A West Virginia remodeling-and-repair contractor has a signed contract for USD 36,500 of kitchen work. The owner then signs a change order for a USD 5,200 bay-window addition, bringing the undertaking to USD 41,700. What is the correct licensing action?
- AProceed, because the original contract was under USD 40,000
- BProceed, because change orders do not count toward the classification limit
- CDo not perform the combined undertaking under the remodeling-and-repair classification; t…