing contractors must furnish a Contractor's Final Payment Affidavit to the property owner at least 5 days prior to filing suit or receiving final contract payment.
Last updated: July 2026

2.1 Florida Construction Lien Law (F.S. 713) & Notice to Owner Rules

Florida's Construction Lien Law, codified in Florida Statutes Chapter 713 (Part I), is one of the most critical legal frameworks that every licensed Florida Roofing Contractor (CCC) must master. The primary purpose of the lien law is twofold: it provides a powerful statutory mechanism for contractors, subcontractors, sub-subcontractors, and material suppliers to secure payment for labor and materials used to improve real property, while simultaneously establishing a structured procedure to protect property owners from paying twice for the same work.

Exam Warning: Understanding who has lien rights—and who does not—is heavily tested on the Florida Roofing Contractor trade and business exams. Under F.S. 713.01, material suppliers who sell materials to another material supplier (known as "suppliers-to-suppliers") do NOT possess statutory lien rights. Lien rights extend only to direct contractors, subcontractors, sub-subcontractors, materialmen supplying contractors or subcontractors, and registered professional lienors (architects, engineers, and land surveyors).


The Notice of Commencement (NOC)

The Notice of Commencement (NOC), governed by F.S. 713.13, is the legal document that triggers the formal construction lien process. Before any construction, alteration, or roofing work begins on real property where the direct contract price exceeds $5,000 (formerly $2,500 prior to recent statutory updates; note that HVAC replacement direct contracts have a $15,000 threshold), the property owner or authorized agent must record an NOC in the public records of the county where the property is located.

Key Requirements for the NOC

  • Recording & Posting: The owner must record the NOC with the clerk of the circuit court and post a certified copy (or notarized copy) conspicuously at the jobsite before work commences or initial inspections are performed.
  • Duration: Unless a shorter or longer duration is explicitly stated in the recorded NOC form, an NOC is valid for one year from the date of recording.
  • Legal Effect & Priority: The NOC establishes the official legal priority date for all subsequent claims of lien filed on the project. Any Claim of Lien recorded while a valid NOC is in effect relates back to the recording date of the NOC.
  • Improper Payments: If a property owner makes payments to a direct contractor without recording an NOC, or makes payments after an NOC has expired, those payments are classified as improper payments. If subcontractors or suppliers remain unpaid, the owner can be forced to pay those sub-lienors even if the full contract price was already paid to the direct contractor.

Notice to Owner (NTO) Rules & Statutory Deadlines

For roofing subcontractors, sub-subcontractors, and material suppliers who are not in direct privity (i.e., do not have a direct contract) with the property owner, serving a Notice to Owner (NTO) under F.S. 713.06 is a mandatory prerequisite to establishing a valid construction lien.

Critical NTO Deadlines

  1. 45-Day Rule: The NTO must be served on the property owner before commencing work or no later than 45 days after the date the lienor first furnishes labor, services, or materials to the jobsite.
  2. Prior to Final Payment: Regardless of the 45-day window, the NTO must be served before the property owner makes final payment to the direct contractor and receives the Contractor's Final Payment Affidavit.
  3. Specially Fabricated Materials: For custom roofing components or specially fabricated metal panels/trusses manufactured off-site, the 45-day clock begins on the date manufacturing commences at the shop, not the date of delivery to the jobsite.

Method of Service (F.S. 713.18)

Serving an NTO must strictly comply with statutory delivery requirements:

  • Registered or Certified Mail: Mailed with postage prepaid and tracking/return receipt requested.
  • Hand Delivery: Physical delivery to the owner, designated agent, or officer of a corporate owner, evidenced by a written affidavit of service.
  • Electronic Service: Permitted if the owner explicitly consented to electronic notice in the contract or NOC.

Note: Direct contractors (who have a direct contract with the owner) are already in privity and are NOT required to serve an NTO.


Statutory Summary of Florida Lien Law Deadlines

The following table outlines the statutory procedures, timelines, and legal references governing Florida Construction Lien Law under F.S. Chapter 713:

Statutory ProcedureGoverning StatuteResponsible PartyMandatory DeadlineConsequence of Non-Compliance
Notice of Commencement (NOC)F.S. 713.13Property OwnerPrior to starting work (contracts > $5,000)Payments made by owner are deemed improper; owner risks double liability
Notice to Owner (NTO)F.S. 713.06Non-privity Lienors (Subs/Suppliers)Within 45 days of first work / before owner final paymentComplete forfeiture of statutory construction lien rights
Claim of Lien RecordingF.S. 713.08All Lienors (Direct & Sub)Within 90 days of last furnishing labor or materialsLien is invalid and unenforceable
Serving Copy of Claim of LienF.S. 713.08(4)(c)LienorWithin 15 days of recording Claim of LienRendered voidable to the extent of demonstrated prejudice to owner
Contractor's Final Payment AffidavitF.S. 713.06(3)(d)Direct ContractorAt least 5 days prior to suit or receiving final paymentBarred from enforcing direct contract lien or instituting lawsuit
Lien Enforcement (Foreclosure)F.S. 713.22LienorWithin 1 year of recording dateLien automatically expires and becomes null and void

Claim of Lien Recording & Service Requirements

If a roofing contractor or subcontractor is not paid for work properly performed, the party must record a formal Claim of Lien in the public records of the county where the property resides pursuant to F.S. 713.08.

90-Day Recording Window

The Claim of Lien must be recorded no later than 90 days from the final date on which the lienor furnished actual labor, services, or materials to the project.

Important Exam Distinction: Remedial work, warranty service, punch-list repairs, or minor touch-ups performed after substantial completion do NOT extend or reset the 90-day recording deadline. The 90-day clock is calculated strictly from the date of substantial completion of the contracted scope of work.

Serving the Claim of Lien

Under F.S. 713.08(4)(c), the lienor must serve a copy of the recorded Claim of Lien on the property owner before recording or within 15 days after recording. While failure to serve within 15 days does not automatically invalidate the lien, it renders the lien voidable to the extent that the owner can demonstrate harm or prejudice resulting from the delay.


Contractor's Final Payment Affidavit

Under F.S. 713.06(3)(d), when a direct roofing contractor completes the project and seeks final payment, or prepares to enforce a construction lien, the contractor must deliver a Contractor's Final Payment Affidavit to the owner. This document is a sworn statement stating that all lienors who served an NTO (subcontractors, roof material suppliers, labor crews) have been paid in full, or listing the exact names and amounts remaining unpaid.

  • The affidavit must be delivered to the owner at least 5 days before filing a lawsuit to enforce a lien.
  • Failure to deliver the affidavit within the 1-year statutory lien enforcement period bars the contractor from enforcing lien rights.

Accelerating Lien Enforcement: Shortening Mechanisms

While a recorded Claim of Lien is valid for 1 year under F.S. 713.22(1), property owners can utilize two statutory mechanisms to force the contractor to act quickly or lose the lien:

  1. Notice of Contest of Lien (F.S. 713.22(2)): The owner or owner's attorney records a Notice of Contest of Lien in the public records. Upon service by the clerk of court, the contractor's window to file a foreclosure lawsuit is dramatically shortened from 1 year to 60 days from the service date.
  2. Action to Show Cause / 20-Day Summons (F.S. 713.21(4)): The owner files a complaint in court, and the clerk issues a summons directing the lienor to show cause within 20 days why the lien should not be vacated and canceled. If the lienor fails to file a foreclosure complaint or show adequate cause within 20 days, the court cancels the lien.

Fraudulent Liens & Penalties (F.S. 713.31)

Florida law imposes severe civil and criminal penalties on contractors who file a Fraudulent Lien. A lien is deemed fraudulent if the lienor willfully exaggerates the amount claimed, includes claims for work not performed or materials not delivered, or compiles the claim with gross negligence.

Legal Consequences of a Fraudulent Lien

  • Loss of Lien Rights: The lien is completely unenforceable and declared void.
  • Criminal Liability: Filing a fraudulent lien exceeding $10,000 is classified as a third-degree felony under F.S. 713.31.
  • Civil Damages & Attorney Fees: The property owner is entitled to recover actual court costs, reasonable attorney fees, bonding fees, and punitive damages equal to the difference between the fraudulent amount claimed and the legitimate amount owed.
Test Your Knowledge

Under F.S. 713.06, what is the mandatory statutory deadline for a roofing subcontractor (who is not in direct privity with the property owner) to serve a Notice to Owner (NTO)?

A
B
C
D
Test Your Knowledge

A commercial roofing contractor completes primary roofing installation on October 1st. On November 15th, the contractor returns to patch a minor leak under warranty. What is the statutory deadline to record a Claim of Lien under F.S. 713.08?

A
B
C
D
Test Your Knowledge

If a property owner records a Notice of Contest of Lien under F.S. 713.22, how does this affect the roofing contractor's timeframe to file a lawsuit to enforce the lien?

A
B
C
D