6.2 Overhead Absorption Rates: Per Unit, Per Labour Hour and Per Machine Hour
Key Takeaways
- Overhead absorption is the final stage of overhead accounting, whereby accumulated production cost centre overheads are charged into individual cost units (products, batches, or services).
- Organizations calculate predetermined overhead absorption rates (OARs) at the start of the financial period using budgeted overheads and budgeted activity levels, ensuring timely product pricing and consistent inventory valuation throughout the year.
- The universal formula for the predetermined overhead absorption rate is: Budgeted Production Overhead ÷ Budgeted Activity Level.
- The chosen absorption base must reflect the dominant operating characteristic of the production centre: machine hours for automated/mechanized bays, direct labour hours for manual/labour-intensive bays, and physical units for homogeneous single-product operations.
- PCTN uses three absorption bases, per unit, per labour hour and per machine hour; a per-unit rate is only fair when all units are identical.
6.2 Overhead Absorption Rates: Per Unit, Per Labour Hour and Per Machine Hour
Key Concept: Overhead absorption (or overhead recovery) is the mechanism by which indirect production overheads accumulated in production cost centres are charged into individual cost units. To avoid the delays and distortions of historical actual figures, management accountants establish Predetermined Overhead Absorption Rates (OARs) at the start of the budget period based on budgeted expenditure and budgeted activity.
Fundamentals and Rationale of Overhead Absorption
Once each production cost centre has a budgeted overhead total (Section 6.1 explains where it comes from; in PCTN tasks it is given to you), the final stage is Overhead Absorption. A standard textbook definition of overhead absorption is:
"The charging of overheads to cost units by means of rates calculated in relation to suitable bases."
Why Absorption Costing is Essential
- Financial Reporting Compliance (IAS 2 / FRS 102): Under UK and International accounting standards, the valuation of inventory (closing work-in-progress and finished goods) on the Statement of Financial Position must include not only prime costs (direct materials and direct labour) but also a systematic allocation of fixed and variable production overheads incurred in converting materials into finished goods.
- Determining Comprehensive Cost of Production: To establish whether a product line is profitable, management must understand its total cost. Ignoring indirect overheads risks pricing goods below full cost, leading to unintended operational losses.
- Guiding Pricing Decisions: In industries using cost-plus contracts (such as bespoke engineering, construction, and government defence procurement), commercial selling prices are established by adding a target profit mark-up to full absorption cost.
Why Use Predetermined Rates Instead of Actual Rates?
A foundational question in cost accounting is: Why do businesses calculate predetermined overhead absorption rates at the beginning of the year using estimates, rather than calculating actual rates at the end of the year using historical figures?
Waiting until the end of the financial year to establish actual overhead rates creates severe commercial and operational problems:
- Lack of Timeliness for Day-to-Day Operations: A business cannot wait until the financial year ends on 31 December to quote a selling price to a customer in February, or to invoice a completed bespoke fabrication in May. Managers need immediate cost figures every single day.
- Erratic Seasonal Fluctuations in Expenditure: Actual overhead expenditures do not occur smoothly across the year. Factory heating and lighting bills are substantially higher in January than in July; machinery maintenance overhauls often take place during the annual August factory shutdown; quarterly rent and annual insurance premiums fall due at irregular intervals. If actual monthly overheads were absorbed into monthly output, identical products manufactured in January would carry significantly higher unit overhead costs than those made in July.
- Distortions Caused by Monthly Volume Fluctuations: Fixed overhead costs (such as factory rent, rates, and depreciation) remain constant regardless of short-term output. If output drops in December due to Christmas holidays, dividing fixed overheads by fewer units would cause the calculated actual unit overhead rate to skyrocket, paradoxically making products seem most expensive to produce when factory activity is at its lowest.
- Providing a Fixed Cost Benchmark: Predetermined rates establish standard targets against which actual performance can be benchmarked, enabling variance analysis and managerial cost control.
The Predetermined Overhead Absorption Rate Formula
The universal mathematical formula for calculating a Predetermined Overhead Absorption Rate (OAR) is:
Where:
- Budgeted Production Overhead: The projected indirect manufacturing expenses for the department for the upcoming budget period (derived from Stage 1 and Stage 2 budget schedules).
- Budgeted Activity Level: The anticipated volume of activity (expressed in labour hours, machine hours, or units) planned for that department during the same period.
Selecting the Appropriate Absorption Base
The choice of absorption base is critical. The base should reflect the primary operational driver that causes overheads to be incurred in that specific production department.
1. Direct Labour Hour Rate
- Best Environment: Labour-intensive production cost centres where skilled or semi-skilled operatives manually manufacture, assemble, or finish products using hand tools.
- Operational Justification: Overheads such as factory supervision, canteen, lighting, and general factory operating costs correlate directly with the human labour hours worked.
2. Machine Hour Rate
- Best Environment: Capital-intensive, automated, or mechanized production cost centres (such as CNC machining bays, automated bottling plants, or chemical process lines).
- Operational Justification: The predominant overheads in automated bays—machinery depreciation, electric power, machinery insurance, cutting tooling, and technical maintenance—are driven by running the machines, not by manual labour.
3. Unit of Output Rate
- Best Environment: Continuous manufacturing facilities producing a single, homogeneous, standardized product (e.g. brickworks, cement plants, sugar refineries).
- Operational Justification: When every unit produced is identical and consumes exactly the same resources and processing time, overheads can be divided equally across units. It is totally unsuitable for factories making diverse or bespoke products.
4. Percentage of Direct Labour Cost
- Limitations: Distorts product costs if workers are paid different hourly rates for reasons unrelated to overhead usage. For example, a senior master craftsman earning £25/hour using a basic manual bench would attract 2.5 times more overhead than an apprentice earning £10/hour, even though both consume identical factory overhead resources.
5. Percentage of Direct Material Cost
- Limitations: Highly problematic because commodity material prices fluctuate independently of factory overheads. A product made from expensive titanium would absorb ten times more factory rent and lighting overhead than an identical product made from carbon steel, which is completely irrational.
6. Percentage of Prime Cost
- Limitations: Combines the distortions of both material cost and labour cost methods.
Comparison of Overhead Absorption Bases
The following table summarizes the primary absorption bases:
| Absorption Base | Formula | Best Operating Environment | Core Advantage | Critical Limitation |
|---|---|---|---|---|
| Direct Labour Hours | Budgeted overhead ÷ budgeted labour hours | Manual, labour-intensive assembly and craft bays | Reflects time spent; unaffected by wage rate variations | Inappropriate for automated machinery bays |
| Machine Hours | Budgeted overhead ÷ budgeted machine hours | Automated, robotic, capital-intensive machine bays | Directly tracks machine running time, power, and wear | Requires precise logging of machine meter hours |
| Units of Output | Budgeted overhead ÷ budgeted units | Single-product, continuous homogeneous production | Extremely simple to calculate and apply | Distorts costs if multiple diverse products are made |
| % of Direct Labour Cost | Budgeted overhead ÷ budgeted labour cost × 100 | Standardized wage environments without pay differentials | Uses existing monetary payroll records | Distorts overheads if wage rates vary by seniority |
| % of Direct Material Cost | Budgeted overhead ÷ budgeted material cost × 100 | Material handling and purchasing cost centres only | Readily accessible from purchase invoices | Unfairly penalizes products using expensive raw materials |
PCTN-Style Task: Comparing the Three Bases
PCTN names three absorption bases: per unit, per labour hour and per machine hour. The percentage-of-cost bases above appear in some textbooks, but the PCTN specification does not list them. A typical task gives you one set of budgeted figures and asks for all three rates.
Dales Kitchenware Ltd makes two products, a pan (A) and a casserole dish (B), in one production department. Its budget shows:
| Budgeted figure | Product A | Product B | Total |
|---|---|---|---|
| Output (units) | 8,000 | 4,000 | 12,000 |
| Labour hours (0.5 per A, 1.0 per B) | 4,000 | 4,000 | 8,000 |
| Machine hours (0.3 per A, 0.6 per B) | 2,400 | 2,400 | 4,800 |
| Production overheads | £96,000 |
Absorption rates:
- Per unit: £96,000 ÷ 12,000 units = £8.00 per unit
- Per labour hour: £96,000 ÷ 8,000 hours = £12.00 per labour hour
- Per machine hour: £96,000 ÷ 4,800 hours = £20.00 per machine hour
Overhead absorbed per unit of each product:
| Basis | Product A | Product B |
|---|---|---|
| Per unit | £8.00 | £8.00 |
| Per labour hour | 0.5 × £12.00 = £6.00 | 1.0 × £12.00 = £12.00 |
| Per machine hour | 0.3 × £20.00 = £6.00 | 0.6 × £20.00 = £12.00 |
Every basis absorbs the full £96,000 at budgeted activity. For example, on the labour hour basis, 8,000 × £6.00 plus 4,000 × £12.00 comes to £96,000. But the per-unit basis charges both products the same £8.00, even though B takes twice as long to make and uses twice the machine time. A per-unit rate is only fair when all units are identical. When products differ, a time-based rate charges each product for the resources it actually uses.
If Product B uses £14.00 of direct materials and 1 labour hour at £15.00 per hour, its unit cost on the labour hour basis is £14.00 + £15.00 + £12.00 = £41.00.
Blanket (Plant-Wide) Rates versus Departmental Rates
- Blanket (Plant-Wide) Rate: A single overhead absorption rate calculated for the entire factory (Total Factory Budgeted Overhead ÷ Total Factory Budgeted Activity). While computationally fast, blanket rates are only accurate if all products spend roughly identical time in all departments, or if the departments have similar cost structures. In practice, blanket rates cause massive cost cross-subsidization.
- Departmental Absorption Rates: Separate, tailored OARs calculated for each individual production department (e.g. machine hour rate for Machining, labour hour rate for Assembly). This ensures products that spend 10 hours in Machining and 1 hour in Assembly absorb overheads reflecting the actual facilities consumed.
Comprehensive Worked Example: Calculating OARs and Absorbing Overheads
To see how predetermined rates work in practice, examine Ribble Valley Manufacturing Ltd, an engineering firm in Preston with two production cost centres: Machining (capital-intensive CNC milling) and Assembly (labour-intensive manual assembly).
1. Annual Departmental Budgets
For the upcoming financial year, the management accountant prepares the following departmental budgets:
| Budgeted Parameter | Machining Department | Assembly Department |
|---|---|---|
| Budgeted Production Overhead | £180,000 | £120,000 |
| Budgeted Machine Hours | 20,000 machine hours | 2,000 machine hours |
| Budgeted Direct Labour Hours | 5,000 labour hours | 15,000 labour hours |
2. Establishing Predetermined OARs
- Machining Department: Because Machining is automated and capital-intensive, machine hours represent the primary cost driver.
- Assembly Department: Because Assembly is manual and labour-intensive, direct labour hours represent the primary cost driver.
3. Absorbing Overheads into a Specific Cost Unit: Job 604
The company receives an order for Job 604, a bespoke specialist conveyor drive unit. The job cost sheet records the following direct expenditures and operating times:
- Direct Materials: 40 kg specialized alloy steel @ £8.50/kg (£340.00) plus pre-machined internal gears (£160.00) = £500.00
- Direct Labour:
- Machining: 3.0 direct labour hours @ £18.00/hour = £54.00
- Assembly: 8.0 direct labour hours @ £15.00/hour = £120.00
- Total Direct Labour: £174.00
- Prime Cost: £500.00 + £174.00 = £674.00
Calculating Production Overhead Absorption:
- Machining Department Overhead Absorbed: Job 604 required 6.0 machine hours on the CNC milling centres.
- Assembly Department Overhead Absorbed: Job 604 required 8.0 direct labour hours in the assembly shop.
- Total Production Overhead Absorbed: £54.00 + £64.00 = £118.00
Full Product Cost Build-Up and Pricing:
| Cost Element | Calculation Details | Amount (£) |
|---|---|---|
| Direct Materials | Alloy steel and internal gears | £500.00 |
| Direct Labour | 3 hrs Machining (£54) + 8 hrs Assembly (£120) | £174.00 |
| Prime Cost | Direct Materials + Direct Labour | £674.00 |
| Absorbed Production Overhead (Machining) | 6.0 machine hours × £9.00/hr | £54.00 |
| Absorbed Production Overhead (Assembly) | 8.0 direct labour hours × £8.00/hr | £64.00 |
| Total Production Cost | Prime Cost + Absorbed Production Overheads | £792.00 |
| Administration & Selling Overhead | Absorbed at 15% of production cost (£792 × 15%) | £118.80 |
| Total Cost of Sales | Production Cost + Non-Production Overheads | £910.80 |
| Profit Mark-Up (25% on total cost) | £910.80 × 25% (or 20% margin on selling price) | £227.70 |
| Selling Price Quoted to Customer | Total Cost + Profit Mark-Up | £1,138.50 |
This calculation highlights the power of predetermined absorption rates: the company was able to quote an accurate, profitable commercial price of £1,138.50 immediately upon receiving the specification, fully covering all manufacturing and administrative overheads.
Common Exam Pitfalls and Practical Traps
- Trap 1: Using Actual Hours to Calculate the Predetermined OAR. A predetermined rate is set before the financial period starts. You must always divide Budgeted Overhead by Budgeted Activity. Actual figures are only used later during the period to calculate the overhead absorbed.
- Trap 2: Mismatching Departmental Bases. In an automated machine shop, never absorb overheads using labour hours. In a manual assembly shop, never absorb overheads using machine hours. Match the base to the department's operational nature.
- Trap 3: Forgetting to Multiply Actual Activity by the OAR. To calculate overhead absorbed into a job, multiply the actual hours consumed by that job by the predetermined hourly rate. Do not use the budgeted hours of the job.
An automated CNC machining bay has budgeted production overheads of £210,000 for the upcoming financial year. It expects to operate 28,000 machine hours and utilize 7,000 direct labour hours. What is the predetermined overhead absorption rate?
Which overhead absorption base is most technically appropriate for a manual finishing and inspection department where skilled workers complete all tasks by hand using bench tools?
What is the primary commercial reason why manufacturing enterprises use predetermined overhead absorption rates rather than waiting to calculate actual overhead rates at year-end?