All Practice Exams

100+ Free GCC Factories Plant Engineering Exam Practice Questions

GCC Factories Engineer — Plant Engineering Examination (South Africa) practice questions are available now; exam metadata is being verified.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
100+ Questions
100% Free

Loading practice questions...

Same family resources

Explore More South Africa Government Certificate of Competency (GCC)

Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.

Sample GCC Factories Plant Engineering Exam Practice Questions

Try these sample questions to test your GCC Factories Plant Engineering Exam exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1A 500 kVA, 11 kV / 400 V distribution transformer has a full-load copper loss of 4.5 kW and an iron loss of 2.5 kW. What is the efficiency of the transformer at full load operating at a power factor of 0.8 lagging?
A.98.28%
B.97.56%
C.96.40%
D.98.90%
Explanation: Full load active output power P_out = S * cos(phi) = 500 kVA * 0.8 = 400 kW. Total losses at full load P_loss = P_cu + P_iron = 4.5 kW + 2.5 kW = 7.0 kW. Total input power P_in = P_out + P_loss = 400 + 7 = 407 kW. Efficiency eta = (P_out / P_in) * 100 = (400 / 407) * 100 = 98.28%.
2A 1000 kVA power transformer has a core (iron) loss of 3.0 kW and a full-load copper loss of 12.0 kW. At what load (in kVA) will the transformer achieve its maximum efficiency?
A.500 kVA
B.707 kVA
C.250 kVA
D.866 kVA
Explanation: Maximum efficiency occurs when variable copper loss equals constant iron loss: x^2 * P_cu_fl = P_iron, where x is the fraction of full load. x = sqrt(P_iron / P_cu_fl) = sqrt(3.0 / 12.0) = sqrt(0.25) = 0.5. Therefore, load for maximum efficiency = 0.5 * 1000 kVA = 500 kVA.
3Two 3-phase transformers A and B are connected in parallel to serve a total load of 700 kVA. Transformer A is rated at 500 kVA with 4% impedance, and Transformer B is rated at 250 kVA with 5% impedance. Assuming equal voltage ratios, how much load does Transformer A carry?
A.500 kVA
B.450 kVA
C.525 kVA
D.400 kVA
Explanation: Load sharing in parallel transformers: S_A = S_total * (S_A_rating / Z_A) / [(S_A_rating / Z_A) + (S_B_rating / Z_B)]. Here, S_A_rating / Z_A = 500 / 4 = 125. S_B_rating / Z_B = 250 / 5 = 50. Sum = 175. Thus, S_A = 700 * (125 / 175) = 500 kVA.
4A 4-pole, 3-phase induction motor operates from a 50 Hz supply. If the actual rotor speed is measured at 1440 rpm, what is the slip of the motor?
A.4.0%
B.2.5%
C.5.0%
D.3.3%
Explanation: Synchronous speed N_s = (120 * f) / P = (120 * 50) / 4 = 1500 rpm. Slip s = (N_s - N) / N_s = (1500 - 1440) / 1500 = 60 / 1500 = 0.04 or 4.0%.
5A 6-pole, 50 Hz, 3-phase induction motor runs at a slip of 3%. What is the frequency of the rotor currents under this operating condition?
A.1.5 Hz
B.3.0 Hz
C.50 Hz
D.48.5 Hz
Explanation: Rotor current frequency f_r = s * f, where s is slip and f is stator supply frequency. f_r = 0.03 * 50 Hz = 1.5 Hz.
6A 3-phase squirrel-cage induction motor develops a Direct-On-Line (DOL) starting torque equal to 2.2 times its full-load torque. If a Star-Delta starter is installed, what starting torque will the motor develop?
A.0.73 times full-load torque
B.1.10 times full-load torque
C.1.47 times full-load torque
D.2.20 times full-load torque
Explanation: In star connection, phase voltage is 1/sqrt(3) of line voltage. Since torque is proportional to the square of phase voltage, T_star = (1/3) * T_DOL. T_star = (1/3) * 2.2 T_FL = 0.733 times full-load torque.
7An industrial plant draws an active power load of 400 kW at a power factor of 0.75 lagging. To avoid utility penalties, the plant engineer decides to improve the power factor to 0.95 lagging using a static capacitor bank. Calculate the required rating of the capacitor bank in kVAR.
A.221.3 kVAR
B.180.5 kVAR
C.352.8 kVAR
D.131.5 kVAR
Explanation: Initial angle phi_1 = acos(0.75) = 41.41°, tan(phi_1) = 0.8819. Initial Q_1 = P * tan(phi_1) = 400 * 0.8819 = 352.76 kVAR. Target angle phi_2 = acos(0.95) = 18.19°, tan(phi_2) = 0.3287. Target Q_2 = P * tan(phi_2) = 400 * 0.3287 = 131.47 kVAR. Required capacitor rating Q_c = Q_1 - Q_2 = 352.76 - 131.47 = 221.3 kVAR.
8An 11 kV factory main busbar is supplied by a 10 MVA transformer with a per-unit percentage reactance of 8% (0.08 pu). Assuming the upstream grid capacity is infinite, what is the symmetrical short-circuit fault MVA level at the busbar?
A.125 MVA
B.80 MVA
C.100 MVA
D.150 MVA
Explanation: Short-circuit fault level S_sc = Rating / Z_pu = 10 MVA / 0.08 = 125 MVA.
9For the 11 kV busbar in Question 008 with a short-circuit fault level of 125 MVA, calculate the 3-phase symmetrical short-circuit fault current in kA.
A.6.56 kA
B.11.36 kA
C.3.79 kA
D.8.25 kA
Explanation: Fault current I_sc = S_sc / (sqrt(3) * V_line) = 125,000,000 VA / (1.73205 * 11,000 V) = 125,000,000 / 19,052.55 = 6,560.8 A = 6.56 kA.
10A 100 m long 3-phase 400 V cable supplies a motor drawing 80 A at 0.8 power factor lagging. The cable parameters per conductor are resistance R = 0.25 ohm/km and reactance X = 0.15 ohm/km. What is the line-to-line voltage drop across the cable?
A.4.02 V (1.01%)
B.6.96 V (1.74%)
C.2.32 V (0.58%)
D.8.04 V (2.01%)
Explanation: Cable length L = 0.1 km. R_line = 0.025 ohm, X_line = 0.015 ohm. cos(phi) = 0.8, sin(phi) = 0.6. Phase voltage drop V_drop_ph = I * (R_line * cos(phi) + X_line * sin(phi)) = 80 * (0.025 * 0.8 + 0.015 * 0.6) = 80 * (0.020 + 0.009) = 80 * 0.029 = 2.32 V. Line-to-line voltage drop = sqrt(3) * 2.32 V = 4.02 V. Percentage drop = (4.02 / 400) * 100 = 1.01%.

About the GCC Factories Plant Engineering Exam Practice Questions

Verified exam format metadata for GCC Factories Engineer — Plant Engineering Examination (South Africa) is pending. The practice questions above remain available while official exam length, timing, passing score, fee, and administrator details are reviewed.