2.4 Job-Site Indirects & Home Office Overhead Allocation

Key Takeaways

  • Job-site general conditions (field indirects) support a specific project site, whereas home office overhead (G&A) sustains the multi-project corporate enterprise.
  • Traditional overhead allocation bases include direct labor dollars, direct labor hours, and total direct costs, each carrying distinct cost-distortion risks.
  • Allocating corporate overhead strictly using direct labor dollars heavily overburdens labor-intensive work packages while under-allocating equipment- and subcontract-intensive scope.
  • The Eichleay formula is the standard legal and cost engineering method for quantifying unabsorbed home office overhead resulting from compensable owner-caused project suspensions.
  • Eichleay claims require demonstrating compensable owner delay, government-imposed suspension/standby, and the contractor's inability to take on replacement work.
Last updated: September 2026

Job-Site Indirects & Home Office Overhead Allocation

A critical competency tested on the AACE CCT examination is the rigorous distinction between direct costs, job-site general conditions (field indirects), and home office overhead (General & Administrative / G&A). Misclassifying field indirects as home office overhead—or arbitrarily allocating corporate overhead across projects—distorts project profitability, compromises competitive bid pricing, and undermines contractual delay claims. Cost engineers must understand how field indirects are budgeted, how corporate overhead is allocated across projects, and how the Eichleay Formula quantifies unabsorbed overhead during owner-caused suspensions.


1. The Three-Tier Cost Architecture

Total Cost Management (TCM) organizes capital project costs into three distinct hierarchical tiers:

+-------------------------------------------------------------------------+
|                      THE THREE-TIER COST HIERARCHY                      |
+-------------------------------------------------------------------------+
| TIER 1: DIRECT COSTS                                                    |
| - Physical components permanently incorporated into the project         |
| - Directly traceable to specific WBS terminal work packages             |
| - Examples: Craft labor, structural rebar, pipe spools, excavators      |
+-------------------------------------------------------------------------+
| TIER 2: JOB-SITE GENERAL CONDITIONS (FIELD INDIRECTS)                   |
| - Site-specific support costs dedicated 100% to ONE project             |
| - Cannot be economically traced to an individual permanent work package |
| - Examples: Site superintendent, field trailers, temporary power        |
+-------------------------------------------------------------------------+
| TIER 3: HOME OFFICE OVERHEAD (CORPORATE G&A)                            |
| - Corporate costs required to sustain the enterprise across all projects|
| - Incurred at central headquarters; requires mathematical allocation    |
| - Examples: Executive salaries, corporate legal, estimating, IT systems |
+-------------------------------------------------------------------------+

Job-Site General Conditions (Field Indirects)

Field indirects are 100% dedicated to a specific project site. They represent the administrative, logistical, and safety infrastructure necessary to construct the works:

  • Site Management & Technical Supervision: Project managers, superintendents, field engineers, safety managers, QA/QC inspectors, schedulers, and timekeepers stationed on site.
  • Temporary Facilities: Mobilization and rental of office trailers, storage conex containers, temporary fences, security gates, and covered walkways.
  • Temporary Utilities: Site temporary electrical power (substations, generators, site lighting), water distribution, temporary construction heating, and telecommunications/internet.
  • Safety & Sanitation: Portable restrooms, hand-washing stations, first-aid trailers, personal protective equipment (PPE) supplies, and trash dumpsters.
  • Site Mobilization & Demobilization: Initial transport of equipment, setting up temporary yards, and final site cleanup and punch-list overhead.
  • Project-Specific Permits & Insurance: Local municipal building permits, Storm Water Pollution Prevention Plan (SWPPP) compliance, Builder's Risk insurance, and project payment & performance bonds.

Home Office Overhead (General & Administrative / G&A)

Home office overhead represents corporate expenditures incurred to support the overall business entity across multiple projects and corporate initiatives. These expenses continue regardless of whether a specific job is active:

  • Corporate executive salaries, board expenses, corporate legal retainers, and CPA auditing fees.
  • Central estimating and business development departments (bidding costs for jobs won and lost).
  • Corporate headquarters office rent, building maintenance, and central utilities.
  • Enterprise software licensing: corporate ERP systems, scheduling platforms, and estimating software.
  • Human resources, centralized payroll processing, and corporate risk management.

2. Overhead Allocation Methodologies & Distortions

Because corporate G&A cannot be directly traced to specific work packages, contractors must allocate G&A to projects using an allocation base. The choice of base directly influences bid competitiveness and job cost tracking.

Traditional Allocation Bases

  1. Direct Labor Dollars Basis: Overhead Rate (% of Labor $)=Total Corporate G&A BudgetTotal Projected Direct Labor Dollars\text{Overhead Rate (\% of Labor \$)} = \frac{\text{Total Corporate G\&A Budget}}{\text{Total Projected Direct Labor Dollars}}
  2. Direct Labor Hours Basis: Overhead Rate ($/Man-Hour)=Total Corporate G&A BudgetTotal Projected Direct Labor Hours\text{Overhead Rate (\$/Man-Hour)} = \frac{\text{Total Corporate G\&A Budget}}{\text{Total Projected Direct Labor Hours}}
  3. Total Direct Cost Basis: Overhead Rate (% of Direct $)=Total Corporate G&A BudgetTotal Projected Direct Cost (Labor + Material + Equip + Subs)\text{Overhead Rate (\% of Direct \$)} = \frac{\text{Total Corporate G\&A Budget}}{\text{Total Projected Direct Cost (Labor + Material + Equip + Subs)}}

The Distortion Risk: Labor vs. Total Cost Allocation

When a contractor allocates corporate G&A strictly on a direct labor dollar basis, labor-intensive projects carry a disproportionate burden of corporate overhead, while material-intensive or subcontract-heavy projects escape overhead allocation. This produces dangerous pricing distortions:

  • Over-Allocating Labor-Intensive Scope: Bids on labor-intensive projects become artificially inflated, causing the contractor to lose competitive tenders.
  • Under-Allocating Subcontract/Equipment Scope: Projects dominated by high-value equipment or subcontracts appear artificially profitable on paper, but fail to generate sufficient corporate overhead recovery, resulting in enterprise cash flow deficits.

Dual-Rate & Activity-Based Costing (ABC) Allocation

To resolve these distortions, sophisticated cost engineering organizations employ dual-rate allocation:

  • Apply one rate (e.g., 20% to 30%) to Direct Labor Dollars to cover labor-related administrative support (HR, payroll, safety).
  • Apply a separate, lower rate (e.g., 3% to 6%) to Materials and Subcontracts to cover procurement, expediting, contracts management, and accounts payable handling.

3. Comparative Allocation Example

A contracting company budgets $1,800,000 in annual corporate G&A overhead. For the upcoming fiscal year, the company projects two major project tenders:

  • Project Alpha (Industrial Piping - Labor-Intensive):
    • Direct Labor: $2,000,000
    • Direct Materials & Equipment: $1,000,000
    • Subcontracts: $500,000
    • Total Direct Cost: $3,500,000
  • Project Beta (Highway Paving - Material & Equipment-Intensive):
    • Direct Labor: $500,000
    • Direct Materials & Equipment: $4,500,000
    • Subcontracts: $500,000
    • Total Direct Cost: $5,500,000
  • Company-Wide Direct Totals: Direct Labor = $4,000,000 | Total Direct Costs = $18,000,000
+-------------------------------------------------------------------------+
|               OVERHEAD ALLOCATION COMPARISON: ALPHA VS. BETA            |
+-----------------------------------+-------------------------------------+
| Method 1: Direct Labor Dollar Base| Method 2: Total Direct Cost Base    |
| Rate = $1.8M / $4.0M = 45.0%      | Rate = $1.8M / $18.0M = 10.0%       |
+-----------------------------------+-------------------------------------+
| Project Alpha Overhead:           | Project Alpha Overhead:             |
| 45.0% * $2,000,000 = $900,000     | 10.0% * $3,500,000 = $350,000       |
| (Overhead is 25.7% of direct cost)| (Overhead is 10.0% of direct cost)  |
+-----------------------------------+-------------------------------------+
| Project Beta Overhead:            | Project Beta Overhead:              |
| 45.0% * $500,000 = $225,000       | 10.0% * $5,500,000 = $550,000       |
| (Overhead is 4.1% of direct cost) | (Overhead is 10.0% of direct cost)  |
+-----------------------------------+-------------------------------------+
| VARIANCE ANALYSIS:                                                      |
| Project Alpha carries $550,000 MORE overhead under the labor-dollar     |
| method, severely undermining bid competitiveness on piping. Project Beta|
| is under-allocated by $325,000 under the labor method, risking enterprise|
| under-recovery if Alpha is lost!                                        |
+-------------------------------------------------------------------------+

4. Unabsorbed Overhead & The Eichleay Formula

When a project suffers an owner-caused compensable delay or work suspension, the contractor's direct work on site stops or slows dramatically. As a result, project progress billings cease or decrease. However, the contractor's fixed home office overhead costs continue to accrue. Because the contractor cannot bill direct costs, it cannot recover the ongoing home office overhead that this project was budgeted to absorb. Furthermore, if the owner placed the contractor on standby, the contractor is legally and practically precluded from committing its project workforce or management to other replacement jobs.

This unrecovered expenditure is called unabsorbed home office overhead. The standard legal and cost engineering method recognized by United States courts and federal contracting boards (originating from Eichleay Corp., ASBCA No. 5183, 1960) is the Eichleay Formula.

The Three-Step Eichleay Calculation

Step 1: Project Allocable Overhead=(Total Contract Billings on Delayed JobTotal Company Billings for Actual Contract Period)×Total Corporate G&A for Period\text{Step 1: Project Allocable Overhead} = \left( \frac{\text{Total Contract Billings on Delayed Job}}{\text{Total Company Billings for Actual Contract Period}} \right) \times \text{Total Corporate G\&A for Period}

Step 2: Daily Allocable Overhead=Project Allocable Overhead (from Step 1)Actual Days of Performance (including delay)\text{Step 2: Daily Allocable Overhead} = \frac{\text{Project Allocable Overhead (from Step 1)}}{\text{Actual Days of Performance (including delay)}}

Step 3: Unabsorbed Overhead Claim=Daily Allocable Overhead (from Step 2)×Days of Compensable Delay\text{Step 3: Unabsorbed Overhead Claim} = \text{Daily Allocable Overhead (from Step 2)} \times \text{Days of Compensable Delay}

Worked Example: Eichleay Formula Claim

A contractor contracts with a federal agency for a $4,800,000 pumping station. During execution, a major owner design defect halts all critical path work for 45 calendar days. The contract was originally scheduled for 355 days, resulting in an actual performance period of 400 calendar days.

  • Contract Billings on Delayed Job: $4,800,000
  • Total Company-Wide Billings during the 400-day period: $24,000,000
  • Total Home Office Overhead (G&A) incurred during the 400-day period: $1,600,000
  • Compensable Owner Delay: 45 calendar days

Step 1: Compute Project Allocable Overhead Allocable Overhead=($4,800,000$24,000,000)×$1,600,000=0.20×$1,600,000=$320,000\text{Allocable Overhead} = \left( \frac{\$4,800,000}{\$24,000,000} \right) \times \$1,600,000 = 0.20 \times \$1,600,000 = \mathbf{\$320,000}

Step 2: Compute Daily Allocable Overhead Daily Overhead Rate=$320,000400 actual performance days=$800.00 per calendar day\text{Daily Overhead Rate} = \frac{\$320,000}{400 \text{ actual performance days}} = \mathbf{\$800.00 \text{ per calendar day}}

Step 3: Compute Total Unabsorbed Overhead Claim Unabsorbed Overhead=$800.00 per day×45 delay days=$36,000.00\text{Unabsorbed Overhead} = \$800.00 \text{ per day} \times 45 \text{ delay days} = \mathbf{\$36,000.00}

Prerequisites for Eichleay Recovery

To sustain an Eichleay unabsorbed overhead claim, three legal and factual conditions must be satisfied:

  1. The delay was government/owner-caused and compensable (e.g., defective drawings, differing site conditions, stop-work order).
  2. The owner required the contractor to remain on standby, ready to resume work immediately once the suspension lifted.
  3. The contractor was unable to take on replacement work during the suspension period to absorb the ongoing home office overhead.

5. Exam Traps & Common Pitfalls

[!WARNING] Trap 1: Confusing Field Indirects (General Conditions) with Home Office G&A Field trailers, site superintendents, temporary utilities, and project safety officers are 100% project-specific indirects (General Conditions). They are NOT home office G&A. Home office G&A includes only enterprise-level expenses (corporate officers, central legal, estimating) that support multiple projects.

[!WARNING] Trap 2: Applying the Eichleay Formula to Contractor-Caused or Concurrent Delays The Eichleay formula cannot be applied if the delay was caused by contractor fault or if there was concurrent contractor delay on the critical path. Furthermore, if the contractor was not on standby and successfully transferred its resources to another revenue-generating project, Eichleay damages are barred.

[!WARNING] Trap 3: Using Scheduled Days Instead of Actual Days in Step 2 of Eichleay In Step 2 of the Eichleay formula, always divide by actual days of contract performance (the original duration plus the delay period), NOT the original baseline scheduled duration. Using original scheduled days improperly inflates the daily overhead rate.

Loading diagram...
Total Project Cost & Price Buildup Architecture
Test Your Knowledge

Which of the following cost items is properly classified as a job-site general conditions indirect cost rather than a corporate home office overhead (G&A) expense?

A
B
C
D
Test Your Knowledge

A general contracting firm incurs $1,200,000 in annual home office G&A overhead. Across its annual project portfolio, the firm expends $4,000,000 in direct craft labor and $15,000,000 in total direct project costs. A project estimator is pricing a concrete foundation package containing $300,000 in direct labor and $700,000 in direct materials/equipment (total direct cost = $1,000,000). How much home office overhead is allocated to this package under the Direct Labor Dollars basis versus the Total Direct Cost basis?

A
B
C
D
Test Your Knowledge

A federal contractor experienced a 50-day compensable suspension of work caused by a government design defect. The contractor incurred $1,800,000 in total home office overhead across the 600-day actual contract performance period. Total billings across the entire company during this 600-day period were $30,000,000, while total billings on the delayed contract were $6,000,000. Using the Eichleay formula, what is the contractor's allowable unabsorbed home office overhead claim?

A
B
C
D