Under 18VAC50-22-30, what work does Virginia Concrete Contracting (CEM) cover?
Cem Scope
Question · Easy
Divide by twenty-seven
Short
Which of the following is expressly included in the Virginia CEM specialty definition?
Besides a CEM specialty contractor, which Virginia Board for Contractors classifications also provide the concrete contracting function?
Trades Exam Prep Podcast
Listen on Spotify
Podcast
A CEM-only firm is hired to place a warehouse floor slab. Which additional task is outside CEM and requires another classification or specialty?
Which group of concrete operations is included in the Virginia CEM specialty?
Question · Medium
A specification calls for a polyethylene film vapor retarder under a slab-on-ground. How does that task fit the Virginia CEM specialty?
A customer wants a cast-in-place concrete retaining wall and a separate face of clay brick veneer. Which licensing split is correct under Virginia specialty definitions?
Which statement best describes how CEM relates to steel erection (STL) on a reinforced concrete job?
If two otherwise similar mixes differ only in water-cement ratio, which mix is expected to have higher compressive strength and lower permeability?
Mix Design
What does a slump test primarily measure on fresh concrete?
Why is intentionally entrained air used in exterior concrete exposed to freezing and thawing in the presence of moisture?
A one-cubic-yard batch contains 564 pounds of cement and 282 pounds of mixing water. What is the water-cement ratio by weight?
Question · Hard
In U.S. ready-mix practice, how much does one standard sack of portland cement weigh?
What is the primary reason to use a water-reducing admixture instead of adding extra mixing water?
A specified mix uses 564 pounds of cement per cubic yard at a water-cement ratio of 0.45. How many pounds of mixing water are required per cubic yard?
A high-range water reducer (superplasticizer) is added at the job. What is the intended effect?
On a hot Virginia afternoon, the batch plant adds a retarding admixture. What is the main purpose?
A trial batch of all mix ingredients occupies 28.35 cubic feet. Using 27 cubic feet per cubic yard, what is the yield of that batch?
Why is calcium chloride often restricted or prohibited as an accelerating admixture in reinforced concrete?
Fly ash or ground-granulated blast-furnace slag is added as a supplementary cementitious material. What is a typical field effect compared with a straight portland-cement mix at the same total cementitious content?
How does intentionally entrained air differ from entrapped air in fresh concrete?
A mix requires 282 pounds of mixing water per cubic yard. Using 8.34 pounds per gallon for water, about how many gallons of water are needed per cubic yard?
A specification calls for a 6-sack mix. How many pounds of portland cement are required per cubic yard?
A truck arrives 1 inch below the specified slump. The finishers want a hose added to the drum. What is the correct concern?
What is the basic performance requirement for concrete formwork?
Formwork Placement
Why is freshly placed concrete consolidated, usually by internal or external vibration?
What is a common result of overvibrating a placement?
What is the usual field concern with letting concrete drop freely a long distance into a wall or column form?
Which placing condition most increases lateral pressure on wall forms?
What is a cold joint in a concrete wall or slab?
When placing a tall wall in lifts, how should the vibrator be used at the lift line?
A formed wall is 8 inches thick, 10 feet high, and 40 feet long. How many cubic yards of concrete are required, using 27 cubic feet per cubic yard and no waste?
A continuous footing is 2 feet wide, 1.5 feet deep, and 48 feet long. How many cubic yards are required with no waste?
A square column is 18 inches by 18 inches and 12 feet high. How many cubic yards of concrete does one column require with no waste?
What is the main structural job of form ties in a wall form?
Why are chamfer strips commonly placed in the corners of column and wall forms?
A pump operator reports that the mix will not move without adding water at the hopper. What is the best first response that protects the specification?
During slipform work, what must not be exceeded while concrete is being placed?
What is the nominal diameter of a #4 reinforcing bar?
Reinforcement
What is the main purpose of concrete cover over reinforcing steel?
What is the proper use of bar chairs, bolsters, or concrete dobies?
For concrete cast against and permanently exposed to earth, what cover to reinforcing is commonly specified?
What is the correct conceptual rule for a lap splice of reinforcing bars?
Why are intersecting reinforcing bars tied with annealed wire?
A footing requires 60 pieces of #4 bar, each 16 feet long. Using 0.668 pounds per foot for #4 bar, what is the total steel weight?
A wall schedule calls for 36 pieces of #5 bar, each 20 feet long. Using 1.043 pounds per foot for #5 bar, what is the total steel weight?