6.1 Quantity Takeoff & Material Estimating
Key Takeaways
Concrete volume is calculated in cubic yards using CU YD = (Length × Width × Depth in feet) / 27, requiring depth in inches to be divided by 12 before multiplying.
Lumber board feet measurements use nominal dimensions using BF = (Nominal Thickness × Nominal Width × Length in feet) / 12, regardless of dressed actual size.
CMU block counts rely on a standard face area of 8" x 16" (0.889 sq ft), yielding a multiplier of 1.125 blocks per square foot of wall face area.
Roofing materials are estimated in squares (1 SQ = 100 sq ft) and require multiplying flat area by roof pitch multipliers before adding waste factors.
Material waste factors (typically 5% to 15%) must be added to net quantities to prevent material shortages during jobsite placement.
Quantity Takeoff & Material Estimating
Quantity Takeoff (QTO) is the foundation of construction estimating. A general contractor must systematically measure, count, and calculate the exact physical quantities of materials required from contract drawings and specifications. In Florida contractor licensing examinations, quantity takeoff questions test both basic geometric conversion skills and industry-standard waste application.
Estimators classify material takeoffs into discrete units of measurement based on trade practice:
| Material Category | Primary Unit of Measure | Abbreviation | Common Calculation Formula / Notes |
|---|---|---|---|
| Concrete & Excavation | Cubic Yards | CU YD / CY | |
| Dimensional Lumber | Board Feet | BF | |
| Concrete Masonry Units | Block Count / Sq Ft | EA / SF | Wall SF blocks/SF |
| Drywall & Sheathing | Square Feet / Sheets | SF / EA | Total Surface Area / Sheet Area ( SF) |
| Roofing Coverings | Squares | SQ | of roof surface |
| Structural Steel | US Tons | Ton / TN | Total Weight (lbs) / lbs/ton |
1. Concrete Volume & Formwork Calculations
Concrete is placed and purchased in Cubic Yards ( or CY). Ready-mix concrete suppliers batch materials by volume, with standard truck capacities ranging from to cubic yards.
The Cubic Yard Formula
To compute concrete volume, all dimensions—Length (), Width (), and Depth/Thickness ()—must be expressed in feet before dividing by (since ):
When thickness is given in inches (e.g., a 4-inch or 6-inch slab), convert inches to feet by dividing by (; ).
LENGTH (ft)
+-----------------------------------+
/ /|
/ / | WIDTH (ft)
+-----------------------------------+ |
| | +
| | / DEPTH (in) / 12
| |/
+-----------------------------------+
Continuous Footings and Thickened Edges
For continuous footings around a perimeter, calculate the centerline length () to avoid double-counting corners:
Alternatively, sum the outside lengths of two opposite sides and the inside lengths of the remaining two sides.
Formwork Surface Contact Area
Concrete forms are estimated in Square Feet of Contact Area (SFCA). For continuous wall footings formed on two sides:
2. Lumber Board Feet & Structural Framing Takeoffs
Lumber quantities for structural framing are quoted in Board Feet (BF). One board foot represents a nominal volume of lumber equal to 1 inch thick by 12 inches wide by 1 foot long ().
The Board Foot Formula
Crucially, board foot calculations always use NOMINAL dimensions (e.g., , , ), NOT actual dressed dimensions ( or ):
If length is given in inches (), the denominator becomes :
Exam Callout: On Florida licensing exams, if a problem asks for the board footage of twenty studs that are feet long, do not substitute actual measurements (). Calculate: .
Wall Stud Quantity Math
To estimate studs for a wall framed at inches on center (o.c.):
Add extra studs for corners ( studs per corner), intersections ( studs per tee-wall), and door/window openings ( king studs and jack studs per opening).
3. Concrete Masonry Units (CMU) & Mortar/Grout Takeoffs
Florida commercial and residential construction relies heavily on concrete masonry unit (CMU) block construction due to high-velocity hurricane zone (HVHZ) wind requirements.
CMU Face Count Formula
A standard stretcher CMU block has nominal dimensions of (including a mortar joint). The elevation face area of one standard block is:
To find the number of blocks needed for a wall:
Where . Deduct full openings greater than sq ft (such as large garage doors or storefront windows).
+-----------------------+ <-- 8" High
| (CORE 1) | (CORE 2) |
+-----------------------+
|<------ 16" Long ------>|
Masonry Mortar and Grout Volume
- Mortar: Approximately to cubic feet of mortar are required per CMU blocks (or roughly to cubic feet per blocks).
- Grout Core Fill: A standard 8-inch hollow CMU block has an open core volume of approximately cu ft per block (or cu ft per core). For solid grouted masonry walls ( cores filled), multiply total block count by and divide by to yield total cubic yards of grout.
4. Roofing, Drywall & Steel Weight Takeoffs
Roofing Takeoff & Pitch Multipliers
Roofing material is measured in Squares (SQ), where . Sloped roofs require multiplying flat plan view areas by a Roof Pitch Multiplier:
| Roof Slope (Rise : 12" Run) | Pitch Factor / Multiplier |
|---|---|
| 3 : 12 | |
| 4 : 12 | |
| 5 : 12 | |
| 6 : 12 | |
| 8 : 12 | |
| 12 : 12 |
Drywall Board Count
Gypsum wallboard (drywall) is estimated in square feet or standard sheets (; ). Deduct openings larger than sq ft. Divide net area by sheet square footage and round up to the nearest whole sheet.
Structural Steel Weight
Structural steel shapes are designated by nominal depth and weight per linear foot. For example, a W12×26 beam weighs lbs per linear foot. Total tonnage is calculated as:
5. Waste Factors & Estimating Margin Adjustments
Raw quantity calculations produce net quantities. Estimators must apply trade-specific waste factors to determine order quantities:
| Material Category | Typical Industry Waste Allowance |
|---|---|
| Concrete Footings & Slabs | |
| Concrete Masonry Units (CMU) | |
| Framing Lumber & Joists | |
| Roof Shingles / Underlayment | |
| Gypsum Wallboard | |
| Structural Steel |
Worked Comprehensive Takeoff Example
Scenario: A general contractor is estimating materials for a rectangular commercial building slab and stem wall in Orlando, FL:
- Building Footprint:
- Slab Thickness:
- Perimeter Continuous Edge Footing: below slab
- Stem Wall Height: (8-inch CMU block, solid grouted)
- Waste Factors: Concrete (), CMU Block (), Grout ()
Step 1: Calculate Concrete Volume for Slab
- Slab Area
- Slab Thickness
- Net Slab Concrete Volume
Step 2: Calculate Continuous Edge Footing Concrete
- Outside Perimeter
- Footing Width
- Footing Centerline Length
- Footing Cross-Section
- Net Footing Concrete Volume
- Total Net Concrete
- Total Concrete Order (with 5% Waste) (Order or CY).
Step 3: Calculate CMU Block and Grout Count
- Wall Elevation Area
- Net Block Count
- Total CMU Order (with 8% Waste)
- Net Grout Volume
- Total Grout Order (with 10% Waste) .
A general contractor is purchasing lumber for a floor framing system requiring 40 floor joists. Each joist is a nominal 2" x 10" piece that is 18 feet long. How many board feet (BF) of lumber must be ordered, before accounting for waste?
600 BF
1,200 BF
1,440 BF
14,400 BF
How many cubic yards of concrete are required for a 60 ft long by 40 ft wide slab that is 6 inches thick, assuming a 5% waste factor?
41.25 CY
44.44 CY
46.67 CY
533.33 CY
An estimator is performing a masonry takeoff for a building foundation wall measuring 160 linear feet in perimeter and 8 feet in height. Using the standard CMU block multiplier of 1.125 blocks per square foot, how many blocks are required if a 10% waste factor is included?
1,280 blocks
1,440 blocks
1,500 blocks
1,584 blocks
A structural steel floor framing plan calls for 15 wide-flange beams designated as W14×34, each with a span length of 30 feet. What is the total weight of these beams in US tons?
7.65 Tons
15.30 Tons
30.60 Tons
15,300 Tons
Sections you finish are checked off in the contents.