Key Facts: EAL Level 3 Inspection & Testing Exam
60 Qs
603/2625/6 On-Screen Exam Questions
EAL Qualification Specification, Issue 5
61.5%
603/2625/6 Pass Mark
EAL Qualification Specification, Issue 5
0.8
Zs Temperature Factor
IET Guidance Note 3
EAL’s Level 3 Inspection & Testing awards cover initial verification and periodic inspection of UK electrical installations. This guide teaches current BS 7671:2018+A4:2026 and IET Guidance Note 3 principles; confirm the examination edition with the centre, as EAL’s public specification does not name one. Study questions supplement the required practical assessments.
Sample EAL Level 3 Inspection & Testing Practice Questions
Try these sample questions to review concepts for the EAL Level 3 Inspection & Testing exam. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.
1Which UK statutory regulation primary places a legal duty on employers, self-employed persons, and employees to ensure electrical systems are designed, constructed, maintained, and tested safely?
2According to BS 7671, what is the primary purpose of Initial Verification on a new electrical installation?
3Under BS 7671 Regulation 643.1, in what sequence must inspection and testing be conducted during Initial Verification?
4Under BS 7671, what maximum disconnection time is specified for a 230V final circuit not exceeding 32A in a TN system?
5In a TT earthing system, what protective device is generally required to achieve automatic disconnection of supply for final circuits due to high earth fault loop impedance?
6Which earthing system uses a combined neutral and protective conductor (PEN) throughout the supply distribution system up to the consumer unit main terminals?
7What is the minimum cross-sectional area required for a copper main protective bonding conductor in an installation connected to a TN-C-S (PME) supply with a neutral supply conductor of 25mm²?
8According to BS 7671 18th Edition Amendment 2, which type of RCD is generally restricted from being specified for general socket-outlet circuits where equipment containing electronic components is installed?
9Under Regulation 411.3.3, additional protection by means of a 30mA RCD is mandatory for socket-outlets rated up to what maximum current in general commercial installations?
10What IP rating is required as a minimum for accessible top surfaces of electrical enclosures containing live parts according to BS 7671?
About the EAL Level 3 Inspection & Testing Exam
EAL offers this scope through three related Level 3 awards: 600/4337/4 (Initial Verification and Certification), 600/4338/6 (Periodic Inspection, Testing and Certification), and 603/2625/6 (the single combined Inspection, Testing, Certification and Reporting award). Together they certify electrician competence in safe isolation, initial verification of new installations, periodic inspection and testing of existing installations, and issuing BS 7671 certificates and EICR reports. This is an English-language MCQ study adaptation for the official assessment; it does not replace required practical, oral, written, or hands-on performance.
Exam sponsor: EAL (Excellence, Achievement & Learning Ltd). The requirements and fees below concern the certification or admission exam, separate from our free practice resources.
Questions
60 questions
Time Limit
120 minutes
Passing Score
Pass/Fail (notionally 60%; the exact on-screen exam pass mark varies: 62% for 600/4337/4, 61.5% for 603/2625/6, 63%/62.5% for the 600/4338/6 bridging and QCR/001 exams)
Exam / Certification Fees
£47 (600/4337/4), £50 (600/4338/6), or £89 (603/2625/6) — EAL's listed qualification price; training-course tuition is set separately by each approved centre
Exam sponsor websiteFees, eligibility, and exam policies can change. Confirm them with the exam sponsor before applying or paying.
Official sources
Our practice resources: topics covered
We aim to reflect publicly available exam outlines and topic information in our study resources. Coverage, format, and difficulty may differ from the actual exam, and we cannot guarantee that every detail is accurate or current. Confirm exam requirements, fees, and policies with the official exam sponsor.
Health and Safety
The health and safety requirements that apply when inspecting, testing and commissioning an electrical installation: EAWR 1989 statutory duties, the prove-test-prove safe isolation sequence, lock-off/secure isolation, and GS38-compliant test equipment.
Requirements for Inspecting and Testing
General requirements for inspecting and testing electrical installations: the current edition of BS 7671 and IET Guidance Note 3, certification documents (EIC, MEIWC, Schedule of Inspections, Schedule of Test Results, signatories, departures), and EICR extent/agreed limitations.
Safe Inspection
The requirements for the safe inspection of electrical installations: inspection before testing (Reg 642.1), enclosure IP ratings, concealed-cable safe zones, AFDD requirements, installation notices, and EICR classification coding (C1, C2, C3, FI).
Safe Testing
The requirements for the safe testing of electrical installations: continuity (R1+R2, R2, ring r1/rn/r2), insulation resistance, polarity, Ze/Zs and the 0.8 factor, PFC/PSCC, RCD testing, phase sequence, functional testing, test-instrument requirements, and fault diagnosis.
Preparing for the EAL Level 3 Inspection & Testing Exam
What You Need to Know
- Passing score: Pass/Fail (notionally 60%; the exact on-screen exam pass mark varies: 62% for 600/4337/4, 61.5% for 603/2625/6, 63%/62.5% for the 600/4338/6 bridging and QCR/001 exams)
- Exam length: 60 questions
- Time limit: 120 minutes
- Exam / certification fees: £47 (600/4337/4), £50 (600/4338/6), or £89 (603/2625/6) — EAL's listed qualification price; training-course tuition is set separately by each approved centre Official sources
Using Our Practice Resources
- Work through all 100 available questions
- Review every answer and explanation
- Track weak areas and revisit them
- Use our AI tutor for tough concepts
EAL Level 3 Inspection & Testing: Suggested Study Strategy
Frequently Asked Questions
What is the difference between EAL's Level 3 Inspection & Testing awards and City & Guilds 2391?
They are listed as acceptable alternatives, not identical courses. The EAS Qualifications Guide (June 2025, produced by TESP for the EAS Management Committee) lists EAL 603/2625/6 alongside City & Guilds 2391-52 in both its Initial Verification (Table A4.10) and Periodic Inspection (Table A4.11) tables, EAL 600/4337/4 alongside City & Guilds 2391-50, and EAL 600/4338/6 alongside City & Guilds 2391-51. Assessment format and item counts differ between awarding bodies.
How is the 0.8 cold-Zs screening factor used?
For the familiar cold-measurement screen, compare measured Zs with 0.8 times the applicable operating-temperature limit. Apply the factor to that limit, not to the measured result. It is a conservative screening approach; an appropriate detailed temperature/protection assessment is also possible. Passing this check does not establish every aspect of circuit safety.
When should an Electrical Installation Condition Report (EICR) be given a Code C1 vs Code C2?
C1 means danger is present, such as accessible live parts, and needs immediate safe action. C2 means a potentially dangerous condition requiring urgent remedial action, such as ineffective fault protection. Assess polarity errors and loop results in their actual circumstances; do not assign C1 to every polarity error or ignore an effective RCD fault-protection arrangement.
Under BS 7671:2018+A4:2026, does an FI code make an EICR unsatisfactory?
FI alone does not make the A4 overall assessment Unsatisfactory; C1 or C2 does. Record all observations using the current form and investigate an identified issue as appropriate. That technical outcome does not remove separate legal duties: England’s current rental regulation 3 can still require further investigation or remedial work within 28 days or the shorter specified period, with the required written confirmation.