11.2 Protocol Submission, Approval & Amendment Processes
Key Takeaways
- ICH E6(R3) Annex 1 section 1.4.6 requires that no participant be enrolled before the IRB/IEC issues its documented approval or favourable opinion of the trial.
- Section 1.4.7 prohibits initiating any deviation from or change to the protocol without prior documented IRB/IEC approval of an appropriate amendment, with two narrow exceptions.
- The two exceptions are changes necessary to eliminate immediate hazards to participants, and changes involving only logistical or administrative aspects where regulatory requirements allow.
- Where a deviation is made to eliminate an immediate hazard, the investigator informs the sponsor promptly and reports the hazard, the change made and any proposed amendment to the IRB/IEC and regulatory authorities.
- In ICH E6(R3) the term "protocol" refers to the protocol and its amendments, and a protocol amendment is defined simply as a documented description of a change to a protocol.
Protocol Submission, Approval & Amendment Processes
Quick Reference: In the ICH E6(R3) glossary, "the term 'protocol' refers to protocol and protocol amendments", and a protocol amendment is "a documented description of a change(s) to a protocol." There is no such thing as an informal amendment. If the change is not documented and approved, it is not an amendment — it is a deviation.
Why this is tested
The ACRP-CP Exam Content Outline lists 2G, "Protocol submission, approval, and amendment processes" in Domain 2, and the task statements include "Coordinate protocol and/or protocol amendments through appropriate approval processes (e.g., IRB/IEC, sponsor, regulatory authority)" and "Implement the administrative and/or clinical tasks for protocol amendments."
Part 1 — Getting to first enrolment
Two approval streams run in parallel and both must complete before anyone is enrolled.
SPONSOR develops protocol (Appendix B contents)
│
┌───────────────┴────────────────┐
│ │
REGULATORY STREAM ETHICS STREAM
Annex 1 §3.8.1 Annex 1 §1 and §3.8.2
Sponsor (or sponsor and Submission by investigator/
investigator) submits any institution or sponsor per
required application to the applicable requirements
appropriate authority for
review, acceptance and/or IRB/IEC review of protocol,
permission to begin ICF, recruitment material,
IB, investigator qualifications
│ │
Permission / acceptance Documented approval or
to begin the trial favourable opinion
└───────────────┬────────────────┘
│
Both complete + contract executed + site greenlight
│
FIRST PARTICIPANT ENROLLED
Annex 1 section 1.4.6 is categorical: the IRB/IEC must specify "that no participant should be enrolled in a trial before the IRB/IEC issues its documented approval/favourable opinion of the trial."
Note the word documented. A chair's verbal assurance, an email saying "it went through", or minutes not yet issued are not approval. The site holds a dated approval letter identifying the exact protocol version and the exact consent form version.
What the IRB/IEC reviews
- The protocol and any amendments
- The informed consent form and any assent documents, in the languages to be used
- Recruitment materials — advertisements, scripts, screening questionnaires
- The Investigator's Brochure or equivalent product information
- Investigator qualifications, typically the current curriculum vitae
- Participant payment and reimbursement arrangements
- Any participant-facing materials such as diaries and instruction sheets
- Information on funding sources and conflicts of interest
Version control is the site's job
Every approved document has a version number and a date. The consent form in the drawer must be the version named in the approval letter. Site staff should be able to answer, without hesitation, which protocol version is currently in force, which consent version each participant signed, and when each was approved.
Part 2 — Amendments
The default rule and its two exceptions
Annex 1 section 1.4.7 requires the IRB/IEC to specify "that no deviations from or changes to the protocol should be initiated without prior documented IRB/IEC approval/favourable opinion of an appropriate protocol amendment except when necessary to eliminate immediate hazards to the participants or, in accordance with applicable regulatory requirements, when the change(s) involves only logistical or administrative aspects of the trial."
Read as a decision:
| Situation | May you act before approval? |
|---|---|
| Ordinary change of any kind | No. Prior documented approval of an amendment is required |
| Change necessary to eliminate an immediate hazard to participants | Yes — act first, then report |
| Change involving only logistical or administrative aspects, where regulatory requirements permit | Yes, per applicable requirements |
Exam Watchout: The immediate-hazard exception is narrow and is about hazard, not inconvenience, recruitment pressure or operational difficulty. A participant developing a dangerous laboratory abnormality who needs a dose held outside the protocol's rules is an immediate hazard. A site that cannot recruit under the current criteria is not.
The immediate-hazard pathway
Annex 1 section 2.5.4: the investigator "should follow the protocol and deviate only where necessary to eliminate an immediate hazard(s) to trial participants. In case of deviations undertaken to eliminate immediate hazard to trial participants, the investigator should inform the sponsor promptly."
Annex 1 section 2.5.5: the investigator "should report information on the immediate hazard, the implemented change and the subsequent proposed protocol amendment, if any, to the IRB/IEC and, where applicable, regulatory authorities."
Immediate hazard identified
│
1. ACT to protect the participant — do not wait for approval
│
2. DOCUMENT in the source record: the hazard, what was done, the clinical rationale
│
3. INFORM THE SPONSOR PROMPTLY (§2.5.4)
│
4. REPORT to the IRB/IEC and, where applicable, regulatory authorities:
the hazard · the change implemented · the proposed amendment, if any (§2.5.5)
│
5. AMEND the protocol if the change needs to become permanent
Substantial versus administrative changes
| Type | Typical content | Route |
|---|---|---|
| Substantial — affects participant safety, rights or well-being, or the scientific value of the trial | New or changed eligibility criteria; dose, schedule or route changes; new procedures; changed primary endpoint; new safety monitoring; sample size change; extended duration | Full IRB/IEC review; usually regulatory notification/submission; consent form usually revised; often registry update |
| Administrative / logistical | Typographical corrections; updated sponsor contact details; change of monitor; formatting; corrected page numbering | Notification or expedited handling per the IRB/IEC's own procedures |
Annex 1 section 1.4.5 permits the IRB/IEC to provide "expedited review and approval/favourable opinion of minor change(s) in ongoing trials" that already hold its approval, in accordance with applicable regulatory requirements. The IRB/IEC decides whether a change is minor — the sponsor's or site's label does not bind it.
Design out the need for amendments
Appendix B makes a point worth carrying into practice: "Building adaptability into the protocol, for example, by including acceptable ranges for specific protocol provisions, can reduce the number of deviations or in some instances the requirement for a protocol amendment. Such adaptability should not adversely affect participant safety or the scientific validity of the trial."
A protocol that specifies "day 28" generates deviations; one that specifies "day 28 ± 3 days" does not, without any loss of scientific integrity. This is Principle 8 — clear, concise and operationally feasible — applied at the drafting stage.
Part 3 — The amendment cascade
Approving an amendment is the beginning of the work, not the end. Each of the following must be handled and evidenced:
| Task | Detail |
|---|---|
| Regulatory submission or notification | Where the change requires it under applicable requirements |
| IRB/IEC approval | Dated, identifying the new protocol version |
| Consent form revision | New version approved before use |
| Re-consent decision | Do currently enrolled participants need to be re-consented, and by when? Ongoing participants affected by a new risk or procedure normally must be |
| Registry update | Where the amendment changes design, endpoints, eligibility or duration |
| Staff retraining | Documented training on the new version, filed as an essential record |
| System updates | eCRF, edit checks, IRT, laboratory manual, source worksheets — Annex 1 4.3 requires trial-specific systems, including updates resulting from protocol amendments, to be handled under the computerised-systems controls |
| Supplies and logistics | New kits, revised diaries, changed drug supply |
| Essential records | Signed protocol and subsequent amendments retained per Appendix C |
| Effective date discipline | The amendment applies from its approval date at that site; participants seen before it continue under the prior version until re-consented |
Exam Watchout: The most common site failure is implementing an amendment on the date the sponsor issued it rather than the date the local IRB/IEC approved it. Sites in a multicentre trial will lawfully be running different protocol versions for a period, and that is correct — each site follows the version approved for it.
Realistic exam scenario
Scenario: A sponsor emails all sites on 3 March with amendment 4, which adds a mandatory electrocardiogram at every visit after two participants elsewhere developed QTc prolongation, and lowers the maximum permitted dose. The email says "effective immediately." A coordinator schedules ECGs from the following day. Her site's IRB approves amendment 4 on 24 March. Between 4 and 24 March, six participants attend visits: five receive the new ECG, and one is dose-reduced under the new maximum.
Evaluation — the two changes are not the same:
- The dose reduction is defensible if it was necessary to eliminate an immediate hazard to that specific participant. Under section 2.5.4 the investigator may deviate for that reason, must inform the sponsor promptly, and under 2.5.5 must report the hazard, the change and the proposed amendment to the IRB/IEC and, where applicable, regulatory authorities. The clinical rationale must be documented in the source record.
- Performing the five additional ECGs before local approval is not covered by either exception. An ECG is a study procedure the participants did not consent to and the IRB had not approved. "The sponsor said effective immediately" carries no weight against section 1.4.7 — the sponsor cannot approve on the IRB's behalf.
Correct actions: stop implementing amendment 4 until the local approval date; document the five pre-approval ECGs as protocol deviations and report them to the IRB/IEC and sponsor; assess whether any participant was placed at risk or incurred an unconsented procedure; determine whether the revised consent form requires re-consent of currently enrolled participants and complete it before their next visit; confirm the registry entry reflects the changed design; document retraining on version 4; and raise a CAPA establishing that at this site amendments take effect on the local IRB approval date, communicated to the sponsor as feedback on its "effective immediately" language.
A sponsor issues a protocol amendment adding a new laboratory test at each visit and instructs sites that it is effective immediately. The site’s IRB has not yet reviewed it. What should the site do?
An investigator holds a dose for a participant whose liver function tests have risen sharply, in a way the protocol does not permit, in order to protect the participant. What must follow?
Which of the following most likely qualifies for expedited IRB/IEC review as a minor change to an ongoing approved trial?