100+ Free Supervision Engineer Practice Questions
Prepare for the China Supervision Engineer Qualification Examination (全国监理工程师职业资格考试) exam with instant access — no signup required.
Loading practice questions...
Key Facts: Supervision Engineer Exam
4 Subjects
Examination subjects under the unified national syllabus
MOHURD / MOT / MWR / MOHRSS Supervision Engineer Blueprint
60%
Fixed passing standard as a share of full marks since 2022 (66, 66, 96, 72)
MOHRSS notice on fixed pass standards for professional qualification exams
4 Years
Rolling validity period to pass all 4 subjects for all-subject candidates
CPTA Supervision Engineer Examination Implementation Measures
11 Hours
Total examination duration across 4 sessions over two consecutive days
CPTA 2026 Examination Timetable
3 Specialties
Engineering practice specialty categories: Civil/Building, Transport, Water Resources
建人规〔2020〕2号 Supervision Engineer Regulations
28 Days
Statutory time limit for submitting contractor claim notices and dossiers
Standard Construction Bidding Documents GF-2017-0201
3 Years
Validity period of registered supervision engineer practising certificate
MOHURD Order 147 Registered Supervision Engineer Management Provisions
The Supervision Engineer Qualification Examination has four subjects under a four-year rolling window and a 60% passing mark on each paper. It covers supervision rules, contract management, target control, and case analysis. This bank is an English-language MCQ study adaptation and does not simulate the official subjective case paper.
Sample Supervision Engineer Practice Questions
Try these sample questions to test your Supervision Engineer exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.
1Under Article 32 of the PRC Construction Law (中华人民共和国建筑法), what is the statutory legal nature of construction project supervision?
2Under the Code of Construction Project Management (GB/T 50319-2013), who has the statutory authority to approve the Supervision Planning (监理规划)?
3According to GB/T 50319-2013, what is the mandatory timing requirement for completing and approving the project Supervision Planning (监理规划)?
4Under GB/T 50319-2013, who is responsible for compiling and approving the Supervision Implementation Rules (监理实施细则)?
5Which on-site inspection method is defined under GB/T 50319 as continuous, uninterrupted on-site supervision of critical structural locations or crucial construction processes?
6Under the Regulations on Quality Management of Construction Works (State Council Order No. 279), what is the statutory minimum sampling ratio for witness sampling of load-bearing structural materials and components?
7Under GB/T 50319-2013, which of the following duties is an exclusive, non-delegable statutory power of the Chief Supervision Engineer (总监理工程师)?
8According to GB/T 50319-2013, under which of the following circumstances is the Chief Supervision Engineer required to issue an Engineering Work Suspension Order (工程暂停令)?
9Under Article 14 of the Regulations on the Safety Management of Construction Works (State Council Order No. 393), what mandatory action must the supervision enterprise take if a contractor refuses to rectify a major safety accident hazard or refuses to suspend construction upon order?
10Under the Provisions on the Administration of Registered Supervision Engineers (MOHURD Order No. 147), what is the statutory validity period of a Registered Supervision Engineer practising certificate, and what are the continuing education requirements for renewal?
About the Supervision Engineer Exam
The Supervision Engineer Qualification Examination (监理工程师职业资格考试) is China's national qualification for engineering-supervision professionals, administered across civil, transport, and water-conservancy tracks by MOHURD, MOT, MWR, and MOHRSS. It covers regulations and supervision theory, contract management, target control, and case analysis. This bank is an English-language MCQ study adaptation, not an official translation or format simulation and not a substitute for the subjective case paper.
Assessment
Four subjects under the unified national blueprint: Basic Theory and Relevant Regulations of Construction Engineering Supervision (建设工程监理基本理论和相关法规, 110 pts, 2.0 h); Construction Engineering Contract Management (建设工程合同管理, 110 pts, 2.0 h); Construction Engineering Target Control (建设工程目标控制, 160 pts, 3.0 h across Civil/Building, Transport, and Water Resources tracks); and Construction Engineering Supervision Case Analysis (建设工程监理案例分析, 120 pts, 4.0 h).
Time Limit
Basic Theory & Regulations 2.0 h (110 pts), Contract Management 2.0 h (110 pts), Target Control 3.0 h (160 pts), Case Analysis 4.0 h (120 pts); total 11.0 hours across two consecutive days
Passing Score
60% of the full mark of each paper (66/110, 66/110, 96/160, 72/120; fixed national standard since 2022)
Exam Fee
Set locally; Guangdong 2026 charges RMB 56 for each basic paper, RMB 66 for Target Control, and RMB 74 for Case Analysis (RMB 252 total) (MOHURD, Ministry of Transport, Ministry of Water Resources & MOHRSS)
Supervision Engineer Exam Content Outline
Supervision Basic Theory & Legal Regulations (建设工程监理基本理论和相关法规)
Statutory basis of engineering supervision, PRC Construction Law, Civil Code Part III (Construction Contracts), Regulations on Quality Management of Construction Works (State Council Order 279), Regulations on Safety Management of Construction Works (State Council Order 393), Code of Construction Project Management (GB/T 50319), organizational structures of project supervision teams, statutory qualifications and duties of the Chief Supervision Engineer (总监理工程师), Professional Supervision Engineers (专业监理工程师), and Supervision Officers (监理员), preparation and approval of Supervision Planning (监理规划) and Supervision Implementation Rules (监理实施细则), inspection methodologies (patrol inspection, side-station supervision 旁站, parallel testing, witness sampling), and issuance protocols for Supervision Notices, Work Suspension Orders (工程暂停令), and Work Resumption Approval Orders.
Construction Contract Management (建设工程合同管理)
Standard Construction Bidding Documents (GF-2017-0201 / FIDIC Red Book), tendering procedures, tender qualification pre-examination, bid security (max 2%) and performance security (max 10%), contract agreement formation, advance payment guarantees and amortization, contractor claims administration (28-day notice rule and 28-day substantiation dossier), employer claims, contract variations and valuation hierarchy, interim payment certificates, completion acceptance certificate issuance, and defect liability period (缺陷责任期) management.
Construction Project Target Control (建设工程目标控制)
Dynamic control of quality, schedule, and investment. Quality Control: raw material inspection, concealed work acceptance (隐蔽工程验收), inspection hierarchy under GB 50300 (Inspection Lot, Sub-item, Sub-division, Unit Project), quality non-conformance handling, quality accident classification and investigation. Schedule Control: progress monitoring (S-curves, banana curves), Critical Path Method (CPM) network analysis (ES, EF, LS, LF, Total Float $TF = LS - ES$, Free Float $FF = \min(ES_j - EF_i)$), schedule compression techniques (crashing, fast-tracking). Investment Control: cost baseline formation, Earned Value Management ($CV = BCWP - ACWP$, $SV = BCWP - BCWS$, $CPI = BCWP / ACWP$, $SPI = BCWP / BCWS$), price index adjustment formulas, and final settlement auditing.
Supervision Case Analysis & Incident Resolution (建设工程监理案例分析)
Integrated scenario resolution combining theory, contracts, and target controls. Assessment of engineering quality accidents (general, major, serious, catastrophic) and liability determination; identification of work safety hazards and emergency suspension powers; delay claim analysis distinguishing employer risk events, contractor defaults, and concurrent delays; calculation of time extensions and direct financial compensations; and formal dispute resolution via negotiation, adjudication, and arbitration.
How to Pass the Supervision Engineer Exam
What You Need to Know
- Passing score: 60% of the full mark of each paper (66/110, 66/110, 96/160, 72/120; fixed national standard since 2022)
- Assessment: Four subjects under the unified national blueprint: Basic Theory and Relevant Regulations of Construction Engineering Supervision (建设工程监理基本理论和相关法规, 110 pts, 2.0 h); Construction Engineering Contract Management (建设工程合同管理, 110 pts, 2.0 h); Construction Engineering Target Control (建设工程目标控制, 160 pts, 3.0 h across Civil/Building, Transport, and Water Resources tracks); and Construction Engineering Supervision Case Analysis (建设工程监理案例分析, 120 pts, 4.0 h).
- Time limit: Basic Theory & Regulations 2.0 h (110 pts), Contract Management 2.0 h (110 pts), Target Control 3.0 h (160 pts), Case Analysis 4.0 h (120 pts); total 11.0 hours across two consecutive days
- Exam fee: Set locally; Guangdong 2026 charges RMB 56 for each basic paper, RMB 66 for Target Control, and RMB 74 for Case Analysis (RMB 252 total)
Keys to Passing
- Work through all 100 available questions
- Review every answer and explanation
- Track weak areas and revisit them
- Use our AI tutor for tough concepts
Supervision Engineer Study Tips from Top Performers
Frequently Asked Questions
What is the China Supervision Engineer Qualification Examination?
It is the statutory national licensing qualification for engineering supervision professionals in the People's Republic of China, jointly administered by MOHURD, MOT, MWR, and MOHRSS. Registered supervision engineers represent project owners on site to independently oversee construction quality, work safety, schedule progress, contract fulfillment, and investment control.
What are the four examination subjects, and how does this bank adapt them?
The examination consists of Basic Theory & Regulations (110 points, 2 h), Contract Management (110, 2 h), Target Control (160, 3 h across Civil, Transport, or Water tracks), and Case Analysis (120, 4 h). The official notices reviewed do not explicitly publish selectable assessment-language options, so no official-language code is asserted. This bank is an English-language MCQ study adaptation, not an official translation or format simulation and not a substitute for the subjective case paper.
What is the passing standard and score validity period?
Since 2022, MOHRSS enforces a fixed passing mark of 60% of the maximum score for each paper: 66/110 for Basic Theory & Regulations, 66/110 for Contract Management, 96/160 for Target Control, and 72/120 for Case Analysis. Candidates taking all four papers have a 4-year rolling cycle to pass all subjects.
What duties are strictly reserved for the Chief Supervision Engineer (总监理工程师)?
Under GB/T 50319, the Chief Supervision Engineer cannot delegate the following statutory responsibilities: (1) Presiding over the preparation and revision of the Supervision Planning; (2) Approving Supervision Implementation Rules; (3) Organizing the review of contractor construction organization designs, hazardous works special safety schemes, and progress schedules; (4) Signing Work Commencement Notices, Work Suspension Orders, and Work Resumption Approval Orders; (5) Signing Interim Payment Certificates and Final Settlement Certificates; (6) Participating in engineering quality accident investigations; and (7) Organizing preliminary completion acceptance and signing the project completion acceptance report.
What are the statutory warranty periods under State Council Order No. 279?
Under Article 40 of the Regulations on the Quality Management of Construction Works (State Council Order 279), minimum statutory warranty periods from completion acceptance are: (1) Infrastructure foundation and main structural works: the reasonable design working life of the structure (typically 50 years for civil buildings); (2) Roof waterproofing, exterior walls, and rooms/toilets with waterproofing requirements: 5 years; (3) Heating and air conditioning systems: 2 heating/cooling periods; (4) Electrical wiring, water supply/drainage pipelines, equipment installation, and decoration works: 2 years.
What is the 28-day rule for contractor claims under GF-2017-0201?
Under the Standard Construction Bidding Documents (GF-2017-0201), if an event occurs that entitles the contractor to time extension or cost compensation, the contractor must send a formal Claim Notice to the supervising engineer within 28 days of becoming aware (or when they ought to have become aware) of the event. If the contractor fails to provide notice within this 28-day window, they lose the right to claim time extension and additional payment. The contractor must then submit detailed substantiating claim accounts within 28 days after the initial notice.