10.3 Submittals, Shop Drawings, Product Data & Samples

Key Takeaways

  • Submittals are not Contract Documents; they are administrative mechanisms prepared by the contractor, fabricators, and manufacturers to demonstrate how they intend to execute the design intent.
  • Under AIA Document A201 Section 3.12.5, the General Contractor is contractually mandated to review, verify field dimensions, coordinate trade requirements, and stamp all submittals prior to forwarding them to the Landscape Architect.
  • The Landscape Architect's review of submittals is strictly limited to checking for conformance with the design concept and general compliance with Contract Documents, never verifying dimensions, quantities, or fabrication methods.
  • Standard review action stamps include Approved / No Exceptions Taken, Approved as Noted / Make Corrections Noted, Revise and Resubmit, Rejected, and Returned Without Action.
  • Informational submittals (concrete break test reports, soil compaction tests, nursery health inspection certificates) are submitted for record documentation and do not receive formal design approval action stamps.
Last updated: September 2026

Core Focus: Submittals represent one of the highest areas of administrative liability for landscape architects during construction. The LARE Section 3 exam heavily tests the submittal workflow, the mandatory contractor review stamp, the distinction between Action and Informational submittals, review stamp legal definitions, and the critical legal boundary separating design intent review from contractor dimensional verification.


1. The Submittal Workflow & Legal Status

A fundamental legal concept in construction administration is that Submittals are NOT Contract Documents (AIA Document A201 Section 3.12.4). Contract Documents consist of the Agreement, Conditions of the Contract (General, Supplementary), Drawings, Specifications, Addenda, and executed Modifications. Submittals (shop drawings, product data, samples, mockups) are administrative instruments prepared by the Contractor, subcontractors, and suppliers to illustrate how the contractor proposes to implement the design concept.

+--------------------------------------------------------------------------+
|                       SUBMITTAL REVIEW LIFECYCLE                         |
+--------------------------------------------------------------------------+
| Trade Subcontractor / Fabricator / Supplier prepares submittal           |
|         │                                                                |
|         ▼                                                                |
| General Contractor (GC) Pre-Review:                                      |
|   ├─ Verifies field measurements and site dimensions                     |
|   ├─ Coordinates inter-trade clearances (e.g., plumbing vs. footings)    |
|   ├─ Checks compliance with technical specifications                     |
|   └─ APPLIES SIGNED/DATED GC REVIEW STAMP                                |
|         │                                                                |
|         ├────────────────────────────────────────┐                       |
|         ▼ (Stamped)                              ▼ (Unstamped)           |
| Landscape Architect Receives Submittal      RETURNED WITHOUT ACTION      |
|         │                                   (Immediately rejected back   |
|         ▼                                    to GC without review)       |
| Landscape Architect Reviews for Design Concept Conformance               |
|   └─ Coordinates with Subconsultants (Civil, Structural, Irrigation)     |
|         │                                                                |
|         ▼                                                                |
| Action Stamp Applied (Approved, Approved as Noted, Revise/Resubmit)      |
|         │                                                                |
|         ▼                                                                |
| Returned to GC ──► Distributed to Subcontractor ──► Fabrication Proceeds |
+--------------------------------------------------------------------------+

The Mandatory Contractor Pre-Review Stamp

Under AIA Document A201 Section 3.12.5: "The Contractor shall review for compliance with the Contract Documents, approve, and submit to the Architect, Shop Drawings, Product Data, Samples, and similar submittals required by the Contract Documents... By submitting Shop Drawings, Product Data, Samples, and similar submittals, the Contractor represents to the Owner and Architect that the Contractor has (1) reviewed and approved them, (2) determined and verified materials, field measurements, and field construction criteria, and (3) checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents."

[!IMPORTANT] The Unstamped Submittal Rule: If a landscape architect receives a submittal directly from a subcontractor, or receives a submittal from the General Contractor that lacks the General Contractor's signed and dated review stamp, the landscape architect must return it immediately without action. Reviewing an unstamped submittal bypasses the contractor's legal responsibility for field dimensions and coordination, effectively assuming that liability onto the design professional.


2. Categorization of Submittal Types

Submittals in landscape architecture fall into two broad contractual classes: Action Submittals (requiring formal design professional review and responsive stamping) and Informational Submittals (submitted for documentation and compliance verification, without design approval stamps).

                               SUBMITTAL CLASSIFICATIONS
                                           │
        +----------------------------------+----------------------------------+
        │                                                                     │
  ACTION SUBMITTALS                                                 INFORMATIONAL SUBMITTALS
  (Require Design Review & Stamp)                                   (For Record & Compliance Only)
  ├─ Shop Drawings (Fabrication, structural)                        ├─ Compaction Test Reports (ASTM D1557)
  ├─ Product Data (Cut sheets, pumps, lights)                       ├─ Concrete Cylinder Breaks (ASTM C39)
  ├─ Material Samples (Stone, pavers, mulch)                        ├─ Topsoil Chemistry / Agronomic Tests
  └─ Physical Mockups (Stone walls, unit pavers)                    └─ Nursery Phytosanitary Certificates

1. Shop Drawings (Action Submittal)

Shop drawings are drawings, diagrams, schedules, and other data specially prepared for the work by the contractor, subcontractor, manufacturer, supplier, or distributor to illustrate some portion of the work.

  • Landscape Architecture Applications:
    • Structural fabrication drawings for custom steel shade structures, pergolas, and decorative gates showing member sizes, weld symbols, and bolt patterns.
    • Reinforcing steel (rebar) placement diagrams for cast-in-place concrete retaining walls, showing lap splices, bends, and bar clearances.
    • Stone fabrication cutting tickets and shop setting drawings for radial granite steps, curved pool coping, and dimensioned architectural masonry.
    • Fountain and water feature mechanical room piping layouts, manifold details, and electrical pump panel diagrams.
    • Precast concrete paver and architectural wall panel shop drawings showing anchor clips, joints, and embedded lifting inserts.

2. Product Data Sheets / Cut Sheets (Action Submittal)

Standard manufacturer product data sheets, catalog illustrations, performance curves, installation instructions, operating charts, and brochures.

  • Landscape Architecture Applications:
    • Irrigation central satellite controllers, commercial rotor heads, drip emitters, master valves, and backflow preventers.
    • Site lighting fixtures, LED bollards, pathway luminaires, and step lights.
    • Site furnishings: benches, bicycle racks, trash receptacles, tree grates, and bollards.
    • Drainage geocomposites, root barriers, filter fabrics, and permeable paver polymeric joint sand.
    • Organic soil amendments, biostimulants, mycorrhizal inoculants, and organic tackifiers.

3. Material Samples (Action Submittal)

Physical samples of specified materials demonstrating full visual range of color, texture, surface finish, grain, and general workmanship.

  • Landscape Architecture Applications:
    • Range Samples: Sets of at least 3 to 5 physical stone units showing the full allowable chromatic variation, veining, and texture of natural quarry stone.
    • Concrete paver sample boards showing color blends and aggregate exposures.
    • Architectural concrete integral pigment color chips and chemical retarder surface exposure samples.
    • Factory-applied powder-coat and fluoropolymer paint color swatches on actual aluminum or steel substrates.
    • Wood samples of specified exterior lumber (e.g., ipê, black locust, western red cedar) showing grain, finish, and protective sealers.

4. Physical On-Site Mockups (Action Submittal)

Full-scale physical assemblies constructed on the project site using actual job materials, equipment, and specified trade labor to establish the visual and technical benchmark of quality.

  • Landscape Architecture Applications:
    • Unit Paving Mockup: A minimum 10 ft by 10 ft on-site panel of permeable concrete pavers, demonstrating sub-base compaction, bedding layer, joint sand sweeping, plate compaction, pattern transitions, edge restraints, and cutting alignment.
    • Stone Masonry Wall Mockup: A 6 ft wide by 4 ft high sample of a stone veneer wall showing mortar joint width, mortar color, joint tooling (raked, flush, concave), corner bonding, and capping.
    • Cast-in-Place Architectural Concrete Mockup: Demonstrating formliner texture, form-tie hole patching, chamfered edges, and color consistency.
  • Contractual Rules for Mockups: The mockup must be formally approved in writing by the Landscape Architect prior to beginning full-scale production. The approved mockup is protected and remains on site throughout construction as the standard of quality against which all subsequent work is judged. If permitted by specifications, an approved mockup may be incorporated into the finished work; if rejected, it must be demolished and rebuilt until approved.

5. Informational Submittals & Quality Certifications

Submittals provided to verify that materials and operations meet contract quality requirements. These are reviewed to ensure compliance, documented in the project log, and filed for the record, but do not receive design approval action stamps.

  • Landscape Architecture Applications:
    • Geotechnical field density test reports (soil compaction percentages per ASTM D1557 / ASTM D698).
    • Concrete compressive strength laboratory test reports (7-day and 28-day cylinder breaks per ASTM C39).
    • Agronomic topsoil laboratory testing reports (pH, organic matter content, soil texture/particle size analysis, cation exchange capacity [CEC], nutrient levels, and heavy metal screening).
    • State Department of Agriculture nursery phytosanitary inspection certificates certifying plant stock is free of quarantine pests and invasive pathogens.
    • Mill certificates and non-destructive testing (NDT) reports for structural steel welds.
    • Installer qualification statements verifying mandatory years of certified commercial experience.

3. Review Action Stamps & Legal Liability Allocation

The wording of the Landscape Architect's review stamp is crafted by professional liability insurers to precisely limit legal exposure.

The Legal Scope of Design Review

Under AIA Document A201 Section 4.2.7: "The Architect will review and approve, or take other appropriate action upon, the Contractor's submittals such as Shop Drawings, Product Data, and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents."

[!CAUTION] What the Review Stamp DOES NOT Mean:

  • The Landscape Architect does NOT verify site dimensions, quantities, or field measurements.
  • The Landscape Architect does NOT approve construction means, methods, techniques, sequences, or procedures.
  • The Landscape Architect does NOT validate job site safety programs.
  • The Landscape Architect's approval does NOT relieve the Contractor of responsibility for errors or omissions in shop drawings, or for deviations from the Contract Documents.

Standard Review Action Stamp Terminology

+--------------------------------------------------------------------------+
|                 LANDSCAPE ARCHITECT SUBMITTAL ACTION STAMP               |
+--------------------------------------------------------------------------+
| [ ] NO EXCEPTIONS TAKEN (APPROVED)                                       |
|     Fabrication and procurement may proceed.                             |
|                                                                          |
| [ ] MAKE CORRECTIONS NOTED (APPROVED AS NOTED)                           |
|     Fabrication may proceed subject to marked corrections. No resubmittal|
|     required unless specifically directed.                               |
|                                                                          |
| [ ] REVISE AND RESUBMIT                                                  |
|     Major discrepancies or missing data. Fabrication NOT authorized.     |
|     Contractor must revise and resubmit.                                 |
|                                                                          |
| [ ] REJECTED                                                             |
|     Submittal deviates fundamentally from contract documents.            |
|     Complete resubmission of compliant product required.                 |
|                                                                          |
| [ ] RETURNED WITHOUT ACTION                                              |
|     Submittal lacked GC stamp, was not required, or was uncoordinated.   |
+--------------------------------------------------------------------------+
| Review is only for general conformance with the design concept of the   |
| Contract Documents. Contractor remains responsible for all dimensions,   |
| quantities, field coordination, and means and methods of construction.   |
+--------------------------------------------------------------------------+

The Hidden Deviation Rule (AIA A201 Section 3.12.8)

A critical exam scenario involves contractor deviations from the contract documents hidden within shop drawings:

  • If a contractor submits a shop drawing that changes a specified material (e.g., changes stainless steel fasteners to zinc-plated steel), and the landscape architect stamps the drawing "Approved" without noticing the change, the contractor is STILL contractually liable for the non-conforming substitution.
  • Under Section 3.12.8, the contractor is not relieved of responsibility for deviations unless:
    1. The contractor specifically calls attention to the deviation in a separate written cover letter at the time of submission; AND
    2. The landscape architect gives specific written approval to the designated deviation as a minor change, or a formal Change Order / CCD is executed.

4. Submittal Log Tracking & Turnaround Timeframes

Efficient submittal processing prevents contractor delay claims. Construction contracts typically stipulate a 14-calendar-day turnaround window (or 10 to 14 business days) for the design professional's review.

The Submittal Schedule (AIA A201 Section 3.10.2)

Promptly after contract award, the General Contractor must prepare and submit a comprehensive Submittal Schedule for the Landscape Architect's approval. The schedule must be coordinated with the construction progress schedule, allowing reasonable time for design review, consultant coordination, and material fabrication lead times.

Essential Fields in a CA Submittal Log

Column HeaderDescription & Purpose
Submittal NumberAlphanumeric tracking code (e.g., 32 14 00-01.0 indicating spec section, sequence, revision).
Spec Section & TitleCSI MasterFormat classification (e.g., 32 14 00 Unit Paving).
Description of ItemClear narrative (e.g., "80mm Interlocking Concrete Pavers - Color Range Sample").
Subcontractor / SupplierOriginating fabricator, quarry, or nursery.
Date Received from GCStarting timestamp for the contractual review window.
Sent to SubconsultantDate forwarded to civil, structural, or irrigation consultant.
Returned from ConsultantDate consultant comments were received by prime Landscape Architect.
Date Returned to GCConcluding timestamp verifying compliance with turnaround timeframe.
Action TakenOfficial review status code (NET, MCN, R&R, REJ, RWA).
Days in ReviewElapsed calendar days (flags potential delay exposure if > 14 days).

5. Submittal Types & Roles Comparison Table

Submittal TypeClassificationOriginatorPurpose & Review ScopeApproval Stamp Required?
Shop DrawingsAction SubmittalContractor / FabricatorVerifies how custom assemblies will be fabricated and erected to achieve design intent.Yes (NET, MCN, R&R, REJ)
Product Data SheetsAction SubmittalManufacturer / SupplierVerifies catalog specifications, physical properties, electrical/hydraulic ratings, and finishes.Yes (NET, MCN, R&R, REJ)
Material SamplesAction SubmittalFabricator / QuarryVerifies color range, surface texture, veining, finish, and aesthetic properties.Yes (NET, MCN, R&R, REJ)
Field MockupsAction SubmittalGeneral ContractorEstablishes full-scale physical standard of quality, jointing, and workmanship on site.Yes (NET, MCN, R&R, REJ)
Soil Compaction TestsInformational SubmittalIndependent Testing AgencyDocuments field density compliance with ASTM compaction requirements; filed for record.No (Reviewed & Filed)
Concrete Cylinder BreaksInformational SubmittalIndependent Testing AgencyDocuments 7-day and 28-day compressive strength compliance with ASTM C39; filed for record.No (Reviewed & Filed)
Nursery Health CertsInformational SubmittalState Dept of AgricultureDocuments plant stock is free from agricultural pests and pathogens; filed for record.No (Reviewed & Filed)

6. Real-World Case Scenario: The Custom Corten Arbor Dimensions

Scenario: A landscape architect designs a custom weathering steel (Corten) pergola for a university courtyard. The contract drawings show general layout, footing locations 24 feet on-center, and structural member profiles. The steel fabrication subcontractor prepares detailed shop drawings. On the shop drawings, the drafter incorrectly dimensions the clear span between column base plates as 22'-6" instead of 24'-0". The General Contractor applies its review stamp without verifying the dimension against the foundation plan. The landscape architect reviews the shop drawing, notes that the steel member thickness and weld callouts conform to structural criteria, and stamps the drawing "No Exceptions Taken." The fabricator builds the arbor and delivers it to the site, where it is discovered that the columns do not align with the cast-in-place concrete piers. The General Contractor submits a change order for $18,500 to demolish and relocate the concrete footings, arguing that the landscape architect approved the 22'-6" dimension on the shop drawings.

Contractual Analysis & Resolution:

  1. Liability for Dimensions: Under AIA Document A201 Section 3.12.5 and Section 3.12.8, the General Contractor is contractually obligated to determine and verify all field measurements, construction criteria, and dimensions.
  2. Scope of Design Review: Under Section 4.2.7, the Landscape Architect's review stamp is strictly for checking conformance with the design concept. The review stamp does not constitute verification or approval of dimensions.
  3. Resolution: The Change Order claim is denied. The General Contractor bears sole legal and financial responsibility for the dimensional discrepancy and must modify the steel arbor or bear the cost of adjusting the foundations at no cost to the Owner.

7. Exam Traps & Pitfalls

  1. The "Approved Stamp Validates Dimensions" Trap: A common exam question tests whether an "Approved" stamp makes the designer liable for incorrect dimensions or quantities. It does not. Dimensional verification is the contractor's exclusive contractual responsibility.
  2. The Unstamped Submittal Trap: If presented with an exam scenario where a subcontractor sends shop drawings directly to the landscape architect, or the GC sends drawings without a review stamp, the only correct answer is to return them immediately unreviewed without action.
  3. The Informational Submittal Approval Trap: Exam questions may ask what action stamp the landscape architect should place on concrete cylinder break reports or soil compaction tests. The answer is that informational submittals do not receive approval action stamps; they are reviewed for compliance and filed for the project record.
  4. The Hidden Deviation Trap: Candidates frequently assume that if a designer approves a shop drawing containing a deviation, the owner is bound to accept it. Unless the contractor explicitly flagged the deviation in a separate written notice and the landscape architect gave written approval to that specific change, the contractor remains contractually obligated to provide what the Contract Documents originally specified.
Test Your Knowledge

A concrete paving subcontractor prepares shop drawings detailing expansion joint layouts, dowel basket alignments, and pour sequence diagrams for a commercial plaza. Before these shop drawings can be formally reviewed by the landscape architect, what contractual action is mandatory under AIA Document A201?

A
B
C
D
Test Your Knowledge

The landscape architect reviews a detailed shop drawing for a custom architectural steel arbor, marks it 'Approved as Noted,' and returns it to the general contractor. During subsequent field erection, the contractor discovers that the arbor's overall length is 6 inches too short to span between the concrete footings installed by another trade. Who bears primary legal and financial responsibility for the dimensional discrepancy?

A
B
C
D
Test Your Knowledge

A landscape architect is reviewing technical submittals for a large civic park development. Which of the following submittals is classified as an 'Informational Submittal' that is submitted for the record rather than requiring a formal approval action stamp from the design professional?

A
B
C
D
Test Your Knowledge

On a high-end institutional campus project, the specifications require a full-scale on-site mockup of an 8-foot-tall curved segmental retaining wall with integrated natural stone veneer and precast concrete coping. What is the primary administrative purpose and contractual rule governing this physical mockup?

A
B
C
D