5.4 Yield, Relative Yield, and Batch Comparison
Key Takeaways
Yield Y = total batch mass / density (D); in ft³, divide by 27 to convert to yd³.
Relative yield Ry = Y / Vd, where Vd is the design volume; Ry = 1.00 means exactly as designed.
Relative yield above 1.00 means more concrete was produced than designed (overyield); below 1.00 means less (underyield, a shortfall).
Cement content = total mass of cement in the batch / yield, giving actual cement per cubic yard.
Because density is the divisor, a high density always produces a low yield, and vice versa.
Yield: How Much Concrete the Batch Made
Yield (Y) is the volume of concrete produced from a batch of known total mass. C138 computes it directly from density:
Y = (total batch mass) / D
The total batch mass is the sum of all ingredient masses actually weighed into the batch — cement, supplementary cementitious materials, all aggregates, water, and admixtures (in pounds). Dividing by density (lb/ft³) yields a volume in cubic feet. To express it in cubic yards, divide by 27 (since 1 yd³ = 27 ft³).
Worked yield example
A batch contains the following masses:
| Ingredient | Mass (lb) |
|---|---|
| Cement | 564 |
| Coarse aggregate | 1,800 |
| Fine aggregate | 1,240 |
| Water | 282 |
| Total batch mass | 3,886 |
Measured density D = 145.0 lb/ft³. Yield Y = 3,886 / 145.0 = 26.80 ft³ = 26.80 / 27 = 0.993 yd³.
Relative Yield: Did the Batch Deliver What Was Designed?
Relative yield (Ry) compares the actual yield to the design volume (Vd) the mix was proportioned to make:
Ry = Y / Vd
- Ry = 1.00 → the batch produced exactly the designed volume.
- Ry > 1.00 → overyield: more concrete than designed (you'll have extra; the mix is slightly 'light').
- Ry < 1.00 → underyield/shortfall: less concrete than designed — a paving or slab order could come up short.
Worked relative-yield example
Using the batch above, the mix was designed to make Vd = 27.00 ft³ (1.000 yd³). Ry = 26.80 / 27.00 = 0.993. Because 0.993 < 1.00, the batch underyielded by about 0.7% — it produced slightly less concrete than ordered. If the same batch had measured a density of only 143.0 lb/ft³, yield would be 3,886 / 143.0 = 27.18 ft³ and Ry = 27.18 / 27.00 = 1.007, an overyield. Higher density → lower yield → lower relative yield, and vice versa.
Cement Content From Yield
C138 also lets you back out the actual cement content (C) delivered per unit volume:
C = (total mass of cement in the batch) / Y
Using the example: 564 lb cement ÷ 0.993 yd³ = 568 lb/yd³. If a specification calls for 564 lb/yd³ (a six-bag mix), the slightly low yield means each cubic yard actually carries a hair more cement than designed — an underyield concentrates the cement. Conversely, overyield dilutes cement content below the target. This is why owners care about relative yield: it ties directly to whether the hardened concrete will meet its strength-driving cement factor.
Why These Numbers Matter on the Job
Yield and relative yield are the producer's quality-control link between the batch ticket and the truck:
- A consistent Ry near 1.00 confirms the plant's batch weights and the assumed aggregate specific gravities are accurate.
- A persistent underyield (Ry < 1.00) means trucks deliver less concrete than billed — costly and a contractual problem.
- A persistent overyield (Ry > 1.00) often signals higher-than-assumed air content or lighter materials, which can compromise strength.
Because all of this rests on the density number, sloppy C138 technique doesn't just mis-state density — it mis-states yield, relative yield, and cement content together.
Units and Conversions to Keep Straight
Yield problems trip candidates up on units more than on the formula. Keep these straight:
| Quantity | Inch-pound unit | Conversion |
|---|---|---|
| Density (D) | lb/ft³ | — |
| Batch mass | lb | — |
| Yield (raw) | ft³ | ÷ 27 → yd³ |
| Yield (reported) | yd³ | report to 0.01 yd³ |
| Relative yield | dimensionless | report to 0.01 |
| Cement content | lb/yd³ | report to 1 lb/yd³ |
A disciplined approach: compute yield in ft³ first (batch mass ÷ density), then divide by 27 only when you need cubic yards. Many wrong answers come from dividing by 27 too early or forgetting it entirely. Likewise, relative yield is unitless — both yield and design volume must be in the same unit (both ft³ or both yd³) before you divide, or the ratio is meaningless.
A Fully Worked Batch
Put it all together with one clean example. A batch of total mass 3,950 lb is designed to produce 27.0 ft³ (1.00 yd³) and contains 611 lb of cement. The measured density is 148.0 lb/ft³.
- Yield: 3,950 / 148.0 = 26.69 ft³ = 26.69 / 27 = 0.99 yd³.
- Relative yield: 26.69 / 27.0 = 0.988 → rounds to 0.99. Below 1.00, so a slight underyield.
- Cement content: 611 / 0.99 yd³ = 617 lb/yd³, slightly above the 611 lb/yd³ target because the underyield concentrates the cement.
Every one of these answers traces back to the single measured density of 148.0 lb/ft³ — which is exactly why the procedure sections (5.1–5.3) matter so much.
One more nuance: the total batch mass must include the water and admixtures actually added, not just the dry materials on the mix-design sheet. If a truck received extra tempering water at the site, that water is part of the batch mass for yield purposes. Using the design batch mass while testing a tempered batch mismatches the numerator and denominator and produces a misleading yield — so always pair the measured density with the as-delivered batch weights when one is computing yield in the field.
A batch has a total mass of 3,750 lb and the measured density is 150.0 lb/ft³. What is the yield in cubic feet?
27.0 ft³
562,500 ft³
0.93 ft³
25.0 ft³
A batch yields 26.5 ft³ of concrete and was designed to produce 27.0 ft³. What is the relative yield, and what does it indicate?
1.019 — the batch overyielded
0.500 — the batch is half the designed volume
0.981 — the batch underyielded, producing less than designed
1.000 — the batch produced exactly the designed volume
If the measured density of a batch comes out higher than it truly should be, what happens to the calculated yield?
The yield is unaffected because batch mass is fixed
The yield comes out too high
The yield comes out too low
The yield becomes negative
Sections you finish are checked off in the contents.