5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406)
Key Takeaways
- Contracting Officers must establish written Pre-Negotiation Objectives under FAR 15.406-1 before conducting price or contract negotiations.
- The Pre-Negotiation Objectives Memorandum (PNOM) documents the agency's negotiation position on price, cost elements, and profit objectives.
- The Price Negotiation Memorandum (PNM) required by FAR 15.406-3 serves as the mandatory post-negotiation document recording the principal elements of the negotiated agreement.
- The Weighted Guidelines Method (FAR 15.404-4) is the structured approach used to analyze profit or fee based on contractor effort, risk, and socioeconomic objectives.
- During negotiations, Contracting Officers must maintain common cut-off dates for Final Proposal Revisions (FPRs) and strictly avoid prohibited negotiation practices.
5.5 Pre-Negotiation Objectives & Competitive Negotiations (FAR 15.406)
Negotiation is a process of bargained exchange between the Government and an offeror designed to reach mutual agreement on contract price, terms, and conditions. Under FAR 15.406-1, Contracting Officers (COs) must establish written pre-negotiation objectives prior to conducting negotiations on any contract or modification requiring cost or price analysis.
Pre-Negotiation Objectives & The PNOM (FAR 15.406-1)
Pre-negotiation objectives establish the Government's official target position, acceptable range, and negotiation boundaries. They ensure that government negotiators enter discussions with a clear strategy supported by price or cost analysis.
The Pre-Negotiation Objectives Memorandum (PNOM)
The CO documents pre-negotiation objectives in a formal Pre-Negotiation Objectives Memorandum (PNOM). The PNOM must detail:
- Technical & Price Assessment: Analysis of proposed direct labor, materials, subcontracts, and indirect rate pools.
- Pricing Position: Government target price, minimum acceptable position, and ceiling price.
- Profit / Fee Objective: Calculation of fair profit using structured profit methodologies.
- Advisory Audit Input: Summary of recommendations provided by DCAA auditors, ACOs, or technical specialists, noting any points of agreement or disagreement.
[Proposal Analysis] ➔ [DCAA / ACO Input] ➔ [Draft PNOM Target & Minimum] ➔ [CO Approval] ➔ [Enter Negotiations]
Structured Profit Analysis & The Weighted Guidelines Method (FAR 15.404-4)
FAR 15.404-4 mandates that Contracting Officers use a structured approach for determining profit or fee objectives on negotiated contracts where cost analysis is performed.
Statutory Fee Limitations (10 U.S.C. 3861 & 41 U.S.C. 3905)
Federal law imposes strict statutory caps on fee percentages based on contract type (calculated as a percentage of estimated cost, excluding fee):
- Experimental, Developmental, or Research Contracts: Fee cannot exceed 15% of estimated cost.
- Architect-Engineer (A-E) Services: Total fee for A-E services for production of designs, plans, and drawings cannot exceed 6% of estimated construction cost.
- All Other Cost-Plus-Fixed-Fee Contracts: Fee cannot exceed 10% of estimated cost.
The Weighted Guidelines Method
Agencies (such as DoD under DFARS 215.404-71) use the Weighted Guidelines Method to establish profit objectives based on four core evaluation factors:
| Weighted Guidelines Factor | Scope & Weight Evaluation |
|---|---|
| Contractor Effort | Direct labor complexity, material management, subcontractor oversight, and overhead allocation. |
| Contract Performance Risk | Financial risk assumed under contract type (Cost-Plus = low risk; Firm-Fixed-Price = high risk). |
| Federal Socioeconomic Programs | Preference points awarded for exceeding small business subcontracting goals. |
| Capital Investments | Amount of private contractor capital invested in facilities, equipment, and technology. |
Executing Competitive Negotiations & Bargained Exchanges
When conducting negotiations, the Contracting Officer leads the acquisition team to achieve contract terms that represent best value to the Government.
Bargaining Techniques & Best Practices
- Objective Bargaining: Focusing on cost line items supported by empirical audit data or market indices.
- Trade-Offs: Exchanging concessions on performance schedules or testing protocols for price reductions.
- Avoiding Unfair Tactics: Government negotiators must maintain professional standards, avoiding arbitrary price cut demands unsupported by cost/price analysis.
The Price Negotiation Memorandum (PNM) (FAR 15.406-3)
Upon completion of negotiations, the Contracting Officer must document the results in a written Price Negotiation Memorandum (PNM). The PNM is the single most critical legal document in the pricing file, recording the basis for finding the negotiated price fair and reasonable.
Mandatory Elements of the PNM (FAR 15.406-3(a))
- Purpose of Negotiation: Summary of acquisition type, solicitation number, and contract action.
- Principal Participants: Names, titles, and organizations of all government and contractor negotiators.
- Current Cost or Pricing Data Certificate: Reference to the signed TINA Certificate of Current Cost or Pricing Data (if applicable).
- Summary of Proposed, Pre-Negotiation, and Final Prices: Comprehensive line-item comparison table showing proposed, PNOM target, and final agreed price.
- Cost Element Discrepancies: Detailed explanation of principal differences between proposed costs, government objective, and final negotiated settlement.
- Impact of Advisory Audits: Summary of DCAA/ACO audit findings and explanation of how audit recommendations were resolved.
- Fair and Reasonable Determination: Explicit legal statement detailing why the final negotiated price is fair and reasonable.
DCAA Advisory Audit Coordination & Resolution Protocols
Prior to finalizing the Pre-Negotiation Objectives Memorandum (PNOM), the Contracting Officer must coordinate with the Defense Contract Audit Agency (DCAA) or civilian contract audit office whenever cost analysis is required. The DCAA audit report provides advisory recommendations regarding questioned direct labor costs, unallowable overhead expenses (under FAR Subpart 31.2), and proposed subcontract pricing. If the CO chooses to depart from DCAA audit recommendations—such as accepting a contractor proposed overhead rate that DCAA questioned—the CO must explicitly document the legal and technical justification for the disposition in both the PNOM and the final Price Negotiation Memorandum (PNM) pursuant to FAR 15.406-3(a)(8).
Step-by-Step Weighted Guidelines Profit Evaluation
When applying the Weighted Guidelines Method (FAR 15.404-4 and DFARS 215.404-71), the CO assigns numerical weights to specific cost risk factors. For example, direct labor effort receives a higher profit weight (e.g., 9% to 12%) than routine material pass-through costs (e.g., 1% to 4%), encouraging contractors to perform high-value technical labor in-house. Contract performance risk assigns a 0% to 1% profit weight for cost-plus-fixed-fee contracts, but increases to 4% to 6% for firm-fixed-price contracts, rewarding contractors for assuming full financial cost risk.
What is the primary purpose of preparing a Pre-Negotiation Objectives Memorandum (PNOM) under FAR 15.406-1?
Under statutory fee caps (FAR 15.404-4(c)(4)), what is the maximum fee allowed for a Cost-Plus-Fixed-Fee (CPFF) contract performing general services?
Which evaluation factor under the Weighted Guidelines Method (FAR 15.404-4) provides higher profit objective percentages to contractors accepting firm-fixed-price contracts over cost-reimbursement contracts?
What mandatory documentation must the Contracting Officer prepare upon completing price negotiations under FAR 15.406-3?