100+ Free GSC Project Manager Practice Questions
Pass your CCA Gold Seal Certified Project Manager exam on the first try — instant access, no signup required.
Loading practice questions...
Explore More CCA Gold Seal Certification Exams (Canada)
Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
Key Facts: GSC Project Manager Exam
180
Exam Questions
Canadian Construction Association
3.5 hours
Exam Duration
Canadian Construction Association
70%
Passing Score
Canadian Construction Association
$490
Enrolment Fee
Canadian Construction Association
$115
Application Fee
Canadian Construction Association
$150
Exam Fee
Canadian Construction Association
Prepare for the CCA Gold Seal Certified Project Manager exam. The exam features 180 multiple-choice questions, has a 3.5-hour time limit, requires a passing score of 70%, and costs $755 total in fees (excluding HST). It tests project financials, CCDC contracts, scheduling, risk management, and ethics.
Sample GSC Project Manager Practice Questions
Try these sample questions to test your GSC Project Manager exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.
1Under provincial builders' lien legislation in Canada, what is the primary purpose of the statutory holdback?
2What does 'overbilling' (billing in excess of costs and estimated earnings) represent on a contractor's balance sheet?
3Under CCDC 2 (2020), what document must the Contractor submit to the Consultant at least 15 calendar days before the first application for payment?
4A project has a Budget at Completion (BAC) of $1,200,000. Currently, the Earned Value (EV) is $400,000, and the Actual Cost (AC) is $500,000. If the remaining work is expected to be performed at the budgeted rate, what is the Estimate at Completion (EAC)?
5If a project shows 'underbilling' (costs and estimated earnings in excess of billings), what is the most likely cause?
6Which of the following best describes the shape and meaning of a typical project cumulative cash flow curve (S-Curve)?
7Under CCDC 2, if a Change Order involves both additions and deletions to the Work, how is the Contractor's markup for overhead and profit calculated?
8A construction project is 6 months into a 12-month schedule. The cumulative Actual Cost (AC) is $850,000, Planned Value (PV) is $900,000, and Earned Value (EV) is $780,000. If the current cost efficiency is expected to continue for the remainder of the project, what is the Estimate at Completion (EAC) given a BAC of $1,800,000?
9How can a Project Manager best optimize project cash flow without compromising relations with subcontractors or violating CCDC 2 terms?
10Under the Construction Act in Ontario, when can holdback be released to a subcontractor whose subcontract is certified complete prior to substantial performance of the entire project?
About the GSC Project Manager Exam
The Gold Seal Certified (GSC) Project Manager credential is Canada's recognized standard of excellence for construction project management professionals. It verifies the candidate's professional capacity to manage project budgets, cash flow, CCDC contracts, scheduling, risks, and health & safety compliance, while adhering to the CCA Code of Ethics.
Assessment
180 multiple-choice questions (CBT, closed book)
Time Limit
3.5 hours
Passing Score
70%
Exam Fee
CAD $150 exam fee (2026). Path typically CAD $490 enrollment + $115 GSC application + $150 exam registration (+ applicable taxes). (Canadian Construction Association (CCA))
GSC Project Manager Exam Content Outline
Project Financials & Cost Control
Budgeting, cash flow forecasting, progress billing, cost tracking, forecasting (EAC/ETC), change order valuation, and financial reporting.
CCDC Contracts & Project Execution
Administration of CCDC 2, 5A, 5B, 14, 30, and CCA 1 contracts; roles of Owner, Consultant, and Contractor; closeout documentation.
Risk Management & Legal/Regulatory Compliance
Hazard assessments, safety regulations (OHS), insurance policies, construction bonding, and Builders' Liens/Construction Acts.
Scheduling & Planning
Critical Path Method (CPM), total and free float, schedule crashing, sequencing, and excusable vs. compensable delay claims.
Dispute Resolution & Ethical Decision-Making
Negotiation, mediation, arbitration, litigation, CCA code of ethics, conflicts of interest, and honest reporting.
How to Pass the GSC Project Manager Exam
What You Need to Know
- Passing score: 70%
- Assessment: 180 multiple-choice questions (CBT, closed book)
- Time limit: 3.5 hours
- Exam fee: CAD $150 exam fee (2026). Path typically CAD $490 enrollment + $115 GSC application + $150 exam registration (+ applicable taxes).
Keys to Passing
- Complete 500+ practice questions
- Score 80%+ consistently before scheduling
- Focus on highest-weighted sections
- Use our AI tutor for tough concepts
GSC Project Manager Study Tips from Top Performers
Frequently Asked Questions
What is the passing score for the Gold Seal Project Manager exam?
The passing score for the Gold Seal Certified (GSC) Project Manager exam is 70%. All questions are multiple-choice, and marks are provided immediately upon completion.
How many questions are on the GSC Project Manager exam, and how long is it?
The exam consists of 180 multiple-choice questions. Candidates are given 3.5 hours (210 minutes) to complete the test, which is administered online with secure live proctoring.
What are the fees for Gold Seal Certification Project Manager?
As of the 2026 guidelines, the application fee is $115, the enrolment fee is $490, and the exam fee is $150 (plus applicable taxes). All fees are non-refundable.
Are there any prerequisites to write the GSC Project Manager exam?
Yes. Candidates must demonstrate at least 5 years (50 credits) of project management experience, with a minimum of 3 years working in Canada. Candidates must also complete mandatory safety, construction law, and project management courses to achieve a total of 100 GSC credits.
What topics are tested on the Gold Seal Project Manager exam?
The exam covers five core domains: Project Financials (25%), CCDC Contracts (20%), Risk Management & Legal (20%), Scheduling & Planning (20%), and Dispute Resolution & Ethics (15%).
Is the GSC Project Manager exam open book?
No. The exam is a closed-book, computer-based test written under secure online proctoring conditions from your home or office.