Sample MMO MTKT Air Conditioning Installation Practice Questions
Try these sample questions to review concepts for the MMO MTKT Air Conditioning Installation exam. Each question includes a detailed explanation. Start the interactive quiz above for the full 20+ question experience with AI tutoring.
1A wall has area 50 m², U-value 0.60 W/(m²·K) and a specified steady temperature difference of 12 K. Ignoring solar and storage effects, what conduction gain is calculated?
2A simplified glazing calculation uses area 12 m², incident solar irradiance 500 W/m² and effective solar heat-gain coefficient 0.35 including the specified shading condition. What instantaneous solar gain results?
3For the specified activity, each of 20 occupants contributes 75 W sensible and 55 W latent heat. What total occupant heat gain is used?
4A room has sensible cooling load 18 kW. Supply air enters at 14°C and room air is 26°C. Using dry-air specific heat 1.02 kJ/(kg·K), neglecting other sensible effects, what dry-air mass flow is required?
5A moisture source adds 2.4 kg/h of water vapor to a room. Using latent heat 2500 kJ/kg, what latent load does this represent?
6Outdoor ventilation air enters at enthalpy 78 kJ/kg dry air and is compared with room air at 50 kJ/kg dry air. For 0.50 kg dry air/s, what total outdoor-air cooling contribution is calculated?
7A room receives a short burst of radiant solar gain. Why may its cooling-load peak occur later than the gain peak?
8A common air handler serves east and west zones. At 09:00 their loads are 18 and 8 kW, with 6 kW internal and 4 kW outdoor-air load. At 15:00 they are 10 and 22 kW, with 8 and 5 kW respectively. At 18:00 they are 6 and 16 kW, with 4 and 3 kW respectively. For these three design cases, what coincident peak applies?
9Lighting adds 4 kW of heat gain: 40% immediately convective and 60% radiant. In this exercise, the hourly response method credits the full convective gain and 50% of the radiant gain to this hour's cooling load, with no earlier radiant gains. What lighting cooling load results?
10A room needs 24 kW sensible and 6 kW latent removal. Supply air is 12 K below room temperature and its humidity ratio is 0.002 kg/kg dry air lower. Use cp = 1.02 kJ/(kg·K) and hfg = 2500 kJ/kg. What minimum dry-air flow has sufficient capacity for both balances at these stated differences?
About the MMO MTKT Air Conditioning Installation Exam
Independent practice for the MTKT air-conditioning qualification, separate from MTHA ventilation. Study heat gains and loads, moist-air properties and processes, and equipment performance at project conditions.
Exam sponsor: TMMOB Makina Mühendisleri Odası (MMO) / PBK. The requirements and fees below concern the certification or admission exam, separate from our free practice resources.
Assessment
240-minute written project: heat-gain calculations worth 50 points, psychrometric work 30 and equipment selection 20. Pass 70/100. The scheme does not identify a separate oral or hands-on assessment.
Time Limit
240 minutes
Passing Score
70/100
Exam / Certification Fees
Published PBK tariff checked 21 October 2026: certificate TRY 1,500 including VAT; no additional examination fee. Course tuition separate and offering-specific.
Exam sponsor websiteFees, eligibility, and exam policies can change. Confirm them with the exam sponsor before applying or paying.
Official sources
- PBK MTKT qualification scheme · Source checked 2026-10-21Three project tasks, prerequisites, 240 minutes and 70/100 threshold.
- 2026 MTKT training and examination notice · Source checked 2026-10-21March 2026 course, mandatory attendance and separate examination booking; tuition is not the examination tariff.
- PBK current fee page · Source checked 2026-10-21Engineering certificate TRY 1,500 including VAT and no additional examination fee.
Our practice resources: topics covered
We aim to reflect publicly available exam outlines and topic information in our study resources. Coverage, format, and difficulty may differ from the actual exam, and we cannot guarantee that every detail is accurate or current. Confirm exam requirements, fees, and policies with the official exam sponsor.
Cooling loads and heat gains
Envelope, solar, internal and outdoor-air contributions; schedules and combined balances.
Psychrometrics
Dry-air mass basis, enthalpy, mixing and dehumidification.
Equipment selection
Rating conditions, coil water flow, bypass factor and net capacity.
Preparing for the MMO MTKT Air Conditioning Installation Exam
What You Need to Know
- Passing score: 70/100
- Assessment: 240-minute written project: heat-gain calculations worth 50 points, psychrometric work 30 and equipment selection 20. Pass 70/100. The scheme does not identify a separate oral or hands-on assessment.
- Time limit: 240 minutes
- Exam / certification fees: Published PBK tariff checked 21 October 2026: certificate TRY 1,500 including VAT; no additional examination fee. Course tuition separate and offering-specific. Official sources
Using Our Practice Resources
- Work through all 20 available questions
- Review every answer and explanation
- Track weak areas and revisit them
- Use our AI tutor for tough concepts
MMO MTKT Air Conditioning Installation: Suggested Study Strategy
Frequently Asked Questions
What prior qualifications are specified?
PBK lists mechanical engineering and the MTMT, MTST and MTHA qualifications, plus at least 30 hours of MTKT training. Confirm current admission details with MMO.
What are the official response languages?
They are not specified in the reviewed sources. Confirm with PBK; Turkish webpage text alone does not establish the assessment-language policy, and this resource does not imply an official English sitting.
How do these MCQs relate to the project?
Their 50/30/20 study proportions follow the published point split, but the format is an adaptation. Complete full heat-gain schedules, psychrometric charts and equipment selections alongside them.