Key Facts: Juru Ukur Konstruksi Exam

4

Official Competency Units

LSP ATAKI and BNSP

Rp 450.000

Online Assessment Fee

LSP ATAKI

24

Questions in this independent bank

OpenExamPrep inventory

This bank provides 24 independent English MCQs across SI163008's four units. It reviews concepts only and does not simulate the scheme's possible oral, written, demonstration, or simulation evidence.

Sample Juru Ukur Konstruksi Practice Questions

Try these sample questions to review concepts for the Juru Ukur Konstruksi exam. Each question includes a detailed explanation. Start the interactive quiz above for the full 24+ question experience with AI tutoring.

1Which personal protective equipment (APD) set best addresses visibility, head-impact, and foot hazards for a juru ukur working near active heavy equipment?
A.High-visibility reflective safety vest, safety helmet, and protective-toe safety boots
B.Safety helmet, safety glasses, and ordinary shoes without high-visibility clothing
C.High-visibility vest, bump cap, and ordinary shoes without protective toes
D.Safety helmet, hearing protection, and safety boots without high-visibility clothing
Explanation: The task assessment identifies three prominent hazards: plant operators must see the surveyor, falling or swinging objects can strike the head, and uneven ground or materials can injure feet. A reflective vest, safety helmet, and protective-toe boots address those hazards; additional APD follows the site risk assessment. This is an independent English-language MCQ study adaptation, not a substitute for practical K3L assessment.
2A project's approved safety plan classifies a deep trench as permit-controlled and requires verified shoring before entry. What must the juru ukur confirm before entering to set an invert stake?
A.An approved Excavation Permit to Work (SIKA) and verified trench shoring check
B.A general site induction card and the survey work order, without a trench-entry check
C.The excavation permit alone, assuming shoring remains acceptable from the prior shift
D.A current shoring inspection alone, without the permit required by the approved safety plan
Explanation: The controls specified in the scenario are cumulative: the applicable excavation permit must be active and the protective system must have been checked before entry. A work order, permit, or inspection on its own leaves one required control unverified. This independent English-language MCQ study adaptation exercises K3L decision-making in unit M.71TPU00.001.2.
3What immediate action should a surveying crew take if a sudden tropical rainstorm triggers severe lightning while they are setting control points in an open paddy field?
A.Stop observations but wait beside the tripod until rainfall begins
B.Cease work, leave exposed equipment, and seek shelter in an enclosed vehicle or substantial building
C.Move beneath an isolated tree while keeping the range poles on the ground
D.Continue only short observations while the crew remains spread across the field
Explanation: An open field provides little lightning protection. The crew should stop work and move promptly to a substantial building or enclosed vehicle, without delaying to handle exposed equipment. An isolated tree and waiting near the setup remain hazardous. This item is independent English-language review of emergency response, not an official practical simulation.
4What is the primary function of a Job Safety Analysis (JSA / Analisis Keselamatan Pekerjaan) prepared by a survey team before beginning high-risk staking out?
A.Listing the task hazards after work so the incident file is complete
B.Deconstructing tasks into sequential steps to systematically identify hazards and define preventive controls
C.Selecting APD without considering elimination, engineering, or administrative controls
D.Copying a general project hazard register without analysing the survey task steps
Explanation: A Job Safety Analysis (JSA) systematically examines each operational step of a specific task (e.g., crossing highways, setting up near excavators, climbing formwork) to identify associated safety hazards and establish administrative and engineering controls before work commences. It turns the survey sequence into controls the crew can brief and apply before exposure begins.
5In the hierarchy of hazard controls (Hirarki Pengendalian Bahaya) applied to surveying near active earthmoving machinery, which measure provides the highest level of protection?
A.Schedule surveying during a verified plant shutdown so no earthmoving machinery operates in the survey zone
B.Use a trained spotter and radio protocol while surveyors remain inside the active plant route
C.Schedule a toolbox briefing and issue high-visibility clothing before entering the shared route
D.Mark the survey work zone with cones while allowing plant to pass immediately beside each setup
Explanation: In the hierarchy of controls, eliminating exposure ranks above engineering controls, administrative controls, and PPE. A verified plant shutdown removes moving machinery from the survey zone instead of relying on people to avoid it.
6What is the primary safety purpose of conducting a daily 'Toolbox Meeting' (safety briefing) before the survey team disperses across a major civil construction site?
A.Reviewing daily site hazards, simultaneous operations, weather warnings, and emergency muster assignments
B.Reviewing only the prior day's completed measurements and arithmetic closures
C.Assigning technical roles without discussing changing site hazards or emergency arrangements
D.Repeating the generic site induction without addressing the day's simultaneous operations
Explanation: The daily toolbox meeting (safety briefing) aligns field crews on shifting daily site risks—such as active blasting schedules, heavy crane lifts, new excavation zones, or weather warnings. It also ensures every worker knows the day's controls, emergency contacts, and assigned muster points.
7What is the primary rule for verbal radio communication (Handy Talky / HT) when transmitting leveling staff readings between surveyor and bookkeeper?
A.Reading the entire value as one number and asking for confirmation only at the end of the survey run
B.Sending each value twice but omitting an explicit decimal-point call
C.Using short project abbreviations without first agreeing their meaning with the receiver
D.Enunciating each digit clearly, stating decimal points, and obtaining readback
Explanation: Numerical survey data are highly susceptible to hearing and transposition errors over two-way radio channels. Professional protocol requires articulating each digit separately (e.g., 'one point four five two'), followed by immediate confirmation through a verbatim readback by the recorder before writing into the field book.
8Why is the three-way communication technique (readback verification) essential between the instrument surveyor and the field bookkeeper?
A.Allowing the recorder to round every value to the field book's displayed precision
B.Preventing numerical transposition errors before leaving the survey station
C.Replacing the need to record the observer and station identifiers
D.Confirming that the staff is vertical without using the rod bubble or observation procedure
Explanation: Transposition errors (swapping adjacent numerals) are among the most common human blunders in field surveying. Readback verification requires the receiver to repeat the value exactly as heard, enabling immediate acoustic detection and correction before the station is abandoned.
9What immediate technical communication should occur if a surveyor realizes halfway through a traverse that the backsight prism was set over the wrong benchmark pin?
A.Continue the traverse, flag the affected points, and apply a translation to all coordinates in the office
B.Take a check shot to the intended benchmark but retain the earlier observations if its distance is close
C.Notify the crew, invalidate corrupted shots, and re-observe from the true benchmark
D.Complete the current station, then notify the crew after downstream setting-out has begun
Explanation: Occupying or sighting the wrong benchmark gives the setup an incorrect reference or orientation, so its downstream coordinates cannot be relied on for setting-out. Professional surveying ethics and quality control require immediate disclosure, invalidation of the affected observations, and re-measurement from the verified control monument.
10What is the primary technical objective of a morning briefing conducted by the juru ukur for the survey field team?
A.Confirming only the day's production target and leaving control information to individual crew members
B.Reviewing the instrument manual without assigning field roles or control points
C.Aligning on project datum, control points, tolerances, and delegated crew roles
D.Assigning field roles and start time while deferring datum and tolerance questions until observations are complete
Explanation: The briefing should establish a shared understanding of the work instruction, datum and control, applicable tolerances, sequence, and team responsibilities before measurement begins. Equipment checks are handled in the preparation process. This question reviews the coordination scope of M.71TPU00.002.2.

About the Juru Ukur Konstruksi Exam

Juru Ukur Konstruksi (Jenjang 3, scheme SI163008) is an active LSP ATAKI qualification with four units: applying K3L, communicating in measurement, preparing measurement work, and preparing the final measurement report.

Exam sponsor: LSP ATAKI Konstruksi Indonesia under BNSP licensing and LPJK registration. The requirements and fees below concern the certification or admission exam, separate from our free practice resources.

Assessment

Delivery is available online, offline, or onsite. The published unit guides allow oral or written questions and practical demonstration or simulation; LSP ATAKI does not publish one fixed SI163008 method mix.

Time Limit

Not published in the current official sources reviewed

Passing Score

Competency decision; numeric pass mark not published

Exam / Certification Fees

Rp 450.000 (daring) / Rp 600.000 (luring)

Exam sponsor website

Reported exam pass rate: Not published. Exam sponsor website

Fees, eligibility, and exam policies can change. Confirm them with the exam sponsor before applying or paying.

Our practice resources: topics covered

We aim to reflect publicly available exam outlines and topic information in our study resources. Coverage, format, and difficulty may differ from the actual exam, and we cannot guarantee that every detail is accurate or current. Confirm exam requirements, fees, and policies with the official exam sponsor.

6 of 24 questions

M.71TPU00.001.2 — Applying K3L at the Workplace

Hazard recognition, selected controls, APD, emergency response, JSA, and briefings.

6 of 24 questions

M.71TPU00.002.2 — Communication in the Measurement Process

Numeric readback, team roles, error escalation, briefings, and controlled revisions.

6 of 24 questions

M.71TPU00.003.2 — Pre-Measurement Preparation

Work scheduling, preliminary field survey, equipment checks, control verification, transport, and data preparation.

6 of 24 questions

M.71TPU00.004.2 — Preparing the Final Measurement Report

Traceable records, complete reports, as-built purpose, archives, review, and rejected observations.

Preparing for the Juru Ukur Konstruksi Exam

What You Need to Know

  • Passing score: Competency decision; numeric pass mark not published
  • Assessment: Delivery is available online, offline, or onsite. The published unit guides allow oral or written questions and practical demonstration or simulation; LSP ATAKI does not publish one fixed SI163008 method mix.
  • Time limit: Not published in the current official sources reviewed
  • Exam / certification fees: Rp 450.000 (daring) / Rp 600.000 (luring) Official sources

Using Our Practice Resources

  • Work through all 24 available questions
  • Review every answer and explanation
  • Track weak areas and revisit them
  • Use our AI tutor for tough concepts

Juru Ukur Konstruksi: Suggested Study Strategy

1Review each of the four unit titles and their performance criteria in Kepmenaker 158/2024.
2Practise clear readback and controlled communication of work instructions and changed control values.
3Prepare evidence showing safe work, measurement readiness, traceable records, and complete report submission.

Frequently Asked Questions

What is the official scheme code and level?

The scheme code is SI163008, registered at KKNI Jenjang 3 (Technician level) by LSP ATAKI Konstruksi Indonesia under BNSP.

What are the published assessment fees?

The official fee published by LSP ATAKI is Rp 450.000 for online (daring) assessment and Rp 600.000 for offline (luring) assessment.

What four competency units are assessed?

The units are M.71TPU00.001.2 (K3L in workplace), M.71TPU00.002.2 (Communication during measurement), M.71TPU00.003.2 (Pre-measurement preparation), and M.71TPU00.004.2 (Final measurement report).