PracticeVideosBlogFlashcards

20.3 CT Disinfection Calculations & Log-Inactivation Compliance

Key Takeaways

  • Under the EPA Surface Water Treatment Rule (SWTR), disinfection adequacy is proven through CT, which is the product of disinfectant residual concentration (C in mg/L) and effective contact time (T10 in minutes): CT = C × T10.

  • Effective contact time (T10) represents the duration required for 10% of a tracer dye to pass through a contact basin: T10 = Theoretical Detention Time (T) × Baffling Factor (BF); regulatory calculations strictly mandate evaluating T at peak hourly flow and minimum operating water volume.

  • Baffling factors range from 0.1 for unbaffled circular tanks (severe short-circuiting) to 0.3 for poor baffling, 0.5 for average baffling, 0.7 for superior serpentine baffling, and 1.0 for perfect plug-flow pipeline reactors.

  • Compliance requires the CT Ratio (CT_achieved / CT_required) to equal or exceed 1.0; a ratio below 1.0 represents a Treatment Technique (TT) violation requiring immediate Tier 2 public notification and regulatory reporting.

  • For treatment facilities with multiple disinfection contact segments in series (e.g., pipe contactor followed by clearwell compartments), total system compliance equals the mathematical sum of individual segment CT Ratios: Total CT Ratio = sum(CT_achieved, i / CT_required, i) >= 1.0.

Last updated: September 2026

The Regulatory Foundation and Mathematical Structure of CT

Under the Safe Drinking Water Act (SDWA) and the Surface Water Treatment Rule (SWTR) (including the Interim Enhanced and Long Term 2 Enhanced SWTR), surface water supplies must provide multi-barrier treatment to achieve mandatory total log-reductions against target pathogens:

  • Giardia lamblia cysts: Minimum 3-log3\text{-log} (99.9%99.9\%) total reduction.
  • Viruses: Minimum 4-log4\text{-log} (99.99%99.99\%) total reduction.
  • Cryptosporidium oocysts: Minimum 2-log2\text{-log} (99%99\%) to 5.5-log5.5\text{-log} reduction depending on source water bin classification.

In a conventional water treatment plant (coagulation, flocculation, sedimentation, and filtration), regulatory agencies grant physical removal credits of 2.5-log2.5\text{-log} for Giardia and 2.0-log2.0\text{-log} for viruses when filtered effluent turbidity meets the standard of ≤0.30 NTU\le 0.30\text{ NTU} in 95%95\% of monthly measurements (and always ≤1.0 NTU\le 1.0\text{ NTU}). The remaining inactivation burden—0.5-log0.5\text{-log} for Giardia and 2.0-log2.0\text{-log} for viruses—must be accomplished through chemical disinfection, verified through CTCT calculations.

+----------------------------------------------------------------------------+
| TOTAL REGULATORY LOG-REDUCTION REQUIREMENT                                |
|                                                                            |
| Pathogen:           Total Mandate:     Filter Credit:    Disinfection Req: |
| -----------------   --------------     --------------    ----------------- |
| Giardia lamblia     3.0-log (99.9%)  - 2.5-log credit  = 0.5-log (CT req)  |
| Viruses             4.0-log (99.99%) - 2.0-log credit  = 2.0-log (CT req)  |
| Cryptosporidium     2.0-log (99.0%)  - 2.0-log credit  = 0.0-log (UV/Mem)  |
+----------------------------------------------------------------------------+
*(Note: Free chlorine cannot inactivate Cryptosporidium oocysts at standard drinking water doses)*.

The Fundamental CT Equation

Disinfection kinetics follow Chick-Watson law, which establishes that pathogen inactivation is a function of the chemical disinfectant concentration (CC) and the contact exposure time (TT):

CT=C×T10CT = C \times T_{10}

Where:

  • C=Disinfectant residual concentration measured at the end of the contact segment (mg/L)C = \text{Disinfectant residual concentration measured at the end of the contact segment }(mg/L).
  • T10=Effective contact time in minutes at which 90% of the water has resided in the basin (min)T_{10} = \text{Effective contact time in minutes at which } 90\% \text{ of the water has resided in the basin } (min).
  • CT=Concentration-time product, expressed in mg/L⋅minCT = \text{Concentration-time product, expressed in } mg/L \cdot min.

Determining T10T_{10} and the Baffling Factor

Water entering a storage basin does not move in perfect, uniform plug flow. Due to inlet jetting, thermal density stratification, and dead spaces, some water molecules take direct shortcuts to the effluent discharge. This phenomenon is termed hydraulic short-circuiting.

Because short-circuiting water receives less disinfectant contact time than the theoretical detention time (T=V/QT = V/Q), the EPA strictly prohibits using theoretical detention time for compliance. Instead, regulations mandate the use of T10T_{10}, which represents the time required for 10%10\% of a conservative tracer dye pulse to pass from basin inlet to outlet.

Tracer Concentration
     ^
     |                     T10
     |           (10% tracer has passed)      Theoretical Detention Time (T = V/Q)
     |                      |                               |
     |                      v                               v
     |                     ###
     |                   #######
     |                 ###########
     |               ###############
     |             ###################
     |           #######################
     +-------------+--------+-------------------------------+------------------> Time
     0            T10      T50                              T (Theoretical)

     Effective Contact Time: T10 = T (Theoretical) × Baffling Factor (BF)

Theoretical Detention Time Under Worst-Case Conditions

Primacy regulations dictate that theoretical detention time (TT) must be calculated under worst-case hydraulic conditions:

  1. Peak Hourly Flow Rate (QpeakQ_{peak}): The highest volumetric flow rate entering or exiting the basin during the day, expressed in gallons per minute (gpmgpm).
  2. Minimum Operating Water Volume (VminV_{min}): The lowest water level / liquid volume maintained in the clearwell during peak demand.
T=Minimum Active Clearwell Storage Volume (gal)Peak Hourly Flow Rate (gpm)T = \frac{\text{Minimum Active Clearwell Storage Volume }(gal)}{\text{Peak Hourly Flow Rate }(gpm)}

Exam Trap: Never use average daily flow or average clearwell storage volume to calculate T10T_{10} for CT compliance! Calculating CT under average conditions overstates available contact time, creating an illegal compliance violation.

The Baffling Factor (BFBF / θ10\theta_{10})

To determine T10T_{10} without performing continuous tracer studies, engineering design standards assign an empirical Baffling Factor (BFBF) to the contact structure:

T10=T×Baffling Factor (BF)T_{10} = T \times \text{Baffling Factor }(BF)

Table 20.3.1: EPA SWTR Baffling Classifications and Baffling Factors (BFBF)

Baffling ClassificationBaffling Factor (BFBF)Physical Basin Configuration & Internal Hydraulics
Unbaffled (None)0.10.1Circular or rectangular reservoir with separate open inlet and outlet; no internal baffles; severe short-circuiting.
Poor0.30.3Single unbaffled inlet and outlet; minimal flow redirection; common in circular storage tanks and deep contact basins.
Average0.50.5Baffled inlet and outlet structures; some intermediate intra-basin deflector walls to redirect velocity streamlines.
Superior0.70.7Serpentine or labyrinth baffling circuits; length-to-width ratio exceeds 10:110:1; highly directed plug-flow channels.
Perfect Plug Flow1.01.0Long transmission pipelines (length/width>40:1length/width > 40:1); no backmixing or dead spaces; 100% of water achieves theoretical detention.

CT Lookup Tables, Water Chemistry, and the CT Ratio

The value of CTrequiredCT_{required} is not a fixed constant; it varies dynamically depending on three primary water quality parameters:

  1. Water Temperature: Disinfection is a chemical reaction. As water temperature decreases, biological inactivation kinetics slow down dramatically. Cold winter water requires significantly higher CT values than warm summer water to achieve identical log-inactivation.
  2. Water pH: Free chlorine exists in water in equilibrium between hypochlorous acid (HOClHOCl) and hypochlorite ion (OCl−OCl^-). HOClHOCl is 80 to 100 times80\text{ to }100\text{ times} more potent as a germicide than OCl−OCl^-. At pH 7.0\text{pH } 7.0, HOClHOCl represents ∼73%\sim 73\% of the residual; at pH 8.0\text{pH } 8.0, HOClHOCl drops to ∼21%\sim 21\%. Therefore, higher pH requires higher CT values.
  3. Disinfectant Residual (CC): Higher residual concentrations slightly increase the required CT value due to non-linear reaction rate changes.

Table 20.3.2: Selected EPA SWTR CT Values for 0.5-Log Inactivation of Giardia lamblia by Free Chlorine

(Values in mg/L⋅minmg/L \cdot min for chlorine residual C=1.0 to 1.4 mg/LC = 1.0\text{ to }1.4\ mg/L)

Water TemperaturepH 6.5pH 7.0pH 7.5pH 8.0pH 8.5
0.5∘C0.5^\circ\text{C} (33∘F33^\circ\text{F})49 mg/L⋅min49\ mg/L\cdot min59 mg/L⋅min59\ mg/L\cdot min70 mg/L⋅min70\ mg/L\cdot min83 mg/L⋅min83\ mg/L\cdot min99 mg/L⋅min99\ mg/L\cdot min
5.0∘C5.0^\circ\text{C} (41∘F41^\circ\text{F})35 mg/L⋅min35\ mg/L\cdot min42 mg/L⋅min42\ mg/L\cdot min50 mg/L⋅min50\ mg/L\cdot min59 mg/L⋅min59\ mg/L\cdot min71 mg/L⋅min71\ mg/L\cdot min
10.0∘C10.0^\circ\text{C} (50∘F50^\circ\text{F})24 mg/L⋅min24\ mg/L\cdot min29 mg/L⋅min29\ mg/L\cdot min35 mg/L⋅min35\ mg/L\cdot min41 mg/L⋅min41\ mg/L\cdot min49 mg/L⋅min49\ mg/L\cdot min
15.0∘C15.0^\circ\text{C} (59∘F59^\circ\text{F})16 mg/L⋅min16\ mg/L\cdot min20 mg/L⋅min20\ mg/L\cdot min23 mg/L⋅min23\ mg/L\cdot min28 mg/L⋅min28\ mg/L\cdot min33 mg/L⋅min33\ mg/L\cdot min
20.0∘C20.0^\circ\text{C} (68∘F68^\circ\text{F})12 mg/L⋅min12\ mg/L\cdot min15 mg/L⋅min15\ mg/L\cdot min17 mg/L⋅min17\ mg/L\cdot min21 mg/L⋅min21\ mg/L\cdot min25 mg/L⋅min25\ mg/L\cdot min

The CT Ratio and Actual Log Inactivation

To determine daily regulatory compliance, operators calculate the CT Ratio:

CT Ratio=CTachievedCTrequired=C×T10CTrequired\mathbf{\text{CT Ratio} = \frac{CT_{achieved}}{CT_{required}} = \frac{C \times T_{10}}{CT_{required}}}
  • Compliance Criteria:
    • CT Ratio≥1.0\text{CT Ratio} \ge 1.0: The water system achieves full compliance with the Surface Water Treatment Rule.
    • CT Ratio<1.0\text{CT Ratio} < 1.0: Treatment Technique (TT) Violation. The facility has delivered under-disinfected water, triggering mandatory state notification, an assessment of microbial risk, and potential Tier 2 Public Notification (or Boil Water Notice if residual drops below 0.2 mg/L0.2\ mg/L).

Calculating Actual Log Inactivation

Actual Log Inactivation=Target Log Requirement×CT Ratio\text{Actual Log Inactivation} = \text{Target Log Requirement} \times \text{CT Ratio}

For a 0.5-log0.5\text{-log} Giardia requirement:

Actual Log Inactivation=0.5×CT Ratio\text{Actual Log Inactivation} = 0.5 \times \text{CT Ratio}

If the CT Ratio is 2.02.0, the facility has achieved 0.5×2.0=1.0-log0.5 \times 2.0 = 1.0\text{-log} (90%90\%) inactivation of Giardia.


Multi-Segment Disinfection Basins in Series

In many modern water treatment plants, disinfection occurs across multiple sequential treatment units prior to the first customer tap (e.g., filtered water pipeline →\to clearwell compartment 11 →\to clearwell compartment 22).

Because disinfectant residual (CC), pH, and baffling conditions vary across each unit, operators cannot simply add detention times together. Instead, the CT Ratio must be computed separately for each individual segment, and the resulting segment ratios are summed:

Total System CT Ratio=∑i=1nCTachieved,iCTrequired,i=Ratio1+Ratio2+⋯+Ration\mathbf{\text{Total System CT Ratio} = \sum_{i=1}^n \frac{CT_{achieved, i}}{CT_{required, i}} = \text{Ratio}_1 + \text{Ratio}_2 + \dots + \text{Ratio}_n}

To satisfy regulatory standards, the Total System CT Ratio must equal or exceed 1.01.0.

[ Filtered Water ]
       |
       v
+-----------------------+     +-----------------------+     +-----------------------+
| Segment 1: Pipeline   | --> | Segment 2: Clearwell  | --> | Segment 3: Main to 1st|
| Contactor (BF = 1.0)  |     | Basin (BF = 0.5)      |     | Customer (BF = 1.0)   |
| Ratio_1 = 0.35        |     | Ratio_2 = 0.75        |     | Ratio_3 = 0.20        |
+-----------------------+     +-----------------------+     +-----------------------+
       |
       +===> TOTAL SYSTEM CT RATIO = 0.35 + 0.75 + 0.20 = 1.30  (COMPLIANT >= 1.0)

Step-by-Step Worked Multi-Step Calculations

Example 1: Clearwell CT Ratio and Log Inactivation Calculation

Problem Statement: A municipal water treatment facility operates an underground concrete clearwell with a total design capacity of 800,000 gallons800,000\text{ gallons}. Under peak morning distribution demand, high-service pumps withdraw water at a peak hourly rate of 4,000 gpm4,000\text{ gpm} (5.76 MGD5.76\text{ MGD} rate), drawing the clearwell water level down to 60%60\% of capacity (480,000 gallons480,000\text{ gallons}). Engineering dye studies establish an average baffling factor of 0.500.50. Finished water leaving the clearwell has a free chlorine residual of 1.20 mg/L1.20\text{ mg/L}, a water temperature of 10∘C10^\circ\text{C}, and a pH of 7.57.5. Under these conditions, the EPA lookup table specifies CTrequired=35 mg/L⋅minCT_{required} = 35\text{ mg/L}\cdot\text{min} for 0.5-log0.5\text{-log} Giardia inactivation. Calculate:

  1. The theoretical detention time (TT) in minutes under peak demand.
  2. The effective contact time (T10T_{10}) in minutes.
  3. The CTachievedCT_{achieved} value in mg/L⋅minmg/L \cdot min.
  4. The CT Ratio and determine compliance.
  5. The actual log inactivation achieved for Giardia.

Solution Procedure:

  • Step 1: Calculate Theoretical Detention Time Under Worst-Case Conditions

    Active Storage Volume (Vmin)=800,000 gal×0.60=480,000 gallons\text{Active Storage Volume } (V_{min}) = 800,000\ gal \times 0.60 = 480,000\ gallons T=VminQpeak=480,000 gal4,000 gpm=120 minutesT = \frac{V_{min}}{Q_{peak}} = \frac{480,000\ gal}{4,000\ gpm} = \mathbf{120\ minutes}
  • Step 2: Calculate Effective Contact Time (T10T_{10})

    T10=T×Baffling Factor (BF)T_{10} = T \times \text{Baffling Factor } (BF) T10=120 min×0.50=60 minutesT_{10} = 120\ min \times 0.50 = \mathbf{60\ minutes}
  • Step 3: Calculate CTachievedCT_{achieved}

    CTachieved=C×T10=1.20 mg/L×60 min=72.0 mg/L⋅minCT_{achieved} = C \times T_{10} = 1.20\ mg/L \times 60\ min = \mathbf{72.0\ mg/L \cdot min}
  • Step 4: Calculate CT Ratio and Evaluate Compliance

    CT Ratio=CTachievedCTrequired=72.0 mg/L⋅min35.0 mg/L⋅min=2.06\text{CT Ratio} = \frac{CT_{achieved}}{CT_{required}} = \frac{72.0\ mg/L\cdot min}{35.0\ mg/L\cdot min} = \mathbf{2.06}

    Because the CT Ratio of 2.06≥1.02.06 \ge 1.0, the facility complies with the SWTR disinfection mandate.

  • Step 5: Calculate Actual Log Inactivation

    Actual Log=0.5-log×CT Ratio=0.5×2.06=1.03-log inactivation\text{Actual Log} = 0.5\text{-log} \times \text{CT Ratio} = 0.5 \times 2.06 = \mathbf{1.03\text{-log inactivation}}

    (The clearwell provides more than double the required pathogen inactivation credit).

Example 2: Cold Water Temperature Drop and Required Residual Adjustment

Problem Statement: During an extreme winter freeze, water entering the clearwell described in Example 1 cools to 0.5∘C0.5^\circ\text{C} while lime softening recarbonation adjustments cause finished water pH to rise to 8.08.0. Due to these cold, high-pH conditions, the EPA lookup table indicates that required CT for 0.5-log0.5\text{-log} Giardia inactivation increases to 83 mg/L⋅min83\text{ mg/L}\cdot\text{min}. If clearwell hydraulic conditions remain identical (T10=60 minutesT_{10} = 60\text{ minutes}):

  1. Calculate the new CT Ratio if the plant maintains the previous 1.20 mg/L1.20\text{ mg/L} free chlorine residual.
  2. Determine whether an operational violation occurs.
  3. Calculate the minimum free chlorine residual concentration (CminC_{min}) required to maintain a CT Ratio of at least 1.001.00.

Solution Procedure:

  • Step 1: Calculate CT Ratio at Existing Residual

    CTachieved=1.20 mg/L×60 min=72.0 mg/L⋅minCT_{achieved} = 1.20\ mg/L \times 60\ min = 72.0\ mg/L\cdot min CT Ratio=72.083.0=0.867\text{CT Ratio} = \frac{72.0}{83.0} = \mathbf{0.867}
  • Step 2: Regulatory Assessment
    Because the CT Ratio of 0.8670.867 is less than 1.01.0, the clearwell is in non-compliance! Delivering water under these conditions constitutes a major treatment technique violation.

  • Step 3: Solve for Minimum Required Free Chlorine Residual (CminC_{min})
    To achieve a CT Ratio ≥1.00\ge 1.00, CTachievedCT_{achieved} must be at least 83.0 mg/L⋅min83.0\ mg/L\cdot min:

    CTachieved=Cmin×T10≥83.0 mg/L⋅minCT_{achieved} = C_{min} \times T_{10} \ge 83.0\ mg/L\cdot min Cmin=CTrequiredT10=83.0 mg/L⋅min60 min=1.383 mg/L≈1.39 mg/LC_{min} = \frac{CT_{required}}{T_{10}} = \frac{83.0\ mg/L\cdot min}{60\ min} = \mathbf{1.383\ mg/L} \approx 1.39\ mg/L

    The operator must immediately increase the chlorinator feed rate to raise the finished clearwell residual from 1.20 mg/L1.20\ mg/L to at least 1.40 mg/L1.40\ mg/L to restore compliance.

Example 3: Multi-Segment Disinfection Contact Calculation

Problem Statement: A water treatment plant satisfies CT across two sequential process units operating at a peak design flow rate of 3,000 gpm3,000\text{ gpm} (4.32 MGD4.32\text{ MGD}):

  • Segment 1 (Transmission Contactor Pipeline): Volume = 15,000 gallons15,000\text{ gallons}; plug-flow pipe hydraulics (BF=1.0BF = 1.0); chlorine residual at pipe discharge = 1.80 mg/L1.80\text{ mg/L}; CTrequired=30.0 mg/L⋅minCT_{required} = 30.0\text{ mg/L}\cdot\text{min}.
  • Segment 2 (Clearwell Storage Compartment): Active volume = 250,000 gallons250,000\text{ gallons}; superior serpentine baffling (BF=0.60BF = 0.60); chlorine residual at clearwell exit = 1.40 mg/L1.40\text{ mg/L}; CTrequired=35.0 mg/L⋅minCT_{required} = 35.0\text{ mg/L}\cdot\text{min}.

Calculate the CT Ratio for each segment, determine the total system CT Ratio, and verify whether the facility achieves 0.5-log0.5\text{-log} Giardia compliance.

Solution Procedure:

  • Step 1: Evaluate Segment 1 (Pipeline Contactor)

    T1=15,000 gal3,000 gpm=5.0 minutesT_1 = \frac{15,000\ gal}{3,000\ gpm} = 5.0\ minutes T10,1=5.0 min×1.0=5.0 minutesT_{10, 1} = 5.0\ min \times 1.0 = 5.0\ minutes CTachieved,1=1.80 mg/L×5.0 min=9.0 mg/L⋅minCT_{achieved, 1} = 1.80\ mg/L \times 5.0\ min = 9.0\ mg/L\cdot min CT Ratio1=9.0 mg/L⋅min30.0 mg/L⋅min=0.30\text{CT Ratio}_1 = \frac{9.0\ mg/L\cdot min}{30.0\ mg/L\cdot min} = \mathbf{0.30}
  • Step 2: Evaluate Segment 2 (Clearwell Storage)

    T2=250,000 gal3,000 gpm=83.33 minutesT_2 = \frac{250,000\ gal}{3,000\ gpm} = 83.33\ minutes T10,2=83.33 min×0.60=50.0 minutesT_{10, 2} = 83.33\ min \times 0.60 = 50.0\ minutes CTachieved,2=1.40 mg/L×50.0 min=70.0 mg/L⋅minCT_{achieved, 2} = 1.40\ mg/L \times 50.0\ min = 70.0\ mg/L\cdot min CT Ratio2=70.0 mg/L⋅min35.0 mg/L⋅min=2.00\text{CT Ratio}_2 = \frac{70.0\ mg/L\cdot min}{35.0\ mg/L\cdot min} = \mathbf{2.00}
  • Step 3: Calculate Total System CT Ratio

    Total CT Ratio=CT Ratio1+CT Ratio2=0.30+2.00=2.30\text{Total CT Ratio} = \text{CT Ratio}_1 + \text{CT Ratio}_2 = 0.30 + 2.00 = \mathbf{2.30} Total Log Inactivation=0.5-log×2.30=1.15-log inactivation\text{Total Log Inactivation} = 0.5\text{-log} \times 2.30 = \mathbf{1.15\text{-log inactivation}}

    The facility achieves full compliance with a total ratio of 2.30≥1.02.30 \ge 1.0.


CT Disinfection Compliance Troubleshooting and Worksheets

Maintaining continuous CT compliance requires active operator intervention whenever hydraulic flow rates, clearwell water elevations, or water quality conditions shift.

Table 20.3.3: CT Disinfection Compliance Troubleshooting Guide

Operational DisturbanceDirect Hydraulic / Kinetic ImpactOperator Corrective Action
Sudden Peak Pumping SurgePumping flow (QQ) doubles, reducing theoretical detention (TT) and T10T_{10} by 50%50\%.Immediately increase chlorinator feed dosage to raise chemical residual (CC) to offset contact time reduction.
Clearwell Level DepletionEmergency firefighting or distribution main break draws clearwell volume (VV) down to low levels.Throttle distribution high-service pumps or bring auxiliary finish tanks online; increase chlorine feed proportionally.
Rapid Water Temperature DropWinter conditions reduce reaction kinetics; CTrequiredCT_{required} increases by 50% to 100%50\%\text{ to }100\%.Pre-calculate winter CT requirements; maintain higher target chlorine residuals throughout winter operating months.
Post-Filter pH IncreaseAdding lime, caustic soda, or soda ash for corrosion control raises pH above 8.08.0, converting HOClHOCl to weak OCl−OCl^-.Shift alkali chemical feed injection point downstream of the clearwell exit to allow primary disinfection to occur at lower pH.
Test Your Knowledge

A municipal clearwell has an active storage volume of 600,000 gallons at its minimum operating water level. The plant experiences a peak hourly flow rate of 3,600 gpm. Tracer studies indicate a baffling factor of 0.40. The finished water effluent maintains a free chlorine residual of 1.5 mg/L. If the state-mandated CT required for 0.5-log Giardia inactivation is 38 mg/L·min, what is the CT Ratio achieved by the clearwell?

A

2.63

B

1.75

C

6.58

D

0.95

Test Your Knowledge

A water facility uses two disinfection contact stages in series before the first customer. Stage 1 is a transmission pipeline achieving a CT Ratio of 0.35. Stage 2 is a baffled contact basin with a T10 contact time of 40 minutes and a free chlorine residual of 0.9 mg/L. If the CT required in Stage 2 is 48 mg/L·min, what is the total system CT Ratio, and does the facility comply with the Surface Water Treatment Rule?

A

0.75; the facility violates the SWTR because Stage 2 alone fails to reach 1.0

B

0.92; the facility violates the SWTR because total CT Ratio is below 1.0

C

1.45; the facility complies with the SWTR

D

1.10; the facility complies with the SWTR

Test Your Knowledge

A water treatment plant operates a clearwell with a T10 contact time of 32 minutes during peak hourly demand. Due to cold winter water temperatures (1.0°C) and a finished water pH of 7.8, the EPA CT table requires a CT of 56 mg/L·min for Giardia inactivation. What is the minimum free chlorine residual concentration (C) that operators must maintain at the clearwell effluent to achieve a CT Ratio of at least 1.0?

A

1.25 mg/L

B

1.75 mg/L

C

2.15 mg/L

D

0.85 mg/L

Sections you finish are checked off in the contents.