6.5 Storage Tanks & Reservoirs

Key Takeaways

  • Distribution storage serves three purposes: equalizing demand, providing fire flow reserve, and supplying emergency reserve during outages.
  • Elevated tanks and standpipes float on the system and set the hydraulic grade line, while ground storage usually requires booster pumping.
  • Inadequate turnover is the leading water quality problem in storage, producing residual loss, nitrification, and thermal stratification.
  • Tank vents and overflows must be screened and the overflow must discharge through an air gap, never submerged or directly connected to a sewer.
  • Tanks must be inspected on a regular cycle and disinfected after cleaning or repair before returning to service.
Last updated: August 2026

6.5 Storage Tanks & Reservoirs

Storage is where the distribution system's water sits still — and standing water is where water quality goes to die. Operators are tested both on why storage exists and on the specific sanitary defects that turn a tank into a contamination pathway.


1. Why Storage Exists

PurposeWhat it does
EqualizationLets the plant and wells run at a steady average rate while the tank absorbs peak-hour demand. Without it, source and pumping capacity would have to match peak instantaneous demand
Fire flow reserveHolds a dedicated volume for firefighting, usually the controlling factor in sizing storage for small systems
Emergency reserveKeeps water flowing during power failure, main break, pump failure, or a plant shutdown
Pressure stabilizationElevated storage floats on the system and holds the hydraulic grade line steady, damping pressure fluctuation

Storage also reduces energy cost by letting pumps run during off-peak power periods.


2. Storage Types

TypeDescriptionHydraulics
Elevated tankBowl on a tower or pedestalFloats on the system; sets the hydraulic grade line directly. All usable volume is at useful pressure
StandpipeTall cylindrical ground-supported tankOnly the upper portion is at useful pressure; the lower portion is effectively dead storage requiring pumping
Ground storage reservoirLarge-volume tank at gradeRequires booster pumping to serve the system
Hydropneumatic tankPressure vessel with an air cushionSmall systems; very little usable volume, primarily controls pump cycling
ClearwellAt the plant, downstream of filtersProvides disinfection contact time for CT credit and buffers between filtration and high-service pumping

Note the exam distinction: a clearwell's primary job is contact time, not distribution storage.


3. Turnover — The Central Water Quality Issue

Water sitting in a tank for days loses disinfectant residual, warms, stratifies, and grows biofilm. Good practice targets complete turnover in roughly 3 to 5 days, achieved by cycling the level meaningfully rather than holding the tank nearly full.

Symptoms of poor turnover

  • Disinfectant residual falls at the tank outlet compared with the inlet.
  • Heterotrophic plate counts rise; coliform positives appear near the tank.
  • Nitrification in chloraminated systems — falling chloramine residual with rising nitrite and nitrate, as described in Section 5.3.
  • Thermal stratification — warm water layers on top and never mixes, so a fraction of the tank is effectively stagnant year-round.
  • Taste, odor, and color complaints concentrated in the tank's service area.

Corrective measures

MeasureEffect
Increase level cyclingDeeper daily draw-down forces exchange of the stored volume
Separate inlet and outlet pipingA single common inlet/outlet pipe lets fresh water enter and immediately leave, leaving the bulk stagnant — this is the classic design defect
Active mixing systemsMechanical or passive mixers break thermal stratification
Deep-cycle then refillPeriodic aggressive draw-down to exchange the full volume
Booster disinfection at the tankRestores residual where turnover alone cannot
Reduce oversized storageSome systems simply hold more storage than demand can turn over

4. Sanitary Defects — The Inspection Checklist

These are exactly the items a sanitary survey looks for, and they are prime exam material:

ComponentRequirement
Hatches and access openingsLocked, with a raised curb at least 4 inches and an overlapping, downward-shielded cover with a gasket
VentsMust be present and sized for maximum flow, downturned or otherwise shielded, and screened (commonly 24-mesh corrosion-resistant) to exclude insects, birds, and debris
OverflowScreened, downturned, and discharging over an air gapnever submerged, never directly connected to a sewer or storm drain
DrainDischarged through an air gap
Roof and seamsWatertight; no ponding, no openings, no bird access
Coating and cathodic protectionInterior coating intact and NSF/ANSI 61 certified; cathodic protection functioning
SiteFenced, secured, graded to drain away from the structure

The single most-tested defect: a submerged overflow or an overflow piped directly into a sewer creates a direct cross-connection between the finished water storage and the sewer. The overflow must always terminate above grade with a visible air gap and a screened, downturned opening.


5. Inspection, Cleaning, and Return to Service

Inspection frequency: exterior inspections should be frequent and routine; interior inspections are commonly performed on a 3-to-5-year cycle, by draining and entering, by diver, or by remotely operated vehicle. Sediment accumulation, coating failure, corrosion, and structural defects are the findings that drive maintenance.

Confined space: entering a drained tank is a permit-required confined space entry. Every requirement in Section 13.1 applies — atmospheric testing, ventilation, attendant, retrieval equipment, and permit.

Disinfection before return to service

Any tank that has been drained, cleaned, coated, or repaired must be disinfected before it is returned to service, following AWWA C652. Three accepted methods:

MethodApproach
Chlorination Method 1Fill the tank with water dosed to about 10 mg/L free chlorine and hold for at least 6 hours
Chlorination Method 2Spray or brush all interior surfaces with a strong solution of roughly 200 mg/L and hold at least 30 minutes
Chlorination Method 3Fill about 5% of the tank volume with water dosed to about 50 mg/L, hold 6 hours, then fill to overflow and hold a further period

After disinfection, the tank is drained or the water is neutralized and disposed of appropriately, then refilled and sampled for bacteriological analysis. Two consecutive satisfactory samples taken 24 hours apart are required before the tank returns to service. Highly chlorinated water must be dechlorinated before discharge to protect receiving waters — see Section 9.1.

Test Your Knowledge

A storage tank shows a much lower disinfectant residual at its outlet than at its inlet, and nearby customers report taste complaints. What is the most likely cause?

A
B
C
D
Test Your Knowledge

How must a finished water storage tank overflow terminate?

A
B
C
D
Test Your Knowledge

After a storage tank is drained, cleaned, and recoated, what must occur before it returns to service?

A
B
C
D
Test Your Knowledge

Which storage type floats on the distribution system and directly establishes the hydraulic grade line?

A
B
C
D