Key Facts: AZ ROC R-4 Boilers Including Solar Exam

50 Questions

Official Question Count

PSI Content Outline

120 Minutes

Time Limit

PSI Content Outline

70%

Passing Score

Arizona Registrar of Contractors

$66

Exam Fee

PSI Services LLC

Open Book Computerized MCQ

Exam Format

PSI / AZ ROC Guidelines

100 Questions

Practice Question Bank

OpenExamPrep Practice Bank

The Arizona ROC R-4 Boilers Including Solar Examination consists of 50 multiple-choice questions administered in a 120-minute open-book PSI session, plus a separate 30-question / 75-minute R-4 Solar examination with a 70% passing threshold ($66 exam fee). This online practice bank provides 100 realistic practice questions with detailed code references and technical explanations adapted for exam preparation.

Sample AZ ROC R-4 Boilers Including Solar Practice Questions

Try these sample questions to test your AZ ROC R-4 Boilers Including Solar exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1Under International Residential Code (IRC) Chapter 20 and ASME Section IV standards, what is the maximum allowable operating pressure for a low-pressure residential hot water heating boiler?
A.15 psig
B.30 psig
C.160 psig
D.250 psig
Explanation: ASME Section IV and IRC M2001 classify low-pressure hot water heating boilers as units operating at pressures not exceeding 160 psig and temperatures not exceeding 250°F. While standard residential hydronic hot water boilers operate between 12 and 30 psig, 160 psig is the upper pressure boundary for the low-pressure boiler classification.
2According to IRC Chapter 20 and ASME Section IV, what is the maximum allowable working pressure (MAWP) for a low-pressure residential steam heating boiler?
A.15 psig
B.30 psig
C.50 psig
D.100 psig
Explanation: Low-pressure steam heating boilers governed by ASME Section IV and IRC M2001 are limited to a maximum allowable working pressure of 15 psig. Any steam boiler operating above 15 psig is classified as a high-pressure power boiler subject to ASME Section I.
3Which ASME code stamp symbol must appear on the rating plate of a low-pressure residential heating boiler and its safety relief valve?
A.'S' or 'A'
B.'H' or 'HV'
C.'U' or 'UM'
D.'PP' or 'E'
Explanation: ASME Section IV governs low-pressure heating boilers. Heating boilers are stamped with the 'H' symbol designator, and safety relief valves designed for Section IV boilers are stamped with the 'HV' symbol designator.
4A contractor calculates that a home has a total net heat loss of 80,000 BTU/h (80 MBH). Assuming a standard AHRI piping and pickup allowance factor of 1.15, what minimum Gross AHRI Output rating must the selected replacement boiler possess?
A.69.5 MBH
B.80.0 MBH
C.92.0 MBH
D.106.0 MBH
Explanation: Gross AHRI Output equals the Net AHRI Rating multiplied by the piping and pickup allowance factor. Here, 80 MBH × 1.15 = 92.0 MBH (92,000 BTU/h). This factor accounts for heat loss from distribution piping and initial heating pickup.
5Per IRC Section M2002.5, which safety device is required on all automatically fired hot water boilers to prevent burner operation if the boiler water drops below the safe operating level?
A.Thermal expansion valve
B.Low water cut-off (LWCO)
C.Automatic air scoop
D.Backflow preventer with atmospheric vent
Explanation: IRC M2002.5 requires an automatically fired hot water heating boiler to be equipped with a low water cut-off (LWCO) installed to automatically stop the burner firing circuit if the water level drops below the manufacturer's lowest permissible water level.
6What is the primary function of a high-limit aquastat on a residential hot water boiler?
A.Regulate incoming natural gas line pressure
B.De-energize the burner circuit when boiler water temperature reaches its safety limit
C.Control circulator pump speed based on outdoor air temperature
D.Maintain a constant water level in the boiler expansion tank
Explanation: The high-limit aquastat is a safety control designed to open its electrical contacts and shut off power to the burner if boiler water temperature exceeds the set high limit (typically 200°F–210°F), preventing water flashing into steam in a hot water boiler.
7High-efficiency condensing boilers produce acidic flue gas condensate with a typical pH between 3.0 and 5.0. According to the IPC and IRC, how must this condensate be treated prior to discharge into a residential drainage system?
A.It must be recirculated back into the boiler return loop.
B.It must pass through a condensate neutralizing kit containing limestone/calcium carbonate media.
C.It must be diluted with equal parts propylene glycol.
D.It must be discharged directly into the potable water supply line.
Explanation: IRC and IPC code provisions mandate that corrosive liquid wastes (pH below 6.0) be neutralized prior to entering metallic or public drainage systems. Passing flue condensate through a inline limestone (calcium carbonate) neutralizer raises the pH to safe levels.
8Per IRC M2001 and manufacturer specifications, what is the minimum required service clearance in front of a residential boiler burner and control access panel?
A.6 inches
B.12 inches
C.24 inches
D.48 inches
Explanation: IRC Section M2001 and standard mechanical equipment installation rules mandate a minimum clearance of 24 inches (or manufacturer listed clearance, whichever is greater) in front of controls, burners, and inspection panels for service access.
9Where should the normal operating water level (NOWL) be maintained in the water gauge glass of a low-pressure residential steam boiler?
A.At the very bottom nut of the gauge glass
B.Approximately in the middle third of the gauge glass
C.Completely filling the top of the gauge glass
D.Below the lower tri-cock valve level
Explanation: In low-pressure steam heating boilers, the normal operating water level (NOWL) should be visible approximately midway (middle third) up the water gauge glass. This ensures adequate water over the heat exchanger while leaving steam disengagement space above.
10What is the primary purpose of performing a periodic bottom blowdown on a residential steam boiler?
A.To increase system operating pressure to 30 psig
B.To flush out accumulated sediment, sludge, and test low-water cut-off operation
C.To purge non-condensable air from the upper radiator vents
D.To recharge the internal diaphragm expansion tank
Explanation: Opening the blowdown valve flushes out suspended solids, scale, and mud that settle at the bottom of the boiler shell, while simultaneously testing the low-water cut-off safety circuit.

About the AZ ROC R-4 Boilers Including Solar Exam

The Arizona ROC R-4 Boilers Including Solar (Residential) Examination is a computer-delivered, open-book trade examination administered by PSI Services LLC for the Arizona Registrar of Contractors. The R-4 license classification authorizes contractors to install, alter, repair, and service residential low-pressure steam and hot water boilers, hydronic space heating systems, radiant floor heating, solar thermal water heaters, solar collector arrays, expansion tanks, heat exchangers, circulating pumps, relief valves, gas supply lines, and associated safety controls.

Assessment

Two separately scored PSI examinations, both open book and both requiring 70%: the R-4 trade examination (50 questions / 120 minutes) and the R-4 Solar examination (30 questions / 75 minutes). Solar content outline: Collection Loops (5), Components (4), Installation (5), Maintenance (2), Mounting (4), Principles (5), Solar Systems Piping (5).

Time Limit

120 minutes

Passing Score

70%

Exam Fee

$66 (Arizona ROC / PSI Services LLC)

AZ ROC R-4 Boilers Including Solar Exam Content Outline

24%

Boilers

12 of 50 items on the official PSI content outline. Steam and hot water boiler types, trim, mountings and operation.

16%

Steam and Hot Water Piping

8 of 50 items on the official PSI content outline. Distribution piping, circulators, air control, expansion and supports.

16%

Gas Piping

8 of 50 items on the official PSI content outline. Fuel gas sizing, materials, joints, shutoffs and leak testing.

10%

Burners

5 of 50 items on the official PSI content outline. Burner types, combustion air, fuel trains and light-off sequence.

10%

Controls

5 of 50 items on the official PSI content outline. Operating and limit controls, low-water cutoffs and safety interlocks.

8%

Flues and Vents

4 of 50 items on the official PSI content outline. Venting categories, sizing, materials, terminations and draft.

8%

Sizing and Estimating

4 of 50 items on the official PSI content outline. Heat-loss calculation, boiler and radiation sizing, and material takeoffs.

8%

Testing and Inspection

4 of 50 items on the official PSI content outline. Hydrostatic and operational testing, relief valve checks and inspections.

How to Pass the AZ ROC R-4 Boilers Including Solar Exam

What You Need to Know

  • Passing score: 70%
  • Assessment: Two separately scored PSI examinations, both open book and both requiring 70%: the R-4 trade examination (50 questions / 120 minutes) and the R-4 Solar examination (30 questions / 75 minutes). Solar content outline: Collection Loops (5), Components (4), Installation (5), Maintenance (2), Mounting (4), Principles (5), Solar Systems Piping (5).
  • Time limit: 120 minutes
  • Exam fee: $66

Keys to Passing

  • Work through all 100 available questions
  • Review every answer and explanation
  • Track weak areas and revisit them
  • Use our AI tutor for tough concepts

AZ ROC R-4 Boilers Including Solar Study Tips from Top Performers

1Master hydronic system calculations, including flow rate (GPM = BTU/h / (500 x ΔT)), head loss, circulator pump curves, and expansion tank sizing formulas.
2Understand solar thermal loop configurations: drainback vs pressurized glycol closed-loop, double-wall heat exchanger code rules for potable water, and ASSE 1017 mixing valves.
3Review safety relief valve rules: Maximum 30 PSI for residential hot water boilers, 15 PSI for low-pressure steam, discharge pipe sizing, and termination within 6 inches of floor.
4Study combustion air calculations per IRC Chapter 24 / IFGC for confined vs unconfined spaces and Category I through IV venting rules.
5Review OSHA 1926 safety requirements including roof fall protection (lanyards, guardrails), ladder positioning (4:1 slope), and non-toxic propylene glycol requirements.

Frequently Asked Questions

How many questions are on the official Arizona ROC R-4 Boilers Including Solar exam?

The official PSI R-4 content outline lists 50 questions with 120 minutes allowed for the main trade examination, plus a separate R-4 Solar examination of 30 questions with 75 minutes allowed.

What is the passing score for the AZ ROC R-4 trade examination?

A passing score of 70% or higher is required on each examination: 35 correct out of 50 on the trade portion and 21 correct out of 30 on the solar portion.

Is the Arizona ROC R-4 exam an open-book test?

Yes. The examination is open-book. Approved reference books such as the International Residential Code (IRC), International Mechanical Code (IMC), NFPA 54 / National Fuel Gas Code, and OSHA 1926 regulations can be brought into the PSI test center.

Does the R-4 license cover solar thermal collector loops and solar water heating?

Yes. The R-4 classification specifically covers residential solar thermal water heating and space heating systems, including flat-plate collectors, evacuated tubes, heat exchangers, differential controllers, and solar loop piping.

Where can I schedule my PSI exam for the Arizona ROC R-4 license?

You can schedule your examination online through PSI Services at https://test-takers.psiexams.com/azcon after completing your Arizona ROC license application requirements.