Formwork Loads, Shoring, Reshoring & Stripping

Key Takeaways

  • Normal-weight concrete weighs about 150 pounds per cubic foot, so a 6-inch elevated slab alone imposes roughly 75 pounds per square foot of dead load.
  • ACI 347 sets a minimum construction live load of 50 psf (75 psf with motorized carts) and a minimum total design load of 100 psf (125 psf with carts).
  • OSHA 29 CFR 1926.703 requires formwork to be designed, fabricated, erected, supported, braced, and maintained to carry all vertical and lateral loads.
  • Reshores are installed after original shores are removed and the slab has deflected under its own weight; backshores never allow the slab to carry its full load.
  • Forms and shores come out only when the concrete reaches the strength the engineer or specification requires — never on a calendar guess.
Last updated: August 2026

Formwork Loads, Shoring, Reshoring & Stripping

Quick Answer: Formwork carries dead load (concrete at about 150 pcf plus the forms themselves) and construction live load (workers, tools, buggies). ACI 347 sets minimums of 50 psf live load — 75 psf with motorized carts — and a 100 psf total design load (125 psf with carts). OSHA 1926.703 requires formwork to be designed and maintained for all vertical and lateral loads. Shores support fresh concrete; reshores are re-installed after the slab has taken its own weight; backshores never let the slab deflect fully. Strip only when the specified strength is verified — never on a calendar.

Foundations and Formwork is a 10-item domain, and formwork collapse is one of the highest-consequence failures in commercial construction. The previous section covered the components of vertical and horizontal systems. This section covers the loads and the sequence — the reasoning that decides whether those components are adequate and when they can safely come out.

Where formwork loads come from

LoadSourceTypical magnitude
Concrete dead loadPlastic concrete in the formAbout 150 pcf normal weight (145 pcf plain, plus reinforcing)
Formwork dead loadSheathing, joists, stringers, shoresOften assumed around 5-15 psf
Construction live loadCrew, tools, hoses, stored material50 psf minimum (ACI 347)
Motorized cart allowancePower buggies on the deck75 psf minimum live load
Lateral concrete pressureFluid head on vertical formsRises with pour height, rate of placement, cooler temperatures
Lateral wind/impactWind on formwork, equipment strikesPer design and jurisdiction

Slab dead-load example. How much dead load does a 6-inch normal-weight elevated slab put on the deck forms?

  • Thickness in feet: 6 / 12 = 0.5 ft
  • Dead load: 0.5 x 150 = 75 psf from the concrete alone

Add formwork self-weight and the 50 psf minimum live load and the deck is designing to roughly 130-140 psf — comfortably above the 100 psf ACI minimum, which is exactly why the minimum is a floor, not a target.

ACI 347 minimums to remember:

  • Construction live load: not less than 50 psf
  • With motorized carts: not less than 75 psf
  • Total design load (dead + live): not less than 100 psf
  • Total design load with motorized carts: not less than 125 psf

Lateral pressure on vertical forms

Fresh concrete behaves like a heavy fluid until it stiffens. Lateral pressure against wall and column forms increases when:

  • The rate of placement is faster (concrete stays plastic deeper into the pour)
  • The pour height is greater
  • Temperatures are cooler (slower set keeps concrete fluid longer)
  • Superplasticizers or high-slump mixes delay stiffening
  • Vibration is applied deeper than the current lift

It decreases with warmer temperatures, slower placement, and mixes that stiffen quickly. The practical control is the rate of placement specified in the form design — pouring faster than the forms were designed for is a leading cause of blowouts, and it is a decision made by the crew, not the engineer.

Never compute a pressure from memory on the job. ACI 347 publishes formulas with limits of applicability; the form design drawing states the assumed rate and temperature. Your responsibility is to place within those assumptions and to stop if conditions change.

Shoring, reshoring, and backshoring

These three terms are frequently confused and are a reliable source of exam items.

TermDefinitionLoad state of the slab
ShoresOriginal vertical supports carrying the fresh pour and its formsSlab carries nothing; shores carry everything
ReshoresSupports placed after forms and original shores are removedSlab has already deflected and carries its own dead load
BackshoresOriginal shores removed and replaced one at a timeSlab is never allowed to deflect fully or carry full load

The distinction matters structurally. A reshore is installed snug but not preloaded, so the slab below it is not asked to carry the new slab's dead load — the reshore only picks up subsequent construction loads. A backshore keeps the slab supported continuously, which is used when a young slab must not be allowed to take its own weight.

Multi-story load path. When a new deck is poured, its weight travels down through shores into the slab below, then through reshores into the slabs below that, until enough levels share the load that no single young slab is overstressed. The number of levels of shoring and reshoring is an engineering decision shown on the shoring drawings. Removing a level early because it is in the way of a delivery is how a progressive collapse starts.

What OSHA requires — 29 CFR 1926 Subpart Q

Subpart Q covers concrete and masonry construction; 1926.703 addresses formwork specifically.

  • Formwork must be designed, fabricated, erected, supported, braced, and maintained to support all vertical and lateral loads that may reasonably be anticipated.
  • Drawings or plans for the jack layout, formwork, shoring, working decks, and scaffolds must be available at the jobsite.
  • Shoring equipment must be inspected before, during, and immediately after the pour; damaged or weakened equipment is removed from service.
  • Reshoring must be erected as the original forms and shores are removed, and must be capable of supporting the loads imposed.
  • Forms and shores may not be removed until the employer determines the concrete has gained sufficient strength to support its own weight and superimposed loads — that determination is based on compliance with the design drawings/specifications or on tests (field-cured cylinders or in-place testing) showing the concrete has reached the required strength.
  • Single-post shores in more than one tier must be designed, spliced to prevent misalignment, and laterally braced.
  • Vertical slip forms, lift-slab operations, and precast erection carry their own specific requirements.

Stripping: criteria before sequence

The criterion is strength, not time. "We always strip at three days" is not an acceptable answer on an assessment or in an incident investigation. Acceptable bases include:

  1. The specification or engineer's stated stripping strength or time, when the design provides one.
  2. Field-cured test cylinders broken to confirm the required compressive strength — field-cured, because they experience the same conditions as the structure, unlike standard lab-cured cylinders used for acceptance.
  3. In-place methods such as maturity or pullout testing where specified and calibrated.

Cold weather, poor curing, low cement content, or admixture problems all delay strength gain. The concrete does not know what the schedule promised.

Stripping sequence

OrderElementReasoning
1Non-loadbearing vertical forms — wall and column sidesThese forms only resisted lateral pressure; the element supports itself
2Beam sidesSame logic — sides carry no gravity load
3Slab soffits and beam bottomsThese carry gravity load; strip only at verified strength, with reshoring plan in place
4Shores under long spans and cantileversHighest deflection sensitivity; strip last and reshore per drawings

Cantilevers are the classic trap. A cantilevered slab or balcony has no backspan support once the shores are gone, and its critical stress is at the support, not midspan. Cantilever shores stay in longer and are removed strictly per the engineer's direction.

Additional stripping discipline:

  • Do not drop or pry recklessly — damaged panels become tomorrow's failure, and falling forms are a struck-by hazard.
  • Apply release agent properly on the previous cycle so panels come away cleanly instead of tearing the concrete face.
  • Protect green concrete edges and corners; arrises chip easily at early ages.
  • Keep exclusion zones below any stripping operation.
  • Clean, inspect, and repair panels, ties, and shores before the next cycle; bent shores and elongated tie holes are rejected, not reused.

Failure modes carpenters control

FailureRoot causeControl
Wall form blowoutPlacement rate exceeded design assumptionPour to the specified rate; monitor ties and walers
Deck collapseShores removed early or reshores omittedVerify strength; follow shoring drawings
Shore punch-throughInadequate mudsill or soft subgradeSound bearing, proper sills, level base
Progressive collapseToo few shored/reshored levelsEngineering decision; never field-modified
Tie failureWrong tie capacity or damaged hardwareMatch tie to design; inspect and reject damaged hardware

Formwork is temporary structure that carries permanent-structure loads at the moment the permanent structure is weakest. That is why the Foundations and Formwork domain rewards candidates who can explain why a shore stays in — not just what it is called.

Test Your Knowledge

Under ACI 347, what is the minimum total design load (dead plus live) for formwork supporting an elevated slab where motorized carts will NOT be used?

A
B
C
D
Test Your Knowledge

What distinguishes reshores from the original shores on a multi-story concrete building?

A
B
C
D
Test Your Knowledge

Under OSHA 29 CFR 1926.703, on what basis may forms and shores be removed from a concrete slab?

A
B
C
D
Test Your Knowledge

Which condition INCREASES lateral pressure against a concrete wall form?

A
B
C
D
Congratulations!

You've completed this section

Continue exploring other exams