Fee Allocation Across Project Phases

Key Takeaways

  • Phase percentages are negotiated and project-specific; AIA does not prescribe 15/20/40/5/20.

  • Subtract included consultant and expense obligations before allocating internal production effort.

  • Distinguish net fee before reserve from the production allowance after reserve.

  • Front-loaded delivery can require more early effort while later contracted review duties remain.

Last updated: October 2026

Fee Allocation Across Project Phases

Quick Answer: In traditional Design-Bid-Build practice, an illustrative work plan distributes architectural fees across the five standard AIA phases as 15% Schematic Design (SD), 20% Design Development (DD), 40% Construction Documents (CD), 5% Bidding & Negotiation, and 20% Construction Administration (CA). Before distributing fees to phases, the project manager must calculate the Internal Production Allowance by deducting engineering consultant pass-through fees (illustratively 20%–35%) and carving out an internal firm contingency reserve (5%–10%). Discrepancies between top-down client fee caps and bottom-up Work Breakdown Structure (WBS) labor estimates must be reconciled prior to contract signing by adjusting scope, reallocating staff seniority, or negotiating additional services.


The Traditional Five-Phase Architectural Fee Structure

Under standard Owner-Architect agreements, such as AIA Document B101-2017, architectural basic services are structured across five sequential phases. AIA does not prescribe phase percentages or universal firm fee benchmarks. The distribution below is an illustrative planning assumption; develop the actual allocation from scope, staffing, delivery method, review needs, and contracted services.

Total Architectural Fee (100%)
├── Schematic Design (SD):          15%
├── Design Development (DD):        20%
├── Construction Documents (CD):     40%
├── Procurement / Bidding:           5%
└── Construction Administration (CA): 20%

1. Schematic Design (SD) — 15% of Basic Services Fee

  • Scope & Objectives: The design team explores conceptual spatial configurations, massing options, site circulation, code classifications, and relationship diagrams based on the Owner's program. The architect prepares preliminary single-line drawings, outline narratives, and an initial Estimate of the Cost of the Work under AIA B101 § 3.2.6.
  • Labor Profile: Highly weighted toward senior design staff (Principals and Senior Project Designers) exploring broad aesthetic and conceptual directions. Total drafting hours are moderate, but billing rates are high.
  • Management Imperative: Obtaining documented owner approval of the Schematic Design documents and updated cost estimate is mandatory before initiating DD. Unresolved conceptual changes permitted to drift into later phases cause catastrophic rework.

2. Design Development (DD) — 20% of Basic Services Fee

  • Scope & Objectives: Refines and fixes the architectural concept. Building systems are finalized, including primary structural framing layouts, mechanical/electrical/plumbing (MEP) distribution strategies, exterior envelope wall assemblies, major material selections, and outline specifications. The architect submits an updated cost estimate under AIA B101 § 3.3.2.
  • Labor Profile: Balanced between senior technical leaders (Project Architect) and production staff (Job Captain, staff designers), with increasing involvement from consulting structural, civil, and MEP engineers.
  • Management Imperative: DD is the "decision freezing" phase. All primary technical systems and dimensions must be established. Overallocating effort here is preferable to underallocating; uncoordinated engineering systems discovered in Construction Documents require expensive redrafting.

3. Construction Documents (CD) — 40% of Basic Services Fee

  • Scope & Objectives: Represents the single largest expenditure of architectural labor. The team generates fully detailed, dimensioned, and annotated construction drawings and comprehensive MasterFormat specifications (the Project Manual) necessary for regulatory permitting, bidding, and construction.
  • Labor Profile: Production-intensive. Dominated by Job Captains, BIM modelers, and technical specification writers, supervised by the Project Architect performing continuous interdisciplinary quality cross-checks.
  • Management Imperative: The PM must guard against "over-detailing" or expanding scope beyond the contract narrative. Detailed deliverables checklists and strict adherence to the Work Breakdown Structure (WBS) prevent fee burn during this phase.

4. Procurement / Bidding & Negotiation — 5% of Basic Services Fee

  • Scope & Objectives: The architect assists the owner in distributing bidding documents to prospective contractors, conducting pre-bid conferences, answering bidder Requests for Information (RFIs), issuing Addenda, and evaluating bid proposals or negotiating contract terms.
  • Labor Profile: Brief calendar window (illustratively 3 to 6 weeks) requiring targeted involvement by the Project Architect and Project Manager.
  • Management Imperative: Maintaining an accurate Addenda log is vital. Because this phase carries only 5% of the fee, poorly coordinated CD sets that generate hundreds of bidder RFIs can exhaust the bidding budget in days.

5. Construction Administration (CA) — 20% of Basic Services Fee

  • Scope & Objectives: Under AIA B101 § 3.6, the architect acts as the owner's representative to observe construction progress, evaluate quality, review contractor submittals and shop drawings, process RFIs, review and certify Applications for Payment (AIA G702/G703), prepare Change Orders (AIA G701), conduct punch list inspections, and issue the Certificate of Substantial Completion (AIA G704).
  • Labor Profile: Sustained, long-duration phase spanning months or years. Involves the Project Architect and field representatives conducting regular site visits and managing submittal logs.
  • Management Imperative: CA fees must be metered carefully across the anticipated construction duration. If construction is delayed through no fault of the architect, basic CA fees will be depleted, requiring the architect to invoke Additional Services under AIA B101 § 4.2 for extended contract administration.

Fee Allocation Adjustments by Project Delivery Method

While the 15/20/40/5/20 breakdown is an illustrative Design-Bid-Build scenario, alternative delivery methods shift the timing and intensity of architectural effort, requiring significant reallocation of the fee curve:

Project Delivery MethodSD (%)DD (%)CD (%)Bidding (%)CA (%)Primary Operational Rationale
Design-Bid-Build (DBB)15%20%40%5%20%Sequential baseline; maximum effort concentrated in fully completed CD set prior to competitive bidding.
Construction Manager as Constructor (CMAR / CMc)18%25%32%5%20%Early CM involvement shifts detailing forward; DD expanded to 25% to support early Guaranteed Maximum Price (GMP) pricing and constructability reviews.
Design-Build (DB)20%25%30%5%20%Architect is teamed with or employed by builder; early trade subcontractor coordination front-loads design decisions into SD and DD.
Fast-Track (Multiple Bid Packages)15%20%35%10%20%Multiple procurement packages (e.g., foundation, structural steel, core/shell, interiors) expand bidding and procurement coordination overhead.
Integrated Project Delivery (IPD)25%30%20%5%20%Follows the MacLeamy Curve; massive front-loading of multi-party collaborative design in early phases dramatically reduces CD drafting and CA field RFIs.

The MacLeamy Curve and Front-Loading Fees

In progressive delivery methods such as Integrated Project Delivery (IPD) or collaborative CMAR, the fee distribution mirrors the MacLeamy Curve. This principle illustrates that the ability to impact cost and functional performance is highest during early design (SD and DD), while the financial cost of making design changes rises exponentially as the project advances into Construction Documents and Construction. Shifting fee and personnel into earlier phases reduces costly change orders, RFIs, and schedule extensions during construction.


Deriving the Internal Production Allowance & Internal Contingency Reserve

Net professional-service fee is measured before the internal reserve. In the worked example, it is $375,000; allocating a $25,000 reserve leaves a $350,000 production allowance. The reserve does not reduce earned net revenue. Included expense obligations must be removed consistently; do not subtract expenses billed separately from a professional-service-only fee.

An architectural project manager must never allocate the full gross contract fee directly to architectural production. Doing so ignores mandatory consultant pass-through costs and exposes the firm to severe financial vulnerability when unexpected complications arise.

Deducting Consultant Pass-Through Fees

For this planning scenario, assume architect-retained consulting engineers (structural, civil, mechanical, electrical, plumbing, and fire protection) account for 20% to 35% of the gross architectural contract fee. These funds do not belong to the architectural firm; they are contractual pass-through obligations governed by agreements such as AIA Document C401-2017.

Establishing the Internal Firm Project Contingency Reserve

For this scenario, the firm chooses an internal project contingency of 5% to 10% from the architectural fee prior to distributing funds across phase labor budgets. This internal contingency serves critical operational purposes:

  • Absorbs Minor Scope Drift: Covers minor client design adjustments that do not rise to the contractual threshold of formal Additional Services.
  • Buffers Against Internal Rework: Mitigates the financial impact of technical coordination hurdles, detailing revisions, or software/BIM modeling snags.
  • Guards QA/QC Peer Reviews: Ensures funds remain available at the conclusion of CD for independent senior quality reviews without depleting phase production hours.

Step-by-Step Mathematical Calculation of Internal Production Allowance

The Internal Production Allowance represents the true revenue available for direct architectural labor and overhead/profit:

Gross Contract Fee−Consultant Fees−Reimbursables−Internal Project Contingency=Internal Production Allowance\text{Gross Contract Fee} - \text{Consultant Fees} - \text{Reimbursables} - \text{Internal Project Contingency} = \text{Internal Production Allowance} Phase Labor Budget=Internal Production Allowance×Phase Allocation Percentage\text{Phase Labor Budget} = \text{Internal Production Allowance} \times \text{Phase Allocation Percentage} Planned Phase Labor Hours=Phase Labor BudgetBlended Hourly Billing Rate\text{Planned Phase Labor Hours} = \frac{\text{Phase Labor Budget}}{\text{Blended Hourly Billing Rate}}

Top-Down vs. Bottom-Up Fee Budgeting Reconciliation

A central duty of the Project Manager during project kickoff is reconciling two fundamentally opposing fee estimation methodologies:

1. Top-Down Fee Budgeting

Top-down budgeting is market-driven or client-driven. It begins with the total fee stipulated in the client's Request for Proposals (RFP), calculated as a fixed lump sum or as a percentage of the estimated Construction Cost (e.g., 7.0% of a $10,000,000 construction budget = $700,000 gross fee). The PM divides this fixed top-down number across phases and attempts to fit staff into the resulting financial boxes.

2. Bottom-Up Fee Budgeting

Bottom-up budgeting is production-driven. Working from the Work Breakdown Structure (WBS), the PM and Project Architect itemize every required drawing sheet, specification section, coordination meeting, and administrative task. They estimate the precise labor hours required by each staff role (e.g., 40 hours of Job Captain drafting, 16 hours of PA detailing) and multiply these hours by the firm's standard billing rates or Direct Personnel Expense (DPE) multipliers:

Bottom-Up Fee=∑(Planned Hours per Role×Hourly Billing Rate)\text{Bottom-Up Fee} = \sum (\text{Planned Hours per Role} \times \text{Hourly Billing Rate})

The Reconciliation Process: Resolving Gaps

In professional practice, the bottom-up estimate can exceed the top-down fee allowance. If a firm signs a contract based on an unadjusted top-down cap without reconciling it against bottom-up reality, the project carries an unresolved risk of overrunning its fee. The PM must execute one or more of the following reconciliation strategies:

  1. Adjust Staff Seniority Mix: Reallocate production tasks from senior architects ($160–$200/hr) to intermediate or junior designers ($90–$110/hr), preserving appropriate senior design, coordination, oversight, and review involvement to reduce the blended hourly rate.
  2. Negotiate Scope and Deliverables: Review the project scope narrative with the client. Remove non-essential deliverables (such as physical study models, photorealistic marketing renderings, or multiple distinct schematic design options) and categorize them as Additional Services.
  3. Streamline Drawing Production: Leverage standard firm detail libraries, modular components, and automated BIM scheduling tools to reduce budgeted production hours per sheet.
  4. Negotiate an Adjusted Fee Cap: Present the granular bottom-up WBS to the client during contract negotiation to demonstrate why the proposed top-down fee is inadequate to support the requested scope of services.

Comprehensive Worked Case Study: Full Project Fee Breakdown

Consider an architectural firm negotiating a stipulated lump-sum agreement of $500,000 for a new community library under a traditional Design-Bid-Build delivery model. The firm plans a 25% consultant allowance, reserves an internal project contingency of 5%, and utilizes a blended team billing rate of $125 per hour.

Initial Fee Deduction Analysis

Financial ComponentCalculationDollar AmountStatus
Gross Contract FeeTotal contract value$500,000Contractual Base
Consultant Fees (25%)$500,000 × 0.25 (Structural, MEP, Civil)-$125,000Pass-Through Liability
Internal Contingency (5%)$500,000 × 0.05-$25,000Reserved Risk Pool
Internal Production Allowance$500,000 - $125,000 - $25,000$350,000Available Direct Architectural Labor

Phase-by-Phase Labor Budget & Staff Hour Distribution Table

Applying the traditional Design-Bid-Build fee percentages to the $350,000 Internal Production Allowance yields the following operational labor allocation across the project lifecycle:

PhaseScenario %Phase Production AllowancePlanned Hours (@ $125/hr)Phase DurationAverage Weekly Hours
Schematic Design (SD)15%$52,500420 hrs8 weeks52.5 hrs/wk
Design Development (DD)20%$70,000560 hrs10 weeks56.0 hrs/wk
Construction Documents (CD)40%$140,0001,120 hrs16 weeks70.0 hrs/wk
Bidding & Negotiation5%$17,500140 hrs4 weeks35.0 hrs/wk
Construction Administration (CA)20%$70,000560 hrs52 weeks10.8 hrs/wk
Total Basic Services100%$350,0002,800 hrs90 weeks—

Reference: AIA B101 compensation blanks and phase percentages.

Test Your Knowledge

An architecture firm signs a standard AIA B101 agreement for a museum expansion with a gross stipulated fee of $600,000. Engineering consultant pass-through fees equal 25% of the gross fee. The firm establishes an internal risk contingency of 5% of the gross fee prior to phase distribution. Under the traditional Design-Bid-Build delivery model, if the firm's blended hourly billing rate for the production team is $120 per hour, how many total labor hours are budgeted for the Construction Documents (CD) phase? Assume the work plan allocates 40% of the available internal production fee to CDs.

A

1,120 hours

B

1,750 hours

C

1,400 hours

D

2,000 hours

Test Your Knowledge

An institutional client switches the delivery method of a high-tech science building from traditional Design-Bid-Build to Construction Manager at Risk (CMAR) with an early Guaranteed Maximum Price (GMP) submittal required at the end of Design Development. How should the architectural project manager adjust the phase fee allocation percentages to accommodate this delivery method?

A

Maintain the exact traditional 15-20-40-5-20 percentage split, but instruct consultants to work unpaid overtime during Design Development.

B

Reduce Schematic Design to 5% and allocate 50% of the total fee to Bidding & Negotiation to coordinate multiple trade contracts.

C

Reallocate the entire 20% Construction Administration fee into Design Development, eliminating CA services since the construction manager handles all field coordination.

D

Shift fee from Construction Documents into Design Development (e.g., expanding DD to 25% and reducing CD to 32%) to support early system detailing, constructability reviews, and GMP bid packaging.

Test Your Knowledge

During project work planning for a commercial project, the project manager completes a bottom-up labor budget based on a detailed Work Breakdown Structure (WBS), calculating that completing the contractual scope will require $240,000 valued at planned billing rates, including cost recovery and profit. However, the client's RFP establishes a firm top-down available internal production fee cap of $200,000. Which action represents the most professionally sound strategy for the project manager to reconcile this $40,000 deficit before contract execution?

A

Present the granular WBS task-hour breakdown to the client to negotiate an increased fee cap, or collaborate with the client to remove specific non-essential deliverables from Basic Services to align scope with the $200,000 budget.

B

Execute the agreement at $200,000 without changes, planning to cut back on independent internal QA/QC reviews and cross-consultant checks during Construction Documents.

C

Sign the contract and instruct the project team to secretly omit required building envelope wall sections from the permit submittal to save drafting hours.

D

Arbitrarily reduce the hourly billing rates entered in the firm's accounting software so the bottom-up calculation mathematically matches $200,000.

Sections you finish are checked off in the contents.