Question 1
Score: 0/0

Which budget update transaction increases the original budget after it has been released?

A
B
C
D
to track
2026 Statistics

Key Facts: SAP S/4HANA PS Exam

80

Exam Questions

180-minute time limit

68%

Passing Score

~55 correct answers

$562

Exam Fee

SAP certification

7

Topic Areas

PS domains tested

3

Exam Attempts

Allowed per certification

C_TS412_2021 covers the traditional SAP Project Systems (PS) module on S/4HANA on-premise and Cloud Private Edition. The exam has 80 questions with a 180-minute time limit and 68% passing score. It tests project structures with WBS elements and networks, materials and components, resources and capacity, scheduling, Easy Cost Planning and budget with availability control, customer projects with milestone and resource-related billing, and the PS Information System.

Sample SAP S/4HANA PS Practice Questions

Try these sample questions to test your SAP S/4HANA PS exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1Which object is always the highest-level node of a project hierarchy in SAP Project Systems?
A.Project Definition
B.Top WBS Element
C.Network Header
D.Standard Project
Explanation: The Project Definition is the binding framework for an entire project — it stores defaults like controlling area, profit center, project profile, and currency that are inherited by all WBS elements. WBS elements sit beneath the project definition; the network header and standard project are different concepts.
2Which three operative indicators can be set on a WBS element?
A.Account Assignment Element, Planning Element, Billing Element
B.Header Element, Detail Element, Summary Element
C.Cost Element, Revenue Element, Statistical Element
D.Project Element, Network Element, Activity Element
Explanation: WBS elements carry three operative indicators that control their behavior: Account Assignment Element (collects actual costs), Planning Element (holds plan values), and Billing Element (allows revenue and customer billing). Any combination can be set on the same WBS element.
3Which transaction is the central tool for creating and changing projects in SAP S/4HANA Project Systems?
A.Project Builder (CJ20N)
B.Project Planning Board (CJ27)
C.PS Information System (CN41N)
D.Easy Cost Planning (CJ9ECP)
Explanation: CJ20N — Project Builder — is the standard maintenance transaction that lets users create and edit project definitions, WBS elements, networks, activities, milestones, and material components in one screen. The Planning Board is for graphical scheduling, the Information System is for reporting, and Easy Cost Planning is a planning tool.
4Which activity type creates a purchase requisition automatically when a network is saved?
A.External Activity
B.Internal Activity
C.General Costs Activity
D.Milestone Activity
Explanation: An External Activity represents work performed by a vendor and triggers an automatic purchase requisition through the assigned purchasing data (control key with external processing). Internal activities consume internal capacity, general costs activities post lump-sum costs to a cost element, and milestone is not an activity type.
5What is the maximum number of billing elements a customer-project sales order item can be assigned to within one project hierarchy branch?
A.One billing element per branch
B.One billing element per WBS level
C.Unlimited
D.Two billing elements per branch
Explanation: When assigning a sales order item to a project, only one WBS element marked as a billing element may exist between the assigned WBS element and the project root in that branch. This rule prevents revenue from being settled to two billing elements that overlap in the hierarchy.
6Which transaction is used to enter or change the original budget of a project?
A.CJ30
B.CJ40
C.CJ20N
D.KO22
Explanation: CJ30 maintains the original budget at WBS level and CJ32 maintains supplements/returns/transfers. CJ40 is for cost-element planning, CJ20N is the Project Builder, and KO22 is for internal-order budgeting.
7What is the primary purpose of Availability Control in SAP Project Systems?
A.Compare assigned values against the budget and warn or block when tolerances are exceeded
B.Reserve materials in inventory for project consumption
C.Block projects that are not yet released
D.Reconcile plan values with actual postings
Explanation: Availability Control monitors assigned values (commitments + actuals + statistical) against the current budget at the activated WBS element and triggers warning, mail, or error messages based on the configured tolerance limits. It is driven by the budget — not by the plan.
8Which planning method uses costing models with templates and quantity-based items to plan costs quickly at the WBS element level?
A.Easy Cost Planning
B.Detailed Planning
C.Network Costing
D.Unit Cost Estimate
Explanation: Easy Cost Planning (ECP) uses costing models with characteristics-driven templates to generate planned costs through unit costing items. Detailed Planning is cost-element-by-cost-element entry, Network Costing values activities and components, and a Unit Cost Estimate is one of the items used inside ECP.
9Which scheduling method calculates the latest possible dates by scheduling backward from the project finish date?
A.Backward scheduling
B.Forward scheduling
C.Top-down scheduling
D.Bottom-up scheduling
Explanation: Backward scheduling starts from the basic finish date and computes the latest start. Forward scheduling starts at the basic start to compute the earliest finish. Top-down/bottom-up describe how WBS dates and network dates synchronize, not the scheduling direction.
10Which billing method posts an invoice request when a milestone is set to fixed-date status on the WBS or network?
A.Milestone Billing
B.Resource-Related Billing
C.Periodic Billing
D.Down-Payment Billing
Explanation: Milestone Billing creates billing plan dates when a billing-relevant milestone is marked as actually reached. Resource-Related Billing (DP91) generates a debit memo request from posted actual costs. Periodic billing is for service contracts; down-payment billing handles advances.

About the SAP S/4HANA PS Exam

The SAP S/4HANA Project Systems (C_TS412_2021) certification validates expertise in the traditional PS module on S/4HANA on-premise and Cloud Private Edition. It covers project structures (WBS, networks, milestones), materials and resources in projects, scheduling, cost and budget management, revenues and billing, and project reporting.

Questions

80 scored questions

Time Limit

180 minutes

Passing Score

68%

Exam Fee

$562 (SAP (Pearson VUE proctored))

SAP S/4HANA PS Exam Content Outline

21-30%

Project Structures

Project definition, WBS element types and operative indicators (account assignment, planning, billing), network header and activity types, milestones, status management, project templates, Project Builder (CJ20N)

11-20%

Material

Material components in networks, BOM transfer, reservations and purchase requisitions, deliveries from projects, assembly processing, and project sourcing via procurement

11-20%

Resources

Internal/external/general-costs/service activities, work centers, capacity planning, time confirmation (CATS, IW41), and network type configuration

11-20%

Dates

Date planning in WBS, network scheduling (forward, backward, top-down, bottom-up), reduction strategies, project planning board, and milestone dates

11-20%

Cost and Budgets

Easy Cost Planning, detailed cost element and activity input planning, original budget with supplements/returns/transfers, availability control, settlement rules, and period-end closing

11-20%

Revenues and Payments

Customer projects, account-assigned sales orders, milestone billing, resource-related billing (DP91), results analysis (WIP), and settlement to profitability segment (PSG)

≤10%

Reporting

PS Information System, hierarchy reports (S_ALR_87013533), cost element reports, line item reports, progress analysis and earned value (POC methods), and project versions

How to Pass the SAP S/4HANA PS Exam

What You Need to Know

  • Passing score: 68%
  • Exam length: 80 questions
  • Time limit: 180 minutes
  • Exam fee: $562

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

SAP S/4HANA PS Study Tips from Top Performers

1Master WBS element operative indicators — Account Assignment Element collects costs, Planning Element holds plan values, Billing Element issues invoices; only one billing element per branch can carry a sales order assignment
2Understand the difference between Easy Cost Planning (quick top-down with templates and unit costing) and Detailed Planning (cost element planning and activity input planning at the WBS or network level)
3Know the difference between Plan (CJ40/CJ42), Budget (CJ30/CJ32 — original, supplements, returns, transfers) and Actuals — only Budget triggers Availability Control with warning, error, and email tolerance limits
4Study network activity types — Internal Activity uses work center and activity type for internal capacity, External Activity creates a purchase requisition, General Costs Activity posts directly to a cost element, Service Activity creates a service purchase requisition with service entry
5Learn the customer project flow — sales order item account-assigned to billing WBS, then either Milestone Billing (driven by billing milestones on the WBS or network) or Resource-Related Billing via DP91 that creates a billing request from actuals

Frequently Asked Questions

What is the SAP C_TS412_2021 exam?

C_TS412_2021 (SAP Certified Associate — SAP S/4HANA Project Systems) is SAP's certification for the traditional PS module on S/4HANA on-premise and Cloud Private Edition. It covers project structures (WBS elements, networks, milestones), materials and resources, date scheduling, cost and budget management with availability control, customer-project billing, and the PS Information System.

What is the passing score for C_TS412_2021?

The passing score for C_TS412_2021 is 68%. With 80 questions and a 180-minute time limit, you need approximately 55 correct answers. The exam is proctored through Pearson VUE either online or at a testing center. SAP allows three attempts per certification period.

Is C_TS412_2021 the same as the C_S4PM cert?

No. C_TS412_2021 covers the traditional SAP PS (Project Systems) module on S/4HANA on-premise and Cloud Private Edition with WBS elements, networks, and Project Builder (CJ20N). C_S4PM covers Cloud Public Edition Project Manager using SAP S/4HANA Cloud Project Management — a different, lighter-weight project solution. Pick the cert that matches your deployment.

How long should I study for the SAP PS certification?

Plan 8-12 weeks of study. Focus on WBS element operative indicators, network and activity types, status management, Easy Cost Planning vs detailed planning, the difference between budget and plan with availability control, milestone vs resource-related billing for customer projects, and period-end closing with settlement and results analysis.

Is the SAP PS certification worth it?

Yes for consultants implementing engineer-to-order, large capital projects, professional services, or any business that runs internal investment or customer-facing projects in SAP. Certified PS consultants are sought after in industries like construction, plant engineering, aerospace, and IT services where project accounting drives revenue recognition.