9.3 Financial Reporting: Statements, Accounting Methods, and Key Ratios

Key Takeaways

  • The balance sheet is a snapshot at a point in time built on assets equals liabilities plus owner's equity; the income statement covers a period and ends in net profit; the cash flow statement reconciles the two by showing where money actually moved.
  • Percentage-of-completion accounting recognizes revenue as the work is performed, usually by the cost-to-cost method, and is the standard for contractors with contracts spanning reporting periods.
  • Underbillings, shown as costs and estimated earnings in excess of billings, mean the contractor has performed work it has not yet invoiced and is financing the customer.
  • Overbillings, shown as billings in excess of costs and estimated earnings, are a liability, not profit, because the contractor has been paid for work it still owes.
  • Depreciation spreads the cost of equipment over its useful life; straight-line divides cost less salvage by the years of life, while accelerated methods and the Section 179 election move the deduction forward.
Last updated: September 2026

Financial Reporting: Statements, Accounting Methods, and Key Ratios

Quick Answer: Three statements answer three different questions. The balance sheet is a snapshot — $\text{Assets} = \text{Liabilities} + \text{Owner's Equity}$. The income statement covers a period and ends in net profit. The cash flow statement reconciles them by tracking where money actually moved. For a contractor, add a fourth: the work-in-progress (WIP) schedule, which exposes underbillings (you performed work you have not billed — you are financing the customer) and overbillings (you were paid for work you still owe — a liability, not profit). Contracts spanning reporting periods are normally reported on percentage of completion, usually measured cost-to-cost.


1. The Balance Sheet

Assets=Liabilities+Owner’s Equity\text{Assets} = \text{Liabilities} + \text{Owner's Equity}

AssetsLiabilities and Equity
Current: cash, accounts receivable, retention receivable, inventory, costs in excess of billings, prepaid insuranceCurrent: accounts payable, accrued payroll and payroll taxes, billings in excess of costs, current portion of notes
Fixed: trucks, trailers, compressors, lifts, tools, less accumulated depreciationLong-term: equipment notes, vehicle loans, long-term debt
Other: deposits, goodwillEquity: paid-in capital plus retained earnings

Retention receivable deserves its own line. It is an asset you cannot spend and often will not see for months.


2. The Income Statement

LineMeaning
Revenue (contract income)Recognized under the chosen accounting method
− Direct job costsLabor burdened, material, subcontracts, equipment, other direct
= Gross profitThe number that must cover overhead
− General and administrative expenseOffice, admin salaries, marketing, insurance not charged to jobs, depreciation on general-use assets, licenses
= Operating profit
± Other income and expenseInterest, gain or loss on equipment sales
= Net profit before tax

The classification rule that gets tested: a cost traceable to a specific project is a direct job cost; a cost of being in business generally is G&A. Depreciation on a crane used on jobs is a direct or equipment cost; depreciation on a car used generally by the sales staff is general and administrative.


3. The Cash Flow Statement

Three sections, and the first one is where contractors learn something:

  • Operating activities — net profit adjusted for non-cash items (depreciation) and for changes in receivables, payables, and billings. A profitable company with exploding receivables shows negative operating cash flow, which is the early warning of the cash crunch described in Section 9.1.
  • Investing activities — equipment and vehicle purchases and sales.
  • Financing activities — borrowing, repayment, owner contributions, and distributions.

4. Accounting Methods

MethodRevenue recognizedTypical use
CashWhen cash is received; expenses when paidVery small contractors; simple but distorts any period with heavy receivables
AccrualWhen earned; expenses when incurredThe general business standard
Completed contractEntirely at completionShort-duration contracts; defers both revenue and cost
Percentage of completionProgressively as work is performedThe contractor standard for contracts spanning reporting periods

Cost-to-Cost Percentage of Completion

Percent Complete=Costs Incurred to DateTotal Estimated Cost\text{Percent Complete} = \frac{\text{Costs Incurred to Date}}{\text{Total Estimated Cost}}

Revenue Earned to Date=Percent Complete×Total Contract Price\text{Revenue Earned to Date} = \text{Percent Complete} \times \text{Total Contract Price}

Worked example. A $400,000 commercial reroof with a total estimated cost of $320,000 has incurred $208,000 of cost to date.

Percent complete=208,000320,000=65%\text{Percent complete} = \frac{208{,}000}{320{,}000} = 65\% Revenue earned=0.65×400,000=$260,000\text{Revenue earned} = 0.65 \times 400{,}000 = \$260{,}000

If the contractor has billed $235,000, it has an underbilling of $25,000: work performed but not invoiced, reported as costs and estimated earnings in excess of billings, an asset — and a sign the billing process is lagging production.

If instead it had billed $290,000, it would have an overbilling of $30,000: billings in excess of costs and estimated earnings, a liability. Overbillings feel like cash in the bank and are not — the contractor still owes the work. Spending overbillings on overhead is a classic route to a failed job and a failed company.


5. Depreciation

Depreciation allocates the cost of a long-lived asset across the periods it serves, matching cost to the revenue it helps produce.

Straight line:

Annual Depreciation=CostSalvage ValueUseful Life in Years\text{Annual Depreciation} = \frac{\text{Cost} - \text{Salvage Value}}{\text{Useful Life in Years}}

A $54,000 roofing truck with a $9,000 salvage value and a 5-year life depreciates $(54{,}000 - 9{,}000) \div 5 = $9{,}000$ per year.

Accelerated methods (declining balance, sum-of-the-years'-digits) take more depreciation early, matching the heavier early productivity and repair profile of construction equipment. The federal Section 179 election and bonus depreciation let a contractor expense qualifying equipment in the year placed in service rather than spreading it — a tax timing decision, not an accounting-principle decision, and one to make with a CPA.

Depreciation is a non-cash expense. It reduces reported profit without reducing cash, which is why the cash flow statement adds it back.


6. The Ratios a Lender or Surety Reads

RatioFormulaWhat it tells them
Current ratioCurrent assets ÷ current liabilitiesShort-term solvency; below 1.0 is a red flag
Quick ratio(Cash + receivables) ÷ current liabilitiesSolvency without relying on inventory or unbilled cost
Debt to equityTotal liabilities ÷ owner's equityLeverage; high ratios limit bonding capacity
Gross margin %Gross profit ÷ revenuePricing and production performance
Net margin %Net profit ÷ revenueWhether overhead is sized to the volume
Working capital turnoverRevenue ÷ working capitalWhether volume has outrun the capital supporting it
Return on equityNet profit ÷ owner's equityWhether the owner's capital is earning its keep

A surety underwriting a payment and performance bond for a public works roofing project will look hardest at working capital, the debt-to-equity ratio, the WIP schedule, and whether the contractor's overbillings are funding operations.


7. Keeping Books a Third Party Can Read

Use a construction chart of accounts that separates direct job cost from G&A. Reconcile bank and credit card accounts monthly. Close the month within about two weeks and produce a WIP schedule with it. Have a CPA familiar with construction prepare at least an annual compiled or reviewed statement — CSLB, sureties, and lenders all want statements someone outside the company stands behind. And retain records: injury records five years, payroll records three years, and tax records generally at least four years after the return is filed.

Loading diagram...
How the Statements Connect
Test Your Knowledge

A contractor has a $400,000 contract with total estimated costs of $320,000 and has incurred $208,000 of cost to date. Using cost-to-cost percentage of completion, how much revenue has been earned?

A
B
C
D
Test Your Knowledge

On the same contract, the contractor has billed the owner $290,000 while $260,000 of revenue has been earned. How is the $30,000 difference reported and what does it mean?

A
B
C
D
Test Your Knowledge

A roofing contractor buys a $54,000 service truck with an estimated salvage value of $9,000 and a five-year useful life. What is the annual straight-line depreciation?

A
B
C
D