2.5 Lien Enforcement, Transfers, Releases & Final Affidavits

Key Takeaways

  • A Claim of Lien must be recorded in the county public records within 90 days of the LAST date of actual work and served on the owner within 15 days of recording.
  • General Contractors MUST deliver a notarized Contractor's Final Payment Affidavit to the owner at least 5 days BEFORE filing a lawsuit to enforce a lien or contract.
  • The standard 1-year statute of limitations for enforcing a Claim of Lien can be shortened to 60 days by an owner recording a Notice of Contest of Lien, or to 20 days via a Summons to Show Cause.
  • Recording a cash deposit or surety bond under F.S. § 713.24 transfers the lien off the real property title onto the substitute security.
Last updated: July 2026

Lien Enforcement, Transfers, Releases & Final Affidavits

Once statutory preliminary steps (such as the Notice of Commencement and Notice to Owner) are met, Florida law establishes strict deadlines and formal documentation rules for perfecting, releasing, accelerating, and enforcing construction liens. Failure to comply with exact statutory timelines invalidates lien rights.


1. Perfecting a Claim of Lien (F.S. § 713.08)

A Claim of Lien is the formal legal instrument recorded in the county public records that attaches a monetary encumbrance directly to the owner's real property title.

The 90-Day Recording Rule

  • The Claim of Lien MUST be recorded in the county clerk's office no later than 90 calendar days after the LAST date of actual, substantive work (labor, services, or materials) furnished by the lienor to the project.
  • Punch List & Warranty Exclusions: Under Florida law, performing routine punch list items, warranty repairs, corrective work, or picking up leftover tools does NOT extend the 90-day recording window. The 90-day clock begins on the last day of substantial contract work.

Mandatory Service on Owner (F.S. § 713.08(4)(c))

  • The lienor MUST serve a copy of the recorded Claim of Lien on the Owner within 15 calendar days after recording.
  • Service must be executed via certified mail, hand delivery, or overnight courier. Failure to serve the copy within 15 days renders the lien voidable if the owner demonstrates damage or prejudice.

2. Contractor's Final Payment Affidavit (F.S. § 713.06(3)(d))

The Contractor's Final Payment Affidavit is a mandatory notarized document required exclusively from the General Contractor (direct contractor) upon project completion:

The 5-Day Rule: The General Contractor MUST deliver a notarized Contractor's Final Payment Affidavit to the Owner at least five (5) calendar days BEFORE filing a lawsuit to enforce a mechanics lien or breach of contract claim.

Required Contents

  1. Sworn statement certifying that all labor, services, and materials have been completed.
  2. Itemized list of all subcontractors and suppliers (who gave timely NTOs) detailing whether they have been paid in full or listing the exact monetary amount remaining unpaid.

Fatal Defect: Delivering the Final Payment Affidavit less than 5 days before filing suit—or failing to deliver it entirely—is a fatal defect that mandates dismissal of the contractor's lawsuit.


3. Lien Enforcement Timelines & Acceleration Mechanisms

Under standard conditions, a recorded Claim of Lien remains valid for one (1) year from its recording date. An enforcement lawsuit (foreclosure of lien) must be filed within that window:

Standard Lien Enforcement Window: 1 Year from Recording Date\text{Standard Lien Enforcement Window: } 1 \text{ Year from Recording Date}

However, Florida law provides property owners two statutory mechanisms to accelerate the lien enforcement timeline and clear property title rapidly:

MechanismInitiated ByStatutory Window Shortened ToLegal Basis
Standard LimitationStatutory Default1 Year from lien recording dateF.S. § 713.22(1)
Notice of Contest of LienOwner records in clerk's office & serves on lienor60 Days from date of service of contest noticeF.S. § 713.22(2)
20-Day Summons to Show CauseOwner files court complaint; clerk issues summons20 Days from service of court summonsF.S. § 713.21(4)

If the lienor fails to file a formal court lawsuit within the shortened 60-day or 20-day timeframe, the Claim of Lien is automatically discharged and extinguished as a matter of law.


4. Lien Waivers & Releases (F.S. § 713.20)

A lien waiver (release) surrenders statutory lien rights in exchange for payment. Florida Statute § 713.20 establishes standard statutory forms:

Types of Lien Releases

  • Partial Lien Release: Executed during progress payments; releases lien rights for labor and materials furnished through a specific effective date.
  • Final Lien Release: Executed upon final payment; completely releases all past, present, and future lien rights on the property.

Conditional vs. Unconditional Releases

  • Conditional Release: States that the waiver is effective ONLY UPON actual receipt and clearance of funds in the lienor's bank account. (Protects contractors against bounced checks).
  • Unconditional Release: Instantly surrenders lien rights upon signing, regardless of whether the payment check clears the bank. (High risk if check dishonors).

Statutory Form Protection: Under F.S. § 713.20, an owner or GC cannot require a lienor to execute a lien waiver that differs from the statutory form unless specified in the project contract.


5. Transferring Lien to Security (Bond) (F.S. § 713.24)

When a contractor files a Claim of Lien against private property, it clouds the owner's title, preventing sales or refinancing. Florida Statute § 713.24 permits an owner or general contractor to transfer the lien off the real property title onto alternative financial security:

Transfer Security Options

  1. Cash Deposit with the Clerk of the Circuit Court; OR
  2. Surety Bond executed by a licensed Florida surety insurer.

Statutory Transfer Formula

Bond Amount=Lien Amount+Interest (at legal rate for 3 years)+(Greater of $1,000 or 25% of Lien Amount for Costs/Attorneys’ Fees)\text{Bond Amount} = \text{Lien Amount} + \text{Interest (at legal rate for 3 years)} + \left( \text{Greater of } \$1,000 \text{ or } 25\% \text{ of Lien Amount for Costs/Attorneys' Fees} \right)

Once transferred, the real property is completely freed from the lien, and the lienor's legal remedy shifts strictly to asserting a claim against the cash deposit or surety bond.


Worked Scenario: Lien Recording, Contest, and Transfer

Scenario: An Earthwork Subcontractor completes grading work on a commercial project in Fort Lauderdale on May 1st. On August 15th (106 days after last work), the sub records a Claim of Lien for $60,000. Realizing an error, the sub discovers that their actual last site work (installing erosion control mats required by specs) occurred on May 20th (87 days prior to August 15th). On September 1st, the Owner records a Notice of Contest of Lien. On September 15th, the Owner transfers the lien to a surety bond under F.S. § 713.24.

Analysis:

  1. Lien Recording Validity: August 15th is within 90 days of May 20th (last substantive contract work). The Claim of Lien was timely perfected.
  2. Impact of Notice of Contest: Recording the Notice of Contest shortens the sub's enforcement window from 1 year to 60 days from September 1st (until October 31st).
  3. Transfer to Bond Effect: The transfer under F.S. § 713.24 removes the cloud on the property title. The subcontractor must file a lawsuit against the surety bond before October 31st to preserve recovery.
Test Your Knowledge

Under Florida Statute § 713.08, what is the maximum deadline for recording a Claim of Lien in the county public records after the LAST day of furnishing labor or materials?

A
B
C
D
Test Your Knowledge

Under F.S. § 713.06(3)(d), at least how many days BEFORE filing a lawsuit to enforce a construction lien must a General Contractor deliver a Contractor's Final Payment Affidavit to the Owner?

A
B
C
D
Test Your Knowledge

When an Owner records and serves a Notice of Contest of Lien under F.S. § 713.22(2), to what timeframe is the lienor's enforcement window shortened?

A
B
C
D