Engineering Economics: Time Value of Money

Key Takeaways

  • P = F/(1+i)ⁿ discounts future amounts.

  • AW spreads PW over n periods.

  • NPV > 0 supports acceptance.

  • Sunk costs are excluded.

  • Use consistent nominal or real rates.

Last updated: July 2026

Quick Answer: Use present worth (PW) and annual worth (AW) with Handbook factors. NPV > 0 accepts independent projects. Ignore sunk costs in replacement analysis.

Single Payment Factors

P=F/(1+i)nF=P(1+i)nP = F/(1+i)^n \quad F = P(1+i)^n

Example: $500,000 in 10 years at 6% → P = 500,000/1.791 ≈ $279,200 today.

Uniform Series

Capital recovery: A=P×(A/P,i,n)A = P \times (A/P, i, n). Sinking fund: A=F×(A/F,i,n)A = F \times (A/F, i, n).

Example: $200,000 scrubber, 15 yr, 8% → A ≈ $23,360/yr capital recovery.

NPV and Benefit-Cost

NPV=∑Bt−Ct(1+i)tNPV = \sum \frac{B_t - C_t}{(1+i)^t}

Accept if NPV > 0 or B/C > 1 (when benefits and costs separated).

Effective Annual Rate

When compounding is m times per year: ie=(1+i/m)m−1i_e = (1 + i/m)^m - 1. Nominal 12% compounded monthly: ie=(1.01)12−1=12.68%i_e = (1.01)^{12} - 1 = 12.68\%.

Gradient and Geometric Series

Some environmental costs grow each year (electricity, chemical prices). Present worth of gradient ( G ):

P=G×(1+i)n−1−nii(1+i)nP = G \times \frac{(1+i)^n - 1 - ni}{i(1+i)^n}

Handbook supplies ((P/G, i, n)) factors — locate before exam day.

Worked Example — UV vs. Chlorine Capital

UV system: P = $400,000, annual O&M $25,000, life 15 yr, MARR 7%.

Chlorine: P = $120,000, annual O&M $55,000 (chemicals + labor), life 15 yr.

Find PW of costs for each (cost-only comparison):

PWUV=400,000+25,000×(P/A,7%,15)PW_{UV} = 400{,}000 + 25{,}000 \times (P/A, 7\%, 15) PWCl=120,000+55,000×(P/A,7%,15)PW_{Cl} = 120{,}000 + 55{,}000 \times (P/A, 7\%, 15)

Using (P/A, 7%, 15) ≈ 9.108: PW_UV ≈ 627,700; PW_Cl ≈ 620,940 — chlorine slightly lower on cost alone; add risk, DBPs, safety qualitatively in essay-style stems.

IRR Concept

Internal rate of return is the rate where NPV = 0. If IRR > MARR, project is attractive. FE may ask you to compare two rates without full IRR calculation — use bracketing or calculator IRR function.

Bond and Loan Equivalence

Equal loan payments use capital recovery factor. Bond interest-only with balloon principal uses different cash flow pattern — read stem carefully.

Sinking Fund for Closure

Landfill post-closure care $2M in 30 years, i = 5%:

A=2,000,000×(A/F,5%,30)≈2,000,000×0.0151=$30,200/yrA = 2{,}000{,}000 \times (A/F, 5\%, 30) \approx 2{,}000{,}000 \times 0.0151 = \$30{,}200/\text{yr}

Escrow this annual deposit for regulatory financial assurance.

Time Value of Money — FE Formulas in Practice

FactorNotationUse
Single payment compound(F/P,i,n)(F/P,i,n)Future of present sum
Present worth(P/F,i,n)(P/F,i,n)Discount future sum
Uniform series PW(P/A,i,n)(P/A,i,n)Capitalize annual O&M
Capital recovery(A/P,i,n)(A/P,i,n)Annualize capital cost
Sinking fund(A/F,i,n)(A/F,i,n)Annual deposit to future goal

Worked Example

A UV disinfection upgrade costs $400,000 now and saves $55,000/year in chemicals for 12 years at MARR = 8%.

PW=−400,000+55,000(P/A,8%,12)PW = -400{,}000 + 55{,}000(P/A,8\%,12)

(P/A,8%,12)=(1.08)12−10.08(1.08)12≈7.536(P/A,8\%,12) = \frac{(1.08)^{12}-1}{0.08(1.08)^{12}} \approx 7.536

PW≈−400,000+414,500=+$14,500PW \approx -400{,}000 + 414{,}500 = +\text{\textdollar}14{,}500 → accept at 8% MARR.

On the Exam: Match cash-flow diagram to the correct factor; mixing (P/A)(P/A) with (A/P)(A/P) is the most common arithmetic trap.

Time Value of Money — FE Formulas in Practice

FactorNotationUse
Single payment compound(F/P,i,n)(F/P,i,n)Future of present sum
Present worth(P/F,i,n)(P/F,i,n)Discount future sum
Uniform series PW(P/A,i,n)(P/A,i,n)Capitalize annual O&M
Capital recovery(A/P,i,n)(A/P,i,n)Annualize capital cost
Sinking fund(A/F,i,n)(A/F,i,n)Annual deposit to future goal

Worked Example

A UV disinfection upgrade costs $400,000 now and saves $55,000/year in chemicals for 12 years at MARR = 8%.

PW=−400,000+55,000(P/A,8%,12)PW = -400{,}000 + 55{,}000(P/A,8\%,12)

(P/A,8%,12)=(1.08)12−10.08(1.08)12≈7.536(P/A,8\%,12) = \frac{(1.08)^{12}-1}{0.08(1.08)^{12}} \approx 7.536

PW≈−400,000+414,500=+$14,500PW \approx -400{,}000 + 414{,}500 = +\text{\textdollar}14{,}500 → accept at 8% MARR.

On the Exam: Match cash-flow diagram to the correct factor; mixing (P/A)(P/A) with (A/P)(A/P) is the most common arithmetic trap.

Time Value of Money — FE Formulas in Practice

FactorNotationUse
Single payment compound(F/P,i,n)(F/P,i,n)Future of present sum
Present worth(P/F,i,n)(P/F,i,n)Discount future sum
Uniform series PW(P/A,i,n)(P/A,i,n)Capitalize annual O&M
Capital recovery(A/P,i,n)(A/P,i,n)Annualize capital cost
Sinking fund(A/F,i,n)(A/F,i,n)Annual deposit to future goal

Worked Example

A UV disinfection upgrade costs $400,000 now and saves $55,000/year in chemicals for 12 years at MARR = 8%.

PW=−400,000+55,000(P/A,8%,12)PW = -400{,}000 + 55{,}000(P/A,8\%,12)

(P/A,8%,12)=(1.08)12−10.08(1.08)12≈7.536(P/A,8\%,12) = \frac{(1.08)^{12}-1}{0.08(1.08)^{12}} \approx 7.536

PW≈−400,000+414,500=+$14,500PW \approx -400{,}000 + 414{,}500 = +\text{\textdollar}14{,}500 → accept at 8% MARR.

On the Exam: Match cash-flow diagram to the correct factor; mixing (P/A)(P/A) with (A/P)(A/P) is the most common arithmetic trap.

Additional review point: verify assumptions, boundary conditions, and whether the problem is steady-state or transient before selecting an answer.

Additional review point: verify assumptions, boundary conditions, and whether the problem is steady-state or transient before selecting an answer.

Additional review point: verify assumptions, boundary conditions, and whether the problem is steady-state or transient before selecting an answer.

Test Your Knowledge

$100,000 in 8 years at 5% present worth ≈

A

$67,680

B

$100,000

C

$147,746

D

$62,500

Sections you finish are checked off in the contents.