8.2 Sand Cone Density Testing and Field Volumetric Verification (ASTM D1556)

Key Takeaways

  • ASTM D1556 is the standard referee test method for determining the in-place density and unit weight of soil using the sand-cone apparatus.
  • Calibrated Ottawa sand (typically 20-30 mesh) must be clean, dry, uniform, free-flowing, uncemented, and have a bulk density verified to within ±0.5%.
  • The cone constant (mass of sand required to fill the double cone funnel and base plate opening) must be accurately determined and deducted from total sand consumed.
  • ASTM D1556 Table 1 mandates minimum test hole volumes based on nominal maximum particle size, requiring 0.050 ft³ for 1/2-inch aggregate, 0.075 ft³ for 1-inch aggregate, and 0.100 ft³ for 2-inch aggregate.
  • External vibrations from idling rollers or nearby construction equipment during sand pouring will densify the sand in the test hole, causing severe underestimation of soil in-place density.
Last updated: September 2026

8.2 Sand Cone Density Testing and Field Volumetric Verification (ASTM D1556)

While nuclear density gauges provide rapid field readings, the Sand Cone Method, standardized under ASTM D1556 (Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method), serves as the definitive referee benchmark in geotechnical quality assurance. When disputes arise regarding nuclear gauge accuracy, when soil contains chemical constituents that distort nuclear readings, or when testing is conducted on projects prohibiting radioactive materials, the sand cone method provides direct, physical, volumetric measurement of in-place soil unit weight.

An ICC Soils Special Inspector must master the apparatus components, calibration physics, aggregate volume thresholds, and multi-step mass-volume calculations required by ASTM D1556.


Equipment and Apparatus Specifications

The sand-cone apparatus consists of precision-machined volumetric components engineered to deliver a consistent, uncompacted volume of calibrated sand into an excavated test hole.

graph TD
    subgraph SandConeAssembly["ASTM D1556 Sand Cone Apparatus"]
        JAR["1-Gallon Transparent Plastic or Metal Jar<br/>(Stores Calibrated Sand Supply)"]
        VALVE["Rotary Cylindrical Valve (1/2-inch Orifice)<br/>Controls Sand Flow Without Jamming"]
        TOP_CONE["Small Funnel Cone (Threaded to Jar)"]
        BOT_CONE["Large Funnel Cone (Flanged 60-degree Angle)<br/>Mates with Base Plate Opening"]
        BASE["Rigid Metal Base Plate (Flanged Center Hole)<br/>Secured to Soil Surface with Corner Anchor Pins"]

        JAR --- TOP_CONE
        TOP_CONE --- VALVE
        VALVE --- BOT_CONE
        BOT_CONE -.->|"Inverts Over"| BASE
    end

1. Sand-Cone Apparatus Components

  • Sand Jar: A rigid 1-gallon (approximately 4.0 L) transparent plastic or metal container capable of holding approximately 15 to 20 lbs of dry sand.
  • Double-Cone Assembly: A detachable metal double funnel with a 60-degree angle on the large funnel. The funnels are joined by a cylindrical metal valve with a 1/2-inch (12.7 mm) diameter orifice, featuring positive stops in the fully open and fully closed positions.
  • Base Plate: A rigid cast aluminum or steel plate, typically 12 inches by 12 inches (300 mm × 300 mm), with a flanged central opening measuring 6.5 inches (165 mm) in diameter matching the large cone funnel. Corner holes allow the plate to be securely pinned to the ground with 8- to 12-inch steel spikes.

2. Standard Ottawa Sand Requirements

ASTM D1556 Section 6 establishes strict criteria for the calibration sand:

  • Grading: Uniform, clean, dry, free-flowing sand meeting the particle size distribution of Standard Ottawa Sand, typically passing the No. 20 (850 µm) sieve and retained on the No. 30 (600 µm) sieve (or graded between No. 20 and No. 40).
  • Shape and Cleanliness: Grains must be sub-rounded to rounded and completely free of dust, silt, organic contaminants, or cementitious coatings. Rounded grains flow with minimal internal friction, ensuring consistent packing density.
  • Moisture Insensitivity: The sand must be dried in an oven and stored in sealed airtight containers. The bulk density must not change by more than 0.5% across normal atmospheric humidity fluctuations.

Laboratory and Pre-Test Calibration Protocols

Before conducting a field test, two essential calibration constants must be established in the laboratory: the Bulk Density of the Sand (ρ_sand) and the Cone Constant (M_c).

graph LR
    subgraph CalibrationFlow["ASTM D1556 Calibration Protocols"]
        direction TB
        CAL1["1. Calibrate Sand Bulk Density (ρ_sand)<br/>Fill container of known volume via funnel.<br/>ρ_sand = Mass / Volume (lb/cu ft)"]
        CAL2["2. Calibrate Cone Constant (M_c)<br/>Invert apparatus over flat glass plate.<br/>Open valve to fill lower cone and base plate.<br/>M_c = M_initial - M_final (lb or g)"]
        CAL1 --> CAL2
        CAL2 --> FIELD["Field Test Execution<br/>Excavate Hole -> Recover 100% Soil -> Pour Sand"]
    end

1. Determination of Sand Bulk Density (ρ_sand)

  1. A rigid calibration container of precisely known volume (such as a 1/10 cu ft or standard 1/30 cu ft Proctor compaction mold with known volume V_cal) is cleaned and weighed.
  2. The sand cone apparatus is filled with dry Ottawa sand, inverted over the calibration mold, and the valve opened fully to allow sand to free-fall from the standard cone height.
  3. When flow stops, the valve is closed, excess sand is struck off flat with a straightedge without shaking or vibrating the mold, and the mass of sand in the mold is determined (M_sand_cal).
  4. Bulk density is calculated: ρsand=Msand,cal/Vcal\rho_{sand} = M_{sand,cal} / V_{cal}
  5. Repeat the determination at least three times. The variations must not exceed ±0.5% of the mean.

2. Determination of the Cone Constant (M_c)

The cone constant (M_c) is the mass of sand required to fill the large lower funnel cone and the flanged recess of the base plate.

  1. Weigh the clean apparatus filled with sand to obtain the initial mass (M_1).
  2. Place the base plate on a clean, level, rigid horizontal surface (such as a thick glass plate or ground steel plate).
  3. Invert the sand cone apparatus, seat the cone rim into the base plate flange, and open the valve fully.
  4. Allow sand to flow under gravity until movement ceases completely. Close the valve.
  5. Re-weigh the apparatus with the remaining sand (M_2).
  6. The cone constant is calculated as: Mc=M1M2M_c = M_1 - M_2
  7. Repeat until three consecutive determinations agree within ±0.5% (or ±0.01 lb / 5 g).

Minimum Test Hole Volume Requirements

Excavating an undersized test hole introduces massive boundary void distortion, severely compromising density accuracy. ASTM D1556 Table 1 establishes mandatory minimum test hole volumes based on the maximum particle size of the soil being evaluated:

Maximum Nominal Particle SizeMinimum Test Hole Volume (cu ft)Minimum Test Hole Volume (cu cm)Minimum Moist Specimen Mass Required for Lab MoistureTypical Minimum Excavated Mass (at 120 pcf)
1/2 in (12.5 mm)0.050 cu ft1,415 cu cm100 g≈ 6.0 lb (2.7 kg)
1 in (25.0 mm)0.075 cu ft2,125 cu cm250 g≈ 9.0 lb (4.1 kg)
2 in (50.0 mm)0.100 cu ft2,830 cu cm500 g≈ 12.0 lb (5.4 kg)

[!IMPORTANT] If the soil contains coarse aggregate exceeding 1 inch, the inspector must dig a larger hole (minimum 0.075 cu ft or greater). Attempting to test coarse base material through an undersized 0.03 cu ft hole will cause individual large gravel particles along the perimeter to dominate the volume, producing invalid density results.


Field Test Procedure: Step-by-Step

graph TD
    STEP1["1. Site Preparation & Base Plate Seating<br/>Plane smooth horizontal surface; drive anchor pins through plate."] --> STEP2["2. Test Hole Excavation<br/>Chisel and scoop test hole through 6.5-in plate orifice.<br/>Maintain vertical walls, flat bottom, minimum volume."]
    STEP2 --> STEP3["3. Capture 100% of Soil & Seal<br/>Place all cuttings into moisture-proof bag/can.<br/>Weigh wet soil immediately (M_wet)."]
    STEP3 --> STEP4["4. Invert Sand Cone & Pour Sand<br/>Seat apparatus over base plate. Open valve fully.<br/>Gravity flow only - NO VIBRATIONS. Close valve."]
    STEP4 --> STEP5["5. Weigh Remaining Sand<br/>Compute net sand in hole, hole volume, and wet density."]
  1. Surface Preparation & Plate Seating: Prepare a flat, smooth, level horizontal area at least twice the diameter of the base plate. Remove all loose debris. Seat the base plate flat against the soil. Drive steel spikes through all four corner holes into the subgrade to ensure the plate cannot shift, rock, or lift during excavation.
  2. Precision Excavation: Excavate the test hole through the 6.5-inch center hole of the base plate using narrow digging chisels, pointed trowels, spoons, and soil augers.
    • Hole walls must be as vertical as possible with a flat bottom.
    • Avoid disturbing, gouging, or compressing the soil surrounding the hole perimeter.
    • Take extreme care not to leave loose soil slough inside the hole.
  3. Moisture Containment: Collect 100% of the excavated soil, gravel, and fines. Immediately place all excavated material into an airtight container or heavy-mil plastic sealable bag. Brush the flange rim clean so all dislodged particles enter the container. Seal immediately to prevent evaporative moisture loss. Weigh the wet soil immediately to obtain M_wet_soil.
  4. Sand Pouring:
    • Weigh the filled sand cone apparatus before testing to establish initial mass (M_before).
    • Invert the apparatus and seat the large cone firmly into the flanged opening of the base plate.
    • Open the 1/2-inch valve fully. Ottawa sand will free-fall into the test hole and funnel.
    • CRITICAL OPERATIONAL RULE: During sand flow, all construction equipment within 50 feet must cease operation. The inspector must stand completely motionless. Any ground vibration, engine idling, or walking near the hole will cause the sand to densify (vibratory compaction), causing excess sand to enter the hole, artificially inflating the calculated hole volume, and yielding a falsely low soil density.
    • When sand movement stops completely, close the valve securely.
  5. Post-Test Weighing: Carefully lift the apparatus and weigh the remaining sand and container to determine final mass (M_after). Brush surplus sand off the surface and salvage the clean sand from the hole if approved, or discard contaminated sand.

Mathematical Formulation and Step-by-Step Calculation

The following sequence outlines the exact mathematical reduction required to determine in-place dry density and percent relative compaction:

Equations:

  1. Total Sand Discharged (M_sand_total): Msand,total=MbeforeMafterM_{sand,total} = M_{before} - M_{after}
  2. Mass of Sand in Test Hole (M_sand_hole): Msand,hole=Msand,totalMcM_{sand,hole} = M_{sand,total} - M_c (where M_c is the pre-calibrated cone constant)
  3. Volume of Test Hole (V_hole): Vhole=Msand,hole/ρsandV_{hole} = M_{sand,hole} / \rho_{sand} (where ρ_sand is the calibrated bulk density of the Ottawa sand)
  4. In-Place Wet Density (ρ_wet): ρwet=Mwet,soil/Vhole\rho_{wet} = M_{wet,soil} / V_{hole}
  5. In-Place Dry Density (ρ_dry): ρdry=ρwet/(1+w/100)=(ρwet×100)/(100+w)\rho_{dry} = \rho_{wet} / (1 + w/100) = (\rho_{wet} \times 100) / (100 + w) (where w is the moisture content in percent determined by ASTM D2216)
  6. Percent Relative Compaction (RC): RC=(ρdry/ρmax,lab)×100%RC = (\rho_{dry} / \rho_{max,lab}) \times 100\% (where ρ_max,lab is the maximum dry density from ASTM D1557 or ASTM D698)

Fully Worked Field Example Problem

An inspector executes an ASTM D1556 sand-cone test on a compacted aggregate base course. Laboratory and field measurements are recorded as follows:

Given Data:

  • Calibrated Bulk Density of Ottawa Sand (ρ_sand): 98.4 lb/cu ft
  • Calibrated Cone Constant (M_c): 3.42 lb
  • Initial Mass of Apparatus + Sand (M_before): 19.85 lb
  • Final Mass of Apparatus + Sand (M_after): 10.15 lb
  • Mass of Wet Soil Recovered from Hole (M_wet_soil): 8.46 lb
  • Laboratory Moisture Content (w) via ASTM D2216: 7.8%
  • Lab Modified Proctor Maximum Dry Density (ρ_max): 132.5 lb/cu ft
  • Specification Requirement: Minimum 95.0% compaction within ±2.0% of optimum moisture.

Step-by-Step Solution:

StepCalculation ParameterMathematical OperationComputed Result
1Total Mass of Sand DischargedM_sand_total = 19.85 lb - 10.15 lb9.70 lb
2Mass of Sand Filling the Test HoleM_sand_hole = 9.70 lb - 3.42 lb6.28 lb
3Volume of the Test HoleV_hole = 6.28 lb / 98.4 lb/cu ft0.0638 cu ft
4In-Place Wet Densityρ_wet = 8.46 lb / 0.0638 cu ft132.60 lb/cu ft
5In-Place Dry Densityρ_dry = 132.60 / (1 + 7.8/100) = 132.60 / 1.078123.01 lb/cu ft
6Percent Relative CompactionRC = (123.01 / 132.5) × 100%92.8%

Compliance Evaluation:

  • Density: The achieved relative compaction of 92.8% fails to meet the specified minimum of 95.0%.
  • Inspector Action: Immediately inform the contractor's earthwork superintendent that the lift fails compaction. Document the test location (coordinates, stationing, lift elevation) and require scarification, re-compaction, and re-testing.
Test Your Knowledge

During an ASTM D1556 sand-cone test, a compactor drives past the test site while the sand is freely flowing from the jar into the excavated hole. How does this vibration affect the test results?

A
B
C
D
Test Your Knowledge

What is the purpose of the 'cone constant' (Mc) in ASTM D1556 sand cone testing, and how is it utilized in field calculations?

A
B
C
D
Test Your Knowledge

According to ASTM D1556 Table 1, what is the minimum required test hole volume when conducting a sand-cone density test on structural fill containing gravel with a maximum nominal particle size of 1.0 inch (25.0 mm)?

A
B
C
D