11.4 Initiating a Project
Key Takeaways
- Initiating a Project is triggered by the request to initiate (from Starting Up) and is performed by the Project Manager; its purpose is to establish firm foundations so the board can authorise the project.
- The headline output is the Project Initiation Documentation (PID) — the project's 'contract' containing the Project Plan, refined Business Case, management approaches, project controls, tailoring, and roles.
- Initiating is where the management approaches (Risk, Quality, Communication, Sustainability, Change, Benefits) are created and where the Project Plan and refined Business Case are built.
- At the end of Initiating, the Project Board authorises both the project and the first stage (a single combined decision), marking the transition into delivery and the start of Controlling a Stage.
Trigger and purpose
Initiating a Project (IP) is triggered by the request to initiate that emerges from Starting Up a Project, once the Project Board has authorised initiation. It is performed by the Project Manager, with contributions from the Executive (Business Case), Project Assurance, and team members.
Its purpose is to establish firm foundations for the project — to do enough planning, risk thinking, and control design that the board can make an informed decision to authorise the project. PRINCE2 treats initiation as an investment: it costs effort, but it prevents far larger losses from a project that was never viable or was set up with the wrong controls. The output of initiation is the basis against which the whole project will be monitored and controlled.
Activities
| Activity | Output | Notes |
|---|---|---|
| Agree the tailoring approach | Tailoring decisions embedded in the PID | How the method will be applied to this project |
| Prepare the Risk Management Approach + Risk Register | How risks will be identified, assessed, controlled | Practice applied to the project |
| Prepare the Quality Management Approach + Quality Register | Quality methods, responsibilities, audit | What 'quality' means here |
| Prepare the Communication Management Approach | Stakeholder engagement plan, report frequency | Who needs what, when |
| Prepare the Issue Management Approach | How issues are captured and assessed, and how changes to baselines are controlled | Also documents the use and composition of any Change Authority |
| Prepare the Change Management Approach | How the organisation moves from its current state to the target state | v7: organisational change management — not project change control |
| Prepare the Commercial Management Approach | Procurement, contracts, and supplier management | New in v7 |
| Prepare the Digital and Data Management Approach | How project data is managed during the project and after it closes | New in v7 |
| Prepare the Sustainability Management Approach | Environmental/social controls (v7 emphasis) | New in v7 as a distinct lens |
| Prepare the Benefits Management Approach | How benefits will be realised and measured | Links to the Business Case |
| Set up project controls | Tolerances, reporting cadence, escalations | The control framework |
| Create the Project Plan | The overall plan, stage boundaries, dependencies | NOT a Stage Plan — the whole project |
| Refine the Business Case | Detailed rationale, costs, benefits, risks | Developed from the outline in the Project Brief |
| Assemble the PID | The consolidated 'project contract' | The single output the board authorises against |
The PID — what's inside
The Project Initiation Documentation is the project's contract. It is the single management product that the board reviews at the end of Initiating, and once authorised it becomes the baseline against which the project is controlled. It contains:
- Project Plan — the full project-level plan with stage boundaries and major dependencies.
- Refined Business Case — the detailed justification, costs, benefits, major risks, and timescales.
- Project controls — tolerances (time, cost, scope, quality, benefits, risk), reporting cadence, and escalation paths.
- Management approaches — Risk, Quality, Communication, Change, Sustainability, Benefits (and Configuration where maintained separately).
- Tailoring — how PRINCE2 has been tailored for this project and why.
- Project management team structure and role descriptions — who does what.
- Project Product Description — carried forward from the Project Brief and refined.
A useful memory hook: the PID is the plan, the case, the controls, the rules, and the people. If a scenario asks what is in the PID, look for that combination; if it lists only the Project Plan, it is incomplete.
Authorisation at the end of Initiating
At the end of Initiating, the PM submits the PID plus the first Stage Plan (the plan for the first delivery stage, not the initiation stage) to the Project Board. The board, in Directing a Project, makes a single combined decision: authorise the project and authorise the first stage. This is the formal point at which the project is committed. From here, the project moves into delivery: Controlling a Stage begins, and Directing a Project continues to overlay it.
A subtle exam point: the initiation stage itself was authorised earlier (in authorise initiation, at the end of Starting Up). What the board authorises at the end of Initiating is the project and the first delivery stage. Do not conflate the two authorisations.
Common exam scenarios
- "What document is assembled at the end of Initiating a Project?" — the PID.
- "Where are the Risk Management Approach and Quality Management Approach created?" — in Initiating a Project (not in Starting Up, which only prepares the outline Business Case and Project Product Description).
- "Who authorises the project, and at the end of which process?" — the Project Board in Directing a Project, at the end of Initiating a Project.
- "What triggers Initiating a Project?" — the request to initiate from Starting Up, after the board has authorised initiation.
- "Is the Project Plan created in Starting Up or Initiating?" — in Initiating. Starting Up produces only an Initiation Stage Plan.
Tailoring and proportionality
For a small project, the PID may be a concise folder; the management approaches may be combined into a single document. For a large or regulated project, each approach may be a substantial standalone document with appendices. The v7 manual stresses that initiation should be proportionate to risk and complexity — the goal is firm foundations, not paperwork for its own sake. The tailoring decision recorded in the PID should explain why each approach is scaled the way it is.
Which combination of management products is assembled into the Project Initiation Documentation at the end of Initiating a Project?
At the end of Initiating a Project, what does the Project Board authorise, and within which process does that decision sit?