11.3 Activation Readiness, Transition Planning & Finalizing the POE Research Plan

Key Takeaways

  • CHD's exam content outline says activation readiness (staff relocation) should incorporate the new processes and workflows linked to evidence-based design strategies.
  • Outline activation steps include developing an activation timeline, reviewing research hypotheses and annotated diagrams, and training on future-state people, process, technology, and physical-environment changes.
  • Readiness also includes staff recruitment, occupant orientation and training, tabletop exercises, full-size mock-up simulations, and pre-occupancy day-in-the-life exercises.
  • The outline calls for updating and finalizing the research plan for post-occupancy evaluation and proposed design research before occupancy.
  • New facilities often see a temporary period of disruption after move-in, which is one reason CHD materials advise waiting at least six months before post-occupancy data collection.
Last updated: September 2026

Activation Readiness, Transition Planning & Finalizing the POE Research Plan

EDAC Core Concept: A building designed around evidence-based workflows only delivers its intended outcomes if people actually work that way on the first day and beyond. Domain 5 of CHD's current Detailed Content Outline asks candidates to describe the steps that should be taken to ensure that activation readiness (staff relocation) incorporates new processes and workflow linked to EBD strategies and interventions, and to update and finalize the research plan for post-occupancy evaluation and proposed design research.


Why Activation Is Part of the EBD Process

Designing decentralized supply servers, same-location headwalls, or family zones creates the opportunity for better outcomes. Staff who carry old habits into the new building—walking to a central supply room out of habit, or asking families to leave at night—can erase the benefit. If the post-occupancy evaluation later shows no change, the team will not know whether the hypothesis was wrong or the workflow was never adopted. Activation readiness protects both outcomes and research validity.


The Outline's Activation Readiness Steps

Outline StepWhat It InvolvesEBD Purpose
Develop an activation timelineSequence training, equipment moves, system go-lives, drills, and patient movesPrevents last-minute shortcuts that bypass new workflows
Review research hypothesesRemind leaders and staff what each EBD feature is expected to changeKeeps the intent visible and prepares staff for measurement
Review annotated diagramsWalk staff through plans that label each intervention and its purposeExplains why spaces are arranged as they are
Train on future-state workflowsAssist the activation team with training covering people, process, and technology, as well as physical environment changesStaff learn new routines before patients arrive
Support staff recruitment and occupant orientation and trainingInclude new hires and all occupant groups in building orientationNew and existing staff start with the same expectations
Simulate tabletop exercises and full-size mock-up environmentsTalk through scenarios and practice in full-size settingsFinds gaps in plans and spaces safely
Conduct pre-occupancy day-in-the-life exercisesRun realistic shifts in the finished building with mock patientsReveals latent hazards and workflow conflicts before opening

Tabletop Exercises vs. Day-in-the-Life Exercises

FeatureTabletop ExerciseDay-in-the-Life Exercise
SettingConference room, discussion-basedThe completed building, hands-on
MethodWalk through a scenario step by step (for example, a patient deterioration or a power failure)Staff perform realistic routines and emergencies with mock patients and real equipment
Best forClarifying roles, communication, and policiesTesting distances, sightlines, equipment fit, supplies, and technology in real space
Typical findingsUnclear responsibilities, missing proceduresCrash carts that block doors, glare on screens, missing outlets, supplies stocked in the wrong place

Transition Disruption and Move Strategies

New facilities often experience a temporary dip in efficiency and satisfaction after move-in while staff learn new locations, equipment, and routines. Honeymoon effects can also inflate early satisfaction. Both are reasons CHD materials advise waiting at least six months after occupancy before collecting post-occupancy data (Section 12.1).

Practical ways to shorten the disruption include super-users or unit champions who support peers on each shift, wayfinding and orientation walks before opening, and rapid issue logs that route early problems to facilities, IT, and supply chain teams.

Move StrategyDescriptionAdvantagesRisks
Single-day ("big bang") moveAll departments and patients move on one planned dayShorter period of running two facilities; one cutoverIntense move-day workload; all systems carry full load at once
Phased occupancyDepartments move in stages over weeks or monthsLessons from early phases improve later ones; systems loaded graduallyCost of running two facilities; split staff; more construction-to-occupancy interfaces

Updating and Finalizing the POE Research Plan

The outline's final Construction and Occupancy item is to update and finalize the research plan for post-occupancy evaluation and proposed design research. By this point the team knows what was actually built, what changed during value engineering, and what baseline data exist. Finalizing the plan means:

Plan ElementUpdate Before Occupancy
HypothesesRemove or revise hypotheses whose features were cut or changed; confirm those that remain
Baseline dataConfirm baseline measures are complete and stored with their definitions
Methods and instrumentsUse the same instruments, definitions, and sampling as the baseline
TimingSchedule data collection after stabilization (at least six months) and across seasons where needed
Team and approvalsConfirm researchers, owner approval, and Institutional Review Board determination where required
Budget and resourcesConfirm funding for data collection, analysis, and dissemination
Commissioning verified ──► Activation timeline ──► Training & orientation
        │                                               │
        ▼                                               ▼
Review hypotheses & annotated diagrams ──► Tabletop, mock-up & day-in-the-life exercises
        │
        ▼
Finalize POE research plan ──► Occupancy ──► Stabilization (6+ months) ──► POE

Worked Scenario: Activating a Unit with Decentralized Supplies

A hospital is moving a 36-bed unit into a new wing designed with decentralized supply servers and hybrid charting alcoves. Eight weeks before opening, the activation team builds a timeline that includes: a hypothesis review session explaining that walking distance and time in patient rooms will be measured; walk-throughs using annotated diagrams; supply-chain training on restocking servers from the corridor; and a tabletop exercise on responding to a deteriorating patient when nurses are dispersed.

Two weeks before opening, a day-in-the-life exercise reveals that crash carts block the sliding bathroom doors in several rooms and that supply servers were stocked by department rather than by room need. Both are corrected before patients arrive. The research plan is then finalized: the walking-distance hypothesis stays, a hypothesis about bathroom sightlines is revised after a door change, and data collection is scheduled to begin after six months of occupancy.


Exam Watch: High-Yield Traps & Pitfalls

[!WARNING] Trap 1: Activation is just moving furniture. The outline frames activation readiness around new processes and workflows linked to EBD strategies.

[!WARNING] Trap 2: Training only on technology. Future-state training covers people, process, technology, and physical environment changes.

[!WARNING] Trap 3: Finalizing the POE plan after opening. The research plan is updated and finalized before occupancy, once the team knows what was built.

Loading diagram...
Activation Readiness Steps in the Exam Content Outline
Test Your Knowledge

Two months before opening, a hospital's activation team plans equipment moves and IT go-live but has not scheduled any review of the EBD hypotheses or the annotated diagrams with staff. According to CHD's exam content outline, why is this a gap?

A
B
C
D
Test Your Knowledge

Which activity best matches a pre-occupancy day-in-the-life exercise?

A
B
C
D
Test Your Knowledge

During construction, value engineering removed the tunable lighting system from a new unit. Before occupancy, what should the team do with the post-occupancy research plan, according to the exam content outline?

A
B
C
D