16.3 Flows, Loadings, Removal Efficiency & Solids Math
Key Takeaways
Hydraulic loading is Q/A (e.g., clarifier gpd/ft² or filter gpm/ft²).
Organic and solids loads use MGD × mg/L × 8.34 for lb/day.
% removal = (in − out)/in × 100 using matching concentration units.
Simple SRT ≈ solids inventory ÷ (WAS + effluent SS) lb/day.
Wet cake tons = dry mass ÷ (decimal % solids) ÷ 2,000 lb/ton.
16.3 Flows, Loadings, Removal Efficiency & Solids Math
Quick Answer: Hydraulic loading compares flow to area (gpd/ft² or similar). Organic loading uses the pounds formula on BOD (or COD): MGD × mg/L × 8.34. Percent removal is . Solids mass balances use the same 8.34 factor for WAS, inventory, and simple SRT/sludge age. Wet tons of cake scale dry solids by cake percent solids.
Wastewater Class C exams lean hard on loadings and solids. Water treatment operators still need removal efficiency and filter hydraulic loading. The algebra is shared.
1. Hydraulic Loading
Hydraulic loading rate (HLR) expresses how much flow is applied per unit area (or sometimes per unit volume for towers).
| Process (examples) | Typical expression | Operator use |
|---|---|---|
| Sedimentation tank | gpd/ft² | Overflow rate |
| Trickling filter | gpd/ft² (media surface plan) | Wetting rate |
| Sand filter | gpm/ft² | Filtration rate |
| Lagoon | lb BOD/acre·day is organic; hydraulic is inches/day etc. | Design checks |
Worked Example 1 — Clarifier Overflow Rate
Secondary clarifier diameter 60 ft, flow 2.0 MGD.
Area:
HLR (gpd/ft²): 2.0 MGD = 2,000,000 gpd.
Worked Example 2 — Filter Rate
Filter area 200 ft², flow 600 gpm.
2. Organic Loading (lb BOD/day and Related)
Same form works for TSS, COD, nitrogen, etc.:
Volumetric organic loading (e.g., aeration tank):
Worked Example 3 — Plant BOD Load
Influent BOD 220 mg/L, flow 1.5 MGD.
Worked Example 4 — Aeration Tank Loading
Same 2,752 lb BOD/day into aeration volume 120,000 ft³.
(Because 120,000 / 1,000 = 120 “thousands.”)
3. Percent Removal Efficiency
| Rule | Meaning |
|---|---|
| Use same units in and out | Both mg/L BOD, both mg/L TSS, etc. |
| Do not subtract loads unless asked | Concentration form is standard for “% removal” |
| 95% removal of 200 mg/L → 10 mg/L out |
Worked Example 5 — BOD Removal
Influent BOD 220 mg/L, effluent BOD 12 mg/L.
Worked Example 6 — Required Effluent from Target Removal
Influent TSS 180 mg/L, need 90% removal. Max effluent TSS:
Worked Example 7 — Load Removed
Flow 2.0 MGD, influent BOD 200 mg/L, effluent 20 mg/L.
Influent load: lb/day
Effluent load: lb/day
Removed: lb/day
% removal: (matches concentration %)
4. Solids Math — WAS, Inventory, Simple SRT
Mass of solids in a flow:
Mass of solids in a tank (inventory):
(Use MG of aeration + clarifier inventory only if the problem defines system volume that way.)
Simple sludge age / SRT (operator exam form):
Solids leaving ≈ WAS lb/day + effluent SS lb/day (if significant). Many basic problems use WAS only when effluent SS is neglected by the stem.
Worked Example 8 — WAS Solids
Waste 0.05 MGD of sludge at 8,000 mg/L SS.
Worked Example 9 — Simple SRT
Aeration tank volume 0.40 MG, MLSS 2,500 mg/L. WAS solids 2,000 lb/day (ignore effluent SS).
Inventory:
SRT:
Worked Example 10 — Include Effluent Solids
Same inventory 8,340 lb. WAS 2,000 lb/day. Effluent flow 1.5 MGD at 10 mg/L SS.
5. Wet Tons of Cake (Dewatering)
Dewatered cake is reported as % total solids (wet basis).
Also: 1 ton = 2,000 lb.
Worked Example 11 — Wet Tons from Dry Solids
A belt press produces 1,200 lb/day dry solids as 20% cake.
Worked Example 12 — Hauling Check
Plant wastes 3,336 lb/day WAS solids (from Example 8). After digestion/thickening assume 80% of that mass is dewatered at 18% cake (simplified exam chain).
Dry to press ≈ lb/day dry.
6. Formula Sheet for This Section
| Quantity | Formula |
|---|---|
| Hydraulic loading | (Q / A) |
| lb/day (BOD, SS, etc.) | MGD × mg/L × 8.34 |
| % removal | |
| Tank solids inventory | MG × mg/L × 8.34 |
| WAS lb/day | WAS MGD × SS mg/L × 8.34 |
| Simple SRT | inventory lb ÷ (WAS + effluent SS) lb/day |
| Wet cake mass | dry mass ÷ decimal % solids |
7. Exam Strategy — Loadings & Solids
- If the stem gives mg/L and MGD, reach for 8.34 immediately.
- % removal almost always uses concentrations, not a mix of load and concentration.
- SRT denominators: read carefully whether effluent SS is included.
- Cake problems: % solids is wet basis unless stated otherwise—wet tons > dry tons.
- Overflow rate: convert MGD → gpd before dividing by ft².
Florida wastewater items often combine a loading question with a removal or WAS follow-on in separate stems—each still uses the same pounds engine.
Influent BOD is 250 mg/L at 2.0 MGD. What is the organic loading in lb BOD/day? (Use × 8.34.)
4,170 lb/day
417 lb/day
2,085 lb/day
8,340 lb/day
Influent TSS = 160 mg/L and effluent TSS = 12 mg/L. What is the percent removal?
7.5%
88.0%
98.0%
92.5%
WAS flow is 0.04 MGD at 10,000 mg/L solids. How many lb/day of solids are wasted?
334 lb/day
3,336 lb/day
1,668 lb/day
33,360 lb/day
A dewatering process yields 2,000 lb/day of dry solids as cake at 25% total solids. How many wet tons of cake are produced per day?
0.5 wet tons/day
1.0 wet tons/day
4.0 wet tons/day
8.0 wet tons/day
Sections you finish are checked off in the contents.