A factory wants a USBC-exempt, DOLI-regulated process boiler set on a new pad, with fuel-train wiring, feedwater piping, and steam process piping completed in the same contract. What is the EMC-only contractor authorized to do?
- AThe complete contract, because 18VAC50-22-30 includes those boilers in EMC
- BSet and remove the boiler equipment only; electrical, plumbing, process piping, and HVAC…
- CSet the boiler and install the steam process piping, but not the fuel-train wiring
- DSet the boiler and the feedwater piping, because feedwater is part of the boiler, not pro…